Question

5. Montgomery Industries spent $590,000 in 2017 on a construction project to build a library. Montgomery...

5. Montgomery Industries spent $590,000 in 2017 on a construction project to build a library. Montgomery also capitalized $29,500 of interest on the project in 2017. Montgomery financed 100% of the construction with a 8% construction loan. The project was completed on September 30, 2018. Additional expenditures in 2018 were as follows: Feb. 28 $ 89,100 Apr. 30 179,100 Jul. 1 35,100 Sept. 30 63,100 Required: Determine the completed cost of the library.

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
5. Montgomery Industries spent $590,000 in 2017 on a construction project to build a library. Montgomery...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Montgomery Industries spent $530,000 in 2015 on a construction project to build a library. Montgomery also...

    Montgomery Industries spent $530,000 in 2015 on a construction project to build a library. Montgomery also capitalized $26,500 of interest on the project in 2015. Montgomery financed 100% of the construction with a 8% construction loan. The project was completed on September 30, 2016. Additional expenditures in 2016 were as follows: Feb. 28 Apr. 30 Jul. 1 Sept. 30 $ 83,700 173,700 29,700 57,700 Required: Determine the completed cost of the library. (Do not round intermediate calculations.) Completed cost of...

  • actice final exam Saved Montgomery Industries spent $660,000 in 2015 on a construction project to build...

    actice final exam Saved Montgomery Industries spent $660,000 in 2015 on a construction project to build a Montgomery also capitalized $33,000 of interest on the project in 2015. Montgomey man ced 100% ofthe construction with a 10% construction loan. The project was completed on September 30, 2016. Additional expenditures in 2016 were as follows: Feb. 28 Apr. 30 Jul. 1 Sept. 30 $95,400 185,400 41400 69,400 Required: Determine the completed cost of the library. (Do not round intermediate calculations.) cost...

  • Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 8% note $9,000, 800, 4% bonds Construction expenditures incurred were as follows: July 1, 2018 September 30, 2018 November 30, 2018 January 30, 2019 $ 48e, eae 720,899 720.99 660,800 120,00€ The company's fiscal year-end is December...

  • Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 7% note $8,000,000, 34 bonds Construction expenditures incurred were as follows: July 1, 2018 September 30, 2018 November 30, 2018 January 30, 2019 $ 340,000 690,000 690,000 630,000 The company's fiscal year-end is December 31. Required: Calculate...

  • Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 6% note $5,000,000, 2% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 540,000 September 30, 2018 750,000 November 30, 2018 750,000 January 30, 2019 690,000 The company’s fiscal year-end is December 31. Required: Calculate...

  • Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 8% note $5,000,000, 4% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 660,000 September 30, 2018 930,000 November 30, 2018 930,000 January 30, 2019 870,000 The company’s fiscal year-end is December 31. Required: Calculate...

  • Hart began construction of a new building last year on July 1, 2017. On the day...

    Hart began construction of a new building last year on July 1, 2017. On the day construction was started, the land was appraised at $350,000. It had been purchased 2 years earfier for $200,000. By Dec. 31, 2017 it had spent $600,000 on construction and correctly paid and capitalized interest in the amount of $32,000. The following added expenditures were made in 2018 prior to completion of the building on September 1, 2018: Date Amount Feb. 1, 2018 Aug.1, 2018...

  • Hart began construction of a new building last year on July 1, 2017. On the day...

    Hart began construction of a new building last year on July 1, 2017. On the day construction was started, the land was appraised at $350,000. It had been purchased 2 years earlier for $200,000. By Dec. 31, 2017 it had spent $600,000 on construction and correctly paid and capitalized interest in the amount of $32,000. The following added expenditures were made in 2018 prior to completion of the building on September 1, 2018: Date Amount Feb. 1, 2018 840,000 Aug.1,...

  • Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 12% note $7,000,000, 7% bonds Construction expenditures incurred were as follows: July 1, 2021 $ 700,000 September 30, 2021 990,000 November 30, 2021 990,000 January 30, 2022 930,000 The company’s fiscal year-end is December 31. Required: Calculate...

  • Exercise 10-25 Interest capitalization; multiple periods [LO10-7] Thornton Industries began construction of a...

    Exercise 10-25 Interest capitalization; multiple periods [LO10-7] Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest- bearing liabilities that were outstanding throughout the construction period: $4,000,000, 9% note $6,000,000, 68 bonds Construction expenditures incurred were as follows: $ 430,000 630,000 630,000 570,000 July 1, 2018 September 30, 2018 November 30, 2018 January 30, 2019 The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT