Question

Montgomery Industries spent $530,000 in 2015 on a construction project to build a library. Montgomery also capitalized $26,50

0 0
Add a comment Improve this question Transcribed image text
Answer #1

first we need to find out average accumulated expenditures for 2003.

expenditures
accumulated expenditures of 2015 (530,000+26,500) 556,500*9 months / 9 months 556,500
expenditure incurred on feb 28 83,700*7 months / 9 months 65,100
expenditure incurred on apr 30 173,700*5 months / 9 months 96,500
expenditure incurred on july 1 29,700 * 3 months /9 months 9,900
expenditure incurred on sept 30 57,700*0/9 months 0
average accumulated expenditure 728,000

interest capitalised in 2016 = 728,000*8%*9/12

=>$43,680.

Completed cost of library => 530,000+26,500+83,700+173,700+29,700+57,700+43,680

=>$944,980.

Add a comment
Know the answer?
Add Answer to:
Montgomery Industries spent $530,000 in 2015 on a construction project to build a library. Montgomery also...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 5. Montgomery Industries spent $590,000 in 2017 on a construction project to build a library. Montgomery...

    5. Montgomery Industries spent $590,000 in 2017 on a construction project to build a library. Montgomery also capitalized $29,500 of interest on the project in 2017. Montgomery financed 100% of the construction with a 8% construction loan. The project was completed on September 30, 2018. Additional expenditures in 2018 were as follows: Feb. 28 $ 89,100 Apr. 30 179,100 Jul. 1 35,100 Sept. 30 63,100 Required: Determine the completed cost of the library.

  • actice final exam Saved Montgomery Industries spent $660,000 in 2015 on a construction project to build...

    actice final exam Saved Montgomery Industries spent $660,000 in 2015 on a construction project to build a Montgomery also capitalized $33,000 of interest on the project in 2015. Montgomey man ced 100% ofthe construction with a 10% construction loan. The project was completed on September 30, 2016. Additional expenditures in 2016 were as follows: Feb. 28 Apr. 30 Jul. 1 Sept. 30 $95,400 185,400 41400 69,400 Required: Determine the completed cost of the library. (Do not round intermediate calculations.) cost...

  • 18.A construction company was hired on a construction project to build a building for $1,800,000. The...

    18.A construction company was hired on a construction project to build a building for $1,800,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2015 2016 Costs incurred during the year $450,000 $1,100,000 Estimated costs to complete 1,050,000 0 Billing during the year 400,000 1,400,000 Cash collections during the year 300,000 1,500,000 Assume that A recognizes revenue on this contract over time according to percentage of completion. Required: Prepare all journal entries...

  • Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 8% note $9,000, 800, 4% bonds Construction expenditures incurred were as follows: July 1, 2018 September 30, 2018 November 30, 2018 January 30, 2019 $ 48e, eae 720,899 720.99 660,800 120,00€ The company's fiscal year-end is December...

  • Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 12% note $7,000,000, 7% bonds Construction expenditures incurred were as follows: July 1, 2021 $ 700,000 September 30, 2021 990,000 November 30, 2021 990,000 January 30, 2022 930,000 The company’s fiscal year-end is December 31. Required: Calculate...

  • Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 7% note $8,000,000, 34 bonds Construction expenditures incurred were as follows: July 1, 2018 September 30, 2018 November 30, 2018 January 30, 2019 $ 340,000 690,000 690,000 630,000 The company's fiscal year-end is December 31. Required: Calculate...

  • Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 6% note $5,000,000, 2% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 540,000 September 30, 2018 750,000 November 30, 2018 750,000 January 30, 2019 690,000 The company’s fiscal year-end is December 31. Required: Calculate...

  • Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 8% note $5,000,000, 4% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 660,000 September 30, 2018 930,000 November 30, 2018 930,000 January 30, 2019 870,000 The company’s fiscal year-end is December 31. Required: Calculate...

  • Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $4,000,000, 10% note $6,000,000, 5* bonds Construction expenditures incurred were as follows: July 1, 2021 September 30, 2021 November 30, 2021 $ 640,000 960,000 960,000 900,000 January 30, 2022 The company's fiscal year-end is December 31. Required: Calculate...

  • Keiron Industries began construction of a warehouse on July 1, year 1. The project was completed...

    Keiron Industries began construction of a warehouse on July 1, year 1. The project was completed on March 31, year 2. No new loans were required to fund construction. Keiron does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 10% note $7,000,000, 5% bonds Construction expenditures incurred were as follows: July 1, year 1 September 30, year 1 November 30, year 1 January 30, year 2 $500,000 600,000 400,000 550,000 The company's fiscal year-end...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT