Question

18.A construction company was hired on a construction project to build a building for $1,800,000. The...

18.A construction company was hired on a construction project to build a building for $1,800,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below:

2015

2016

Costs incurred during the year

$450,000

$1,100,000

Estimated costs to complete

1,050,000

0

Billing during the year

400,000

1,400,000

Cash collections during the year

300,000

1,500,000

Assume that A recognizes revenue on this contract over time according to percentage of completion.

Required:

Prepare all journal entries to record costs, billings, collections, and profit recognition.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Journal entries
2015 2016
Debit Credit Debit Credit
Construction in progress $              450,000 $           1,100,000
   Various accounts $              450,000 $        1,100,000
Accounts receivable $              400,000 $           1,400,000
   Billings on construction contract $              400,000 $        1,400,000
Cash $              300,000 $           1,500,000
Accounts receivable $              300,000 $        1,500,000
Construction In progress $                 90,000 $              160,000
Cost of construction $              450,000 $           1,100,000
Revenue from long term contracts $              540,000 $        1,260,000
2014 2015
Contract price $           1,800,000 $           1,800,000
Actual costs to date $              450,000 $           1,550,000
Estimated costs $           1,050,000 $                          -  
total estimated costs $           1,500,000 $           1,550,000
Estimated gross profit (loss) $              300,000 $              250,000
revenue recognition
2014:(450000/1500000)= 30%
30%*1800000= $              540,000
2015= 100%
1800000-540000 $           1,260,000
Add a comment
Know the answer?
Add Answer to:
18.A construction company was hired on a construction project to build a building for $1,800,000. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Beavis Construction Company was the low bidder on a construction project to build an earthen dam...

    Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below. $ Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2017 2018 450,000 $1,100,000 1,050,000 400,000 1,400,000 300,000 1,500,000 Assume that Beavis recognizes revenue upon completion of the project. Required: Compute the amount of gross profit...

  • Davis Construction company was a low bidder on a construction project to build and earthen dam...

    Davis Construction company was a low bidder on a construction project to build and earthen dam for $2,000,000. The project was begun in 2017. Cost and other are presented bellow. 2017 2018 Costs incurred during the year $450,000 $1,100,000 Total costs 1,050,000 50,000 Percentage of completion 30%   96.875% Billings during the year 500,000 1,400,000 Cash collections during the year 400,000 1,400,000 Assume the Beavis recognizes revenue on the contract over time according to percentage of completion Required 1. Compute the...

  • Davis Construction company was a low bidder on a construction project to build and earthen dam...

    Davis Construction company was a low bidder on a construction project to build and earthen dam for $2,000,000. The project was begun in 2017. Cost and other are presented bellow. 2017 2018 Costs incurred during the year $450,000 $1,100,000 Total costs 1,050,000 50,000 Percentage of completion 30%   96.875% Billings during the year 500,000 1,400,000 Cash collections during the year 400,000 1,400,000 Assume the Beavis recognizes revenue on the contract over time according to percentage of completion Required 1. Compute the...

  • Required information SB Problem The following information applies to the questions displayed below.) Beavis Constru...

    Required information SB Problem The following information applies to the questions displayed below.) Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below. Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2017 2018 $ 450,000 $1,108, eee 1,050,000 400,000 1,400,000 300,000 1,500,000 Problem 5-284 Assume...

  • Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,810,000. The pr...

    Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,810,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2020 $ 447,000 $1,110,000 1,043,000 405,000 1,405,000 305,000 1,505,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Required: Prepare all...

  • Beavis Construction Company was the low bidder on a construction project to build an earthen dam...

    Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,890,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below: 2017 2018 Costs incurred during the year $ 423,000 $ 1,190,000 Estimated costs to complete 987,000 0 Billings during the year 445,000 1,445,000 Cash collections during the year 345,000 1,545,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....

  • 1) Wind and Water Energy Company hired Smith Construction Corporation to build a new building for...

    1) Wind and Water Energy Company hired Smith Construction Corporation to build a new building for its operation. Smith agreed to build the plant for $1,200,000, and Wind and Water Energy agreed to pay Smith $300,000 on January 1 and July 1 for two years, beginning July, 2006. Smith estimates that it will incur total costs of $950,000 to complete construction. The following details at December 31, 2006: Costs incurred to date $400,000   Estimated costs to complete     550,000 Billings...

  • Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1780,000. T...

    Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1780,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2020 2021 $458,500 $1,080,000 851,500 495.000 1.285.000 395,000 1,385,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Required: Prepare all...

  • Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the...

    Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,750,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below: 2017 2018 Costs incurred during the year $ 469,000 $ 1,050,000 Estimated costs to complete 871,000 0 Billings during the year 480,000 1,270,000 Cash collections during the year 380,000 1,425,000 Assume that Beavis recognizes...

  • McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun...

    McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun in 2023 and completed in 2024. Cost and other data are presented below: 2024 $1,300 Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2023 $1,500 1,200 1,200 1,000 1,300 1,500 1. Compute the amount of revenue and gross profit recognized during 2023 and 2024. 2. Assume that McCombs recognizes revenue on this contract over...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT