(1) Standard cost per unit is given by:
Direct materials per unit :7 lbs @ $7 per lb = $49
Direct labor per unit: 3 hrs @ $15 per hour = $45
Overhead per unit : 3 hrs @ $12 per hour = $36
Standard cost per unit = Direct material per unit + Direct labor per unit + Overhead per unit
Standard cost per unit = $49 + $45 + $36 = $130 per unit
(2) For total cost variance, we need to find the standard cost and actual cost as per below:
Standard cost = Standard cost per unit * No. of units
where, standard cost = $130 per unit (as calculated in previous step (a)), No. of units = 8300
Putting the values in the above equation, we get,
Standard cost = $130 * 8300 = $1079000
Calculation of actual cost:
Direct materials: 58600 lbs @ $7.10 per lb = $416060
Direct labor: 24600 hrs @ $15.50 per hour = $381300
Overhead: $304100
Actual cost = Direct material + Direct labor + Overhead
Actual cost = $416060 + $381300 + $304100 = $1101460
Now, we will calculate total cost variance as below:
Total cost variance = Standard cost - Actual cost
Putting the values in the above equation, we get,
Total cost variance = $1079000 - $1101460 = - $22460
Since the variance is negative, so it is an unfavorable variance.
Required information The following information applies to the questions displayed below] A manufactured product has the...
Required information The following information applies to the questions displayed below) A manufactured product has the following information for June Standard Actual Direct materials (7 lbs. @ $7 per lb.) 58,600 lbs. @ $7.10 per lb. Direct labor (3 hrs. $15 per hr.) 24,600 hrs. $15.50 per hr. Overhead (3 hrs. 512 per hr.) $304,100 Units manufactured 8,300 Compute the direct materials price variance and the direct materials quantity variance Indicate whether each variance is favorable or unfavorable AQ -...
Required information The following information applies to the questions displayed below) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (7 lbs. @ $7 per lb.) (3 hrs. @ $15 per hr.) (3 hrs. $12 per hr.) Actual 58,600 lbs. 57.10 per lb. 24,600 hrs. @ $15.50 per hr. $384,100 8,300 Compute the direct labor rate variance and the direct labor efficiency variance Indicate whether each variance is favorable or unfavorable. AH...
Required information (The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. $7 per lb.) (3 hrs. $17 per hr.) (3 hrs. @ $12 per hr.) Actual 50, 200 lbs. @ $7.10 per lb. 24,600 hrs. @ $17.50 per hr. $304,000 8,300 Compute the direct labor rate variance and the direct labor efficiency variance. Indicate whether each variance is favorable or unfavorable....
Required information [The following information applies to the questions displayed below] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. @ $7 per lb.) (2 hrs. $16 per hr.) (2 hrs. @ $13 per hr.) Actual 44.3e9 lbs. @ $7.10 per lb. 14,300 hrs. $16.50 per hr. $196,700 7,300 (1) Compute the standard cost per unit Direct materials Direct labor Overhead Total (2) Compute the total cost variance for June,...
Required information [The following information applies to the questions displayed below. A manufactured product has the following information for June. Direct materials 1 Actual lbs. @ $7.20 per 9 54,400 lb. Standard (7 lbs. @ $7 per lb.) (3 hrs. @ $15 per hr.) (3 hrs. @ $12 per hr.) Direct labor Overhead Units manufactured 32 saa hrs. @ $15.50 per 22,8001 hr. $283,300 7,700 (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute...
Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard 5 lbs. @ $7 per lb. 3 hrs. @ $16 per hr. 3 hrs. @ $11 per hr. Actual 43, 600 lbs. @ $7.10 per lb. 25,600 hrs. @ $16.60 per hr. $290,400 8,600 (1) Compute the standard cost per unit. (2) Compute the total cost variance for June. Complete this question...
Required information (The following information applies to the questions displayed below.) A manufactured product has the following information for June. Standard (7 lbs. e $7 per lb.) (2 hrs. e $16 per hr.) (2 hrs. e S$12 per hr.) Actual Direct materials Direct labor Overhead 51, 600 lbs. e S7.10 per 1b. 14, 200 hrs.e S16.50 per hr. S180, 400 7, 300 Units manufactured (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute the...
Help Sav Required information The following information applies to the questions displayed below.) A manufactured product has the following information for June Direct materials Direct labor Overhead Units manufactured Standard (5 lbs. $7 per lb.) (2 hrs. $16 per hr.) (2 hen. $12 per hr.) Actual 40,400 lbs. $7.10 per lb. 15,800 hrs. $16.60 per hr. $198.000 8.000 (1) Compute the standard cost per unit Direct materials Direct labor Overhead Total (2) Compute the total cost variance for June, Indicate...
Required information [The following information applies to the questions displayed below] A manufactured product has the following information for June. Standard Actual Direct materials Direct labor Overhead (6 lbs. $7 per 1b.) (2 hrs. $17 per hr.) (2 hrs. $11 per hr.) 48,000 lbs.e $7.20 per 1b. 15,5ee hrs.@ $17.50 per hr. $179,4e0 7,900 Units manufactured Compute the direct materials price variance and the direct materials quantity variance. Indicate whether each variance is favorable or unfavorable. AQ= Actual Quantity SQ-...
Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (5 lbs. @ $8 per lb.) (2 hrs. @ $17 per hr.) (2 hrs. @ $12 per hr.) Actual 43,900 lbs. @ $8.10 per lb. 17,100 hrs. @ $17.40 per hr. $214,700 8,700 (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute the total cost variance...