Answer
Actual DATA for |
7700 |
units |
|
Quantity (AQ) |
Rate (AR) |
Actual Cost |
|
Direct Material |
54400 |
$ 7.20 |
$ 391,680.00 |
Direct labor |
22800 |
$ 15.50 |
$ 353,400.00 |
Variable Overhead |
22800 |
$ 12.43 |
$ 283,300.00 |
Standard DATA for |
7700 |
units |
|
Quantity (SQ) |
Rate (SR) |
Standard Cost |
|
[A] |
[B] |
[A x B] |
|
Direct Material |
( 7 lbs x 7700 units)=53900 lbs |
$ 7.00 |
$ 377,300.00 |
Direct labor |
( 3 hours x 7700 units)=23100 hours |
$ 15.00 |
$ 346,500.00 |
Variable Overhead |
( 3 hours x 7700 units)=23100 hours |
$ 12.00 |
$ 277,200.00 |
--Material
Actual Cost |
Standard Cost |
|||||||||
AQ |
x |
AP |
AQ |
x |
SP |
SQ |
x |
SP |
||
54,400 |
x |
$ 7.20 |
54,400 |
x |
$ 7.00 |
53,900 |
x |
$ 7.00 |
||
$ 391,680.00 |
$ 380,800.00 |
$ 377,300.00 |
||||||||
Price Variance - Material |
$ 10,880.00 |
Quantity Variance - Material |
$ 3,500.00 |
Direct material Price Variance |
$ 10,880.00 |
Unfavourable |
Direct material Quantity Variance |
$ 3,500.00 |
Unfavourable |
Total Direct material Variance |
$ 14,380.00 |
Unfavourable |
--Labor Cost
Actual Cost |
Standard Cost |
|||||||||
AH |
x |
AR |
AH |
x |
SR |
SH |
x |
SR |
||
22,800 |
x |
$ 15.50 |
22,800 |
x |
$ 15.00 |
23,100 |
x |
$ 15.00 |
||
$ 353,400.00 |
$ 342,000.00 |
$ 346,500.00 |
||||||||
Rate Variance - Labor |
$ 11,400.00 |
Efficency Variance - Labor |
$ 4,500.00 |
Labor Rate Variance |
$ 11,400.00 |
Unfavourable |
Labor Efficiency Variance |
$ 4,500.00 |
Favourable |
Total Labor Cost [Spending] Variance |
$ 6,900.00 |
Unfavourable |
Required information [The following information applies to the questions displayed below. A manufactured product has the...
Required Information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard Actual 6 lbs. @ $7 per lb. 54,400 en lbs. @ $7.20 per *° lb. 3 hrs. @ $16 per hr. 26,800 6 seg hrs. @ $16.50 per 3 hrs. @ $11 per hr. $303,900 9,000 Compute the direct materials price variance and the direct materials quantity variance. (Indicate the effect of...
Required information (The following information applies to the questions displayed below.] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. @ $7 per lb.) (3 hrs. @ $16 per hr.) (3 hrs. @ $12 per hr.) Actual 43,800 lbs. @ $7.20 per lb. 21,300 hrs. @ $16.40 per hr. $264,300 7,200 Compute the direct materials price variance and the direct materials quantity variance. Indicate whether each variance is favorable or...
Required information [The following information applies to the questions displayed below] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. @ $7 per lb.) (2 hrs. $16 per hr.) (2 hrs. @ $13 per hr.) Actual 44.3e9 lbs. @ $7.10 per lb. 14,300 hrs. $16.50 per hr. $196,700 7,300 (1) Compute the standard cost per unit Direct materials Direct labor Overhead Total (2) Compute the total cost variance for June,...
Required information The following information applies to the questions displayed below) A manufactured product has the following information for June Standard Actual Direct materials (7 lbs. @ $7 per lb.) 58,600 lbs. @ $7.10 per lb. Direct labor (3 hrs. $15 per hr.) 24,600 hrs. $15.50 per hr. Overhead (3 hrs. 512 per hr.) $304,100 Units manufactured 8,300 Compute the direct materials price variance and the direct materials quantity variance Indicate whether each variance is favorable or unfavorable AQ -...
Required information The following information applies to the questions displayed below) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (7 lbs. @ $7 per lb.) (3 hrs. @ $15 per hr.) (3 hrs. $12 per hr.) Actual 58,600 lbs. 57.10 per lb. 24,600 hrs. @ $15.50 per hr. $384,100 8,300 Compute the direct labor rate variance and the direct labor efficiency variance Indicate whether each variance is favorable or unfavorable. AH...
Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (5 lbs. @ $8 per lb.) (2 hrs. @ $17 per hr.) (2 hrs. @ $12 per hr.) Actual 43,900 lbs. @ $8.10 per lb. 17,100 hrs. @ $17.40 per hr. $214,700 8,700 (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute the total cost variance...
Required information (The following information applies to the questions displayed below.) A manufactured product has the following information for June. Standard (7 lbs. e $7 per lb.) (2 hrs. e $16 per hr.) (2 hrs. e S$12 per hr.) Actual Direct materials Direct labor Overhead 51, 600 lbs. e S7.10 per 1b. 14, 200 hrs.e S16.50 per hr. S180, 400 7, 300 Units manufactured (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute the...
Required information [The following information applies to the questions displayed below] A manufactured product has the following information for June. Standard Actual Direct materials Direct labor Overhead (6 lbs. $7 per 1b.) (2 hrs. $17 per hr.) (2 hrs. $11 per hr.) 48,000 lbs.e $7.20 per 1b. 15,5ee hrs.@ $17.50 per hr. $179,4e0 7,900 Units manufactured Compute the direct materials price variance and the direct materials quantity variance. Indicate whether each variance is favorable or unfavorable. AQ= Actual Quantity SQ-...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (7 lbs. @ $8 per lb.) (2 hrs. @ $15 per hr.) (2 hrs. @ $11 per hr.) Actual 55,900 lbs. @ $8.10 per lb. 15,500 hrs. @ $15.40 per hr. $179, 700 7,900 Compute the direct materials price variance and the direct materials quantity variance. Indicate whether each variance is favorable...
Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard 5 lbs. @ $7 per lb. 3 hrs. @ $16 per hr. 3 hrs. @ $11 per hr. Actual 43, 600 lbs. @ $7.10 per lb. 25,600 hrs. @ $16.60 per hr. $290,400 8,600 (1) Compute the standard cost per unit. (2) Compute the total cost variance for June. Complete this question...