Required information The following information applies to the questions displayed below) A manufactured product has the follo
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Actual Cost Standard cost
AQ AP AQ*AP AQ SP AQ*SP SQ SP SQ*SP
58600 7.10 416060 58600 7 410200 58100 7 406700
5860 3500
Material price variance 5860 Unfavorable
Material quantity variance 3500 Unfavorable
Total material variance 9360 Unfavorable
Add a comment
Know the answer?
Add Answer to:
Required information The following information applies to the questions displayed below) A manufactured product has the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information The following Information applies to the questions displayed below.] A manufactured product has the...

    Required information The following Information applies to the questions displayed below.] A manufactured product has the following Information for June Direct eaterials Direct labor (6 lbs. e $7 per lb.) (2 hrs. e $15 per hr.) (2 hrs. e $13 per hr.) 46, 800 lbs. $7.10 per 1b 15, 100 hrs. $15.50 per hr $206, 800 Units sanufactured 7,700 Compute the direct materials price variance and the direct materials quantity varlance. Indicate whether each varlance is favorable or AQ Actual...

  • Required information [The following information applies to the questions displayed below.) A manufactured product has the...

    Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. @ $7 per lb.) (2 hrs. @ $15 per hr.) (2 hrs. @ $12 per hr.) Actual 43,600 lbs. @ $7.10 per lb. 14,000 hrs. @ $15.40 per hr. $179,700 7,200 AQ = Actual Quantity SQ = Standard Quantity AP = Actual Price SP = Standard Price Compute the direct...

  • Required information [The following information applies to the questions displayed below.) A manufactured product has the...

    Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June Direct materials Direct labor Overhead Units manufactured Standard 5 lbs. @ $8 per lb. 3 hrs. @ $17 per hr. 3 hrs. @ $13 per hr. Actual 42,100 lbs. @ $8.20 per lb. 24,500 hrs. @ $17.50 per hr. $329,000 8,300 Compute the direct materials price variance and the direct materials quantity variance. (Indicate the effect of each variance by...

  • Required information [The following information applies to the questions displayed below.) A manufactured product has t...

    Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June Direct materials Direct labor Overhead Units manufactured Standard 5 lbs. @ $8 per lb. 3 hrs. @ $17 per hr. 3 hrs. @ $13 per hr. Actual 42,100 lbs. @ $8.20 per lb. 24,500 hrs. @ $17.50 per hr. $329,000 8,300 Compute the direct materials price variance and the direct materials quantity variance. (Indicate the effect of each variance by...

  • Required information The following information applies to the questions displayed below] A manufactured product has the...

    Required information The following information applies to the questions displayed below] A manufactured product has the following information for June Standard (7 lbs. $7 per 1b.) (3 hrs.@ $15 per hr.) (3 hrs. $12 per hr.) Actual 58,600 lbs. $7.10 per 1b. 24,600 hrs. @$15.5e per hr. $ 304,100 8,300 Direct materials Direct labor Overhead Units manufactured (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute the total cost variance for June. Indicate whether...

  • Required information [The following information applies to the questions displayed below.) A manufactured product has the...

    Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Actual Direct materials 42,100 lbs. @ $8.20 per Direct labor Standard 5 lbs. @ $8 per lb. 3 hrs. @ $17 per hr. 3 hrs. @ $13 per hr. lb. hrs. @ $17.50 per 24,500 hr. $329,000 Overhead Units manufactured 8,300 Compute the direct materials price variance and the direct materials quantity variance. (Indicate the effect of each variance by...

  • Required information [The following information applies to the questions displayed below.] A manufactured product has the...

    Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Standard Actual Direct materials 5 lbs. @ $9 per lb. 40,400 lbs. @ $9.20 per lb. Direct labor 3 hrs. @ $15 per hr. 23,700 hrs. @ $15.60 per hr. Overhead 3 hrs. @ $12 per hr. $ 294,800 Units manufactured 8,000 Compute the direct materials price variance and the direct materials quantity variance. (Indicate the effect of each variance...

  • Required information (The following information applies to the questions displayed below.) A manufactured product has the...

    Required information (The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (7 lbs. @ $9 per lb.) (3 hrs. @ $16 per hr.) (3 hrs. @$12 per hr.) Actual 62,000 lbs. @ $9.20 per lb. 26,000 hrs. @ $16.50 per hr. $323,000 8,800 Compute the direct materials price variance and the direct materials quantity variance. Indicate whether each variance is favorable or unfavorable....

  • Required information [The following information applies to the questions displayed below] A manufactured product has the...

    Required information [The following information applies to the questions displayed below] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. @ $7 per lb.) (2 hrs. $16 per hr.) (2 hrs. @ $13 per hr.) Actual 44.3e9 lbs. @ $7.10 per lb. 14,300 hrs. $16.50 per hr. $196,700 7,300 (1) Compute the standard cost per unit Direct materials Direct labor Overhead Total (2) Compute the total cost variance for June,...

  • Required information The following information applies to the questions displayed below) A manufactured product has...

    Required information The following information applies to the questions displayed below) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (7 lbs. @ $7 per lb.) (3 hrs. @ $15 per hr.) (3 hrs. $12 per hr.) Actual 58,600 lbs. 57.10 per lb. 24,600 hrs. @ $15.50 per hr. $384,100 8,300 Compute the direct labor rate variance and the direct labor efficiency variance Indicate whether each variance is favorable or unfavorable. AH...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT