Answer
Direct Materials = 6 x 7 = $ 42
Direct Labor = 2 x 16 = $ 32
Overhead = 2 x $ 13 = $ 26
Total = 42 + 32 + 26 = $ 100
>Total Standard Cost = 7300 units x
$ 100 = $ 730,000
>Total Actual Cost = (44300 x 7.1) + (14300 x 16.50)+196700 =
747,180
>Total Cost Variance = 747180 – 730000 = $ 17,180 Unfavourable
Actual Cost |
Standard Cost |
|||||||||
AQ |
x |
AP |
AQ |
x |
SP |
SQ |
x |
SP |
||
44,300 |
x |
$ 7.10 |
44,300 |
x |
$ 7.00 |
43,800 |
x |
$ 7.00 |
||
$ 314,530.00 |
$ 310,100.00 |
$ 306,600.00 |
||||||||
Price Variance - Material |
$ 4,430.00 |
Quantity Variance - Material |
$ 3,500.00 |
Direct material Price Variance |
$ 4,430.00 |
Unfavourable |
Direct material Quantity Variance |
$ 3,500.00 |
Unfavourable |
Total Direct material Variance |
$ 7,930.00 |
Unfavourable |
Actual Cost |
Standard Cost |
|||||||||
AH |
x |
AR |
AH |
x |
SR |
SH |
x |
SR |
||
14,300 |
x |
$ 16.50 |
14,300 |
x |
$ 16.00 |
14,600 |
x |
$ 16.00 |
||
$ 235,950.00 |
$ 228,800.00 |
$ 233,600.00 |
||||||||
Rate Variance - Labor |
$ 7,150.00 |
Efficency Variance - Labor |
$ 4,800.00 |
Labor Rate Variance |
$ 7,150.00 |
Unfavourable |
Labor Efficiency Variance |
$ 4,800.00 |
Favourable |
Total Labor Cost [Spending] Variance |
$ 2,350.00 |
Unfavourable |
Required information [The following information applies to the questions displayed below] A manufactured product has the...
Required information (The following information applies to the questions displayed below.) A manufactured product has the following information for June. Standard (7 lbs. e $7 per lb.) (2 hrs. e $16 per hr.) (2 hrs. e S$12 per hr.) Actual Direct materials Direct labor Overhead 51, 600 lbs. e S7.10 per 1b. 14, 200 hrs.e S16.50 per hr. S180, 400 7, 300 Units manufactured (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute the...
Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard 5 lbs. @ $7 per lb. 3 hrs. @ $16 per hr. 3 hrs. @ $11 per hr. Actual 43, 600 lbs. @ $7.10 per lb. 25,600 hrs. @ $16.60 per hr. $290,400 8,600 (1) Compute the standard cost per unit. (2) Compute the total cost variance for June. Complete this question...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. @ $8 per lb.) (3 hrs. @ $16 per hr.) (3 hrs. @ $12 per hr.) Actual 49,000 lbs. @ $8.10 per lb. 23,900 hrs. @ $16.50 per hr. $297,500 8,100 (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute the total cost variance...
Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (5 lbs. @ $8 per lb.) (2 hrs. @ $17 per hr.) (2 hrs. @ $12 per hr.) Actual 43,900 lbs. @ $8.10 per lb. 17,100 hrs. @ $17.40 per hr. $214,700 8,700 (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute the total cost variance...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Standard Actual Direct materials 6 lbs. @ $7 per lb. 43,700 lbs. @ $7.10 per lb. Direct labor 3 hrs. @ $16 per hr. 21,200 hrs. @ $16.50 per hr. Overhead 3 hrs. @ $13 per hr. $ 285,800 Units manufactured 7,200 Compute the direct materials price variance and the direct materials quantity variance. (Indicate the effect of each variance...
Required information [The following information applies to the questions displayed below. A manufactured product has the following information for June. Direct materials 1 Actual lbs. @ $7.20 per 9 54,400 lb. Standard (7 lbs. @ $7 per lb.) (3 hrs. @ $15 per hr.) (3 hrs. @ $12 per hr.) Direct labor Overhead Units manufactured 32 saa hrs. @ $15.50 per 22,8001 hr. $283,300 7,700 (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute...
Required Information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard Actual 6 lbs. @ $7 per lb. 54,400 en lbs. @ $7.20 per *° lb. 3 hrs. @ $16 per hr. 26,800 6 seg hrs. @ $16.50 per 3 hrs. @ $11 per hr. $303,900 9,000 Compute the direct materials price variance and the direct materials quantity variance. (Indicate the effect of...
Required information The following information applies to the questions displayed below) A manufactured product has the following information for June Standard Actual Direct materials (7 lbs. @ $7 per lb.) 58,600 lbs. @ $7.10 per lb. Direct labor (3 hrs. $15 per hr.) 24,600 hrs. $15.50 per hr. Overhead (3 hrs. 512 per hr.) $304,100 Units manufactured 8,300 Compute the direct materials price variance and the direct materials quantity variance Indicate whether each variance is favorable or unfavorable AQ -...
Required information (The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. $7 per lb.) (3 hrs. $17 per hr.) (3 hrs. @ $12 per hr.) Actual 50, 200 lbs. @ $7.10 per lb. 24,600 hrs. @ $17.50 per hr. $304,000 8,300 Compute the direct labor rate variance and the direct labor efficiency variance. Indicate whether each variance is favorable or unfavorable....
[The following information applies to the questions displayed below.] A manufactured product has the following information for June. Standard (6 lbs. @ $8 per lb.) (2 hrs. @ $16 per hr.) |(2 hrs. @ $12 per hr.) Actual 48,500 lbs. @ $8.10 per lb 15,700 hrs. @ $16.50 per hr. $198,000 8,000 Direct materials Direct labor Overhead Units manufactured (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total $ 0 (2) Compute the total cost variance...