Required information
[The following information applies to the questions
displayed below.]
A manufactured product has the following information for
June.
Standard | Actual | |||
Direct materials | 6 lbs. @ $7 per lb. | 43,700 | lbs. @ $7.10 per lb. | |
Direct labor | 3 hrs. @ $16 per hr. | 21,200 | hrs. @ $16.50 per hr. | |
Overhead | 3 hrs. @ $13 per hr. | $ | 285,800 | |
Units manufactured | 7,200 | |||
Compute the direct materials price variance and the direct
materials quantity variance. (Indicate the effect of each
variance by selecting for favorable, unfavorable, and no variance.
Round "Cost per unit" answers to 2 decimal places.)
AQ = Actual Quantity
SQ = Standard Quantity
AP = Actual Price
SP = Standard Price
|
Compute the direct labor rate variance and the direct labor
efficiency variance. (Indicate the effect of each variance
by selecting for favorable, unfavorable, and no variance. Round
"Rate per hour" answers to 2 decimal places.)
AH = Actual Hours
SH = Standard Hours
AR = Actual Rate
SR = Standard Rate
|
(A)
Material price variance = actual quantity purchased x (standard price - actual price)
= 43700 x ($7 - $7.10)
= $4370 Unfavorable
(B)
Material quantity variance = standard price x (standard quantity - actual quantity used)
= $7 x (43200 - 43700)
= $3500 Unfavorable
Where,
Standard quantity = actual output x standard quantity per unit of output
= 7200 x 6 = 43200 lbs
———————————————————
(A)
Labor rate variance = actual hours x (standard rate - actual rate)
= 21200 x ($16 - $16.50)
= $10600 Unfavorable
(B)
Labor efficiency variance = standard rate x (standard hours - actual hours)
= $16 x (21600 - 21200)
= $6400 Favorable
Where,
Standard hours = actual output x standard hours per unit of output
= 7200 x 3 = 21600 hours
Required information [The following information applies to the questions displayed below.] A manufactured product has the...
Required information [The
following information applies to the questions displayed below.] A
manufactured product has the following information for June.
Standard Actual Direct materials 5 lbs. @ $9 per lb. 40,400 lbs. @
$9.20 per lb. Direct labor 3 hrs. @ $15 per hr. 23,700 hrs. @
$15.60 per hr. Overhead 3 hrs. @ $12 per hr. $ 294,800 Units
manufactured 8,000 Compute the direct materials price variance and
the direct materials quantity variance. (Indicate the effect of
each variance...
Required Information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard Actual 6 lbs. @ $7 per lb. 54,400 en lbs. @ $7.20 per *° lb. 3 hrs. @ $16 per hr. 26,800 6 seg hrs. @ $16.50 per 3 hrs. @ $11 per hr. $303,900 9,000 Compute the direct materials price variance and the direct materials quantity variance. (Indicate the effect of...
Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June Direct materials Direct labor Overhead Units manufactured Standard 5 lbs. @ $8 per lb. 3 hrs. @ $17 per hr. 3 hrs. @ $13 per hr. Actual 42,100 lbs. @ $8.20 per lb. 24,500 hrs. @ $17.50 per hr. $329,000 8,300 Compute the direct labor rate variance and the direct labor efficiency variance. (Indicate the effect of each variance by...
Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June Direct materials Direct labor Overhead Units manufactured Standard 5 lbs. @ $8 per lb. 3 hrs. @ $17 per hr. 3 hrs. @ $13 per hr. Actual 42,100 lbs. @ $8.20 per lb. 24,500 hrs. @ $17.50 per hr. $329,000 8,300 Compute the direct materials price variance and the direct materials quantity variance. (Indicate the effect of each variance by...
Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard 5 lbs. @ $7 per lb. 3 hrs. @ $16 per hr. 3 hrs. @ $11 per hr. Actual 43, 600 lbs. @ $7.10 per lb. 25,600 hrs. @ $16.60 per hr. $290,400 8,600 (1) Compute the standard cost per unit. (2) Compute the total cost variance for June. Complete this question...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (7 lbs. @ $8 per lb.) (2 hrs. @ $15 per hr.) (2 hrs. @ $11 per hr.) Actual 55,900 lbs. @ $8.10 per lb. 15,500 hrs. @ $15.40 per hr. $179, 700 7,900 Compute the direct materials price variance and the direct materials quantity variance. Indicate whether each variance is favorable...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard 7 lbs. @ $8 per lb. 2 hrs. @ $15 per hr. 2 hrs. @ $11 per hr. Actual 61,300 lbs. @ $8.10 per lb. 17,100 hrs. @ $15.40 per hr. $ 197,500 8,700 Compute the direct materials price variance and the direct materials quantity variance. (Indicate the effect of each variance...
Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Actual Direct materials 42,100 lbs. @ $8.20 per Direct labor Standard 5 lbs. @ $8 per lb. 3 hrs. @ $17 per hr. 3 hrs. @ $13 per hr. lb. hrs. @ $17.50 per 24,500 hr. $329,000 Overhead Units manufactured 8,300 Compute the direct materials price variance and the direct materials quantity variance. (Indicate the effect of each variance by...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard 6 lbs. @ $8 per lb. 3 hrs. @ $17 per hr. 3 hrs. @ $13 per hr. Actual 43,100 lbs. @ $8.10 per lb. 21,100 hrs. @ $17.40 per hr. $282,800 7,100 Compute the direct materials price variance and the direct materials quantity variance. (Indicate the effect of each variance by...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. @ $8 per lb.) (3 hrs. @ $16 per hr.) (3 hrs. @ $12 per hr.) Actual 49,000 lbs. @ $8.10 per lb. 23,900 hrs. @ $16.50 per hr. $297,500 8,100 (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute the total cost variance...