first we need to find out average accumulated expenditures for 2003.
expenditures | ||
accumulated expenditures of 2015 (530,000+26,500) | 556,500*9 months / 9 months | 556,500 |
expenditure incurred on feb 28 | 83,700*7 months / 9 months | 65,100 |
expenditure incurred on apr 30 | 173,700*5 months / 9 months | 96,500 |
expenditure incurred on july 1 | 29,700 * 3 months /9 months | 9,900 |
expenditure incurred on sept 30 | 57,700*0/9 months | 0 |
average accumulated expenditure | 728,000 |
interest capitalised in 2016 = 728,000*8%*9/12
=>$43,680.
Completed cost of library => 530,000+26,500+83,700+173,700+29,700+57,700+43,680
=>$944,980.
Montgomery Industries spent $530,000 in 2015 on a construction project to build a library. Montgomery also...
5. Montgomery Industries spent $590,000 in 2017 on a construction project to build a library. Montgomery also capitalized $29,500 of interest on the project in 2017. Montgomery financed 100% of the construction with a 8% construction loan. The project was completed on September 30, 2018. Additional expenditures in 2018 were as follows: Feb. 28 $ 89,100 Apr. 30 179,100 Jul. 1 35,100 Sept. 30 63,100 Required: Determine the completed cost of the library.
actice final exam Saved Montgomery Industries spent $660,000 in 2015 on a construction project to build a Montgomery also capitalized $33,000 of interest on the project in 2015. Montgomey man ced 100% ofthe construction with a 10% construction loan. The project was completed on September 30, 2016. Additional expenditures in 2016 were as follows: Feb. 28 Apr. 30 Jul. 1 Sept. 30 $95,400 185,400 41400 69,400 Required: Determine the completed cost of the library. (Do not round intermediate calculations.) cost...
18.A construction company was hired on a construction project to build a building for $1,800,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2015 2016 Costs incurred during the year $450,000 $1,100,000 Estimated costs to complete 1,050,000 0 Billing during the year 400,000 1,400,000 Cash collections during the year 300,000 1,500,000 Assume that A recognizes revenue on this contract over time according to percentage of completion. Required: Prepare all journal entries...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 8% note $9,000, 800, 4% bonds Construction expenditures incurred were as follows: July 1, 2018 September 30, 2018 November 30, 2018 January 30, 2019 $ 48e, eae 720,899 720.99 660,800 120,00€ The company's fiscal year-end is December...
Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 12% note $7,000,000, 7% bonds Construction expenditures incurred were as follows: July 1, 2021 $ 700,000 September 30, 2021 990,000 November 30, 2021 990,000 January 30, 2022 930,000 The company’s fiscal year-end is December 31. Required: Calculate...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 7% note $8,000,000, 34 bonds Construction expenditures incurred were as follows: July 1, 2018 September 30, 2018 November 30, 2018 January 30, 2019 $ 340,000 690,000 690,000 630,000 The company's fiscal year-end is December 31. Required: Calculate...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 6% note $5,000,000, 2% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 540,000 September 30, 2018 750,000 November 30, 2018 750,000 January 30, 2019 690,000 The company’s fiscal year-end is December 31. Required: Calculate...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 8% note $5,000,000, 4% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 660,000 September 30, 2018 930,000 November 30, 2018 930,000 January 30, 2019 870,000 The company’s fiscal year-end is December 31. Required: Calculate...
Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $4,000,000, 10% note $6,000,000, 5* bonds Construction expenditures incurred were as follows: July 1, 2021 September 30, 2021 November 30, 2021 $ 640,000 960,000 960,000 900,000 January 30, 2022 The company's fiscal year-end is December 31. Required: Calculate...
Keiron Industries began construction of a warehouse on July 1, year 1. The project was completed on March 31, year 2. No new loans were required to fund construction. Keiron does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 10% note $7,000,000, 5% bonds Construction expenditures incurred were as follows: July 1, year 1 September 30, year 1 November 30, year 1 January 30, year 2 $500,000 600,000 400,000 550,000 The company's fiscal year-end...