a | Out standing loan 1 9% | $4,000,000 | ||
b | Out standing loan 2 6 % | $6,000,000 | ||
c | Total loana+b) | $10,000,000 | ||
Amount of interest in 2018 during construction perios | ||||
d | On Loan 1 (a*9%) | $360,000 | ||
e | On Loan 2 (b*6% | $360,000 | ||
f | Total Capitalizable interest | $720,000 | ||
Average interest rate f/c*100 | 7.2% | |||
Expenditures incurred | For 2018 | |||
Date | Amount | Capitalizable Interest (Amount *average interest rate* period left till the end of the year/12 | Capitalization period | |
1-Jul | $430,000 | $15,480 | For 6 months | |
30-Sep | $630,000 | $11,340 | For 3 months | |
30-Nov | $630,000 | $7,560 | For two months | |
Total capitlaizable interest for 2018 | $34,380 | |||
For 2019 | ||||
Date | Amount | Capitalizable Interest (Amount *average interest rate* period left till the end of the year/12 | ||
Cumulative amount incurred for previous year | $1,690,000 | $121,680 | For 12 months | |
30-Jan | $570,000 | $37,620 | For 11 months | |
Total capitlaizable interest for 2019 | $159,300 |
Exercise 10-25 Interest capitalization; multiple periods [LO10-7] Thornton Industries began construction of a...
Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $4,000,000, 9% note $6,000,000, 6% bonds Construction expenditures incurred were as follows: July 1, 2021 $ 430,000 September 30, 2021 630,000 November 30, 2021 630,000 January 30, 2022 570,000 The company’s fiscal year-end is December 31. Required: Calculate...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 7% note $8,000,000, 34 bonds Construction expenditures incurred were as follows: July 1, 2018 September 30, 2018 November 30, 2018 January 30, 2019 $ 340,000 690,000 690,000 630,000 The company's fiscal year-end is December 31. Required: Calculate...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 6% note $5,000,000, 2% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 540,000 September 30, 2018 750,000 November 30, 2018 750,000 January 30, 2019 690,000 The company’s fiscal year-end is December 31. Required: Calculate...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 8% note $5,000,000, 4% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 660,000 September 30, 2018 930,000 November 30, 2018 930,000 January 30, 2019 870,000 The company’s fiscal year-end is December 31. Required: Calculate...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 8% note $9,000, 800, 4% bonds Construction expenditures incurred were as follows: July 1, 2018 September 30, 2018 November 30, 2018 January 30, 2019 $ 48e, eae 720,899 720.99 660,800 120,00€ The company's fiscal year-end is December...
Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $4,000,000, 10% note $6,000,000, 5* bonds Construction expenditures incurred were as follows: July 1, 2021 September 30, 2021 November 30, 2021 $ 640,000 960,000 960,000 900,000 January 30, 2022 The company's fiscal year-end is December 31. Required: Calculate...
Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 12% note $7,000,000, 7% bonds Construction expenditures incurred were as follows: July 1, 2021 $ 700,000 September 30, 2021 990,000 November 30, 2021 990,000 January 30, 2022 930,000 The company’s fiscal year-end is December 31. Required: Calculate...
Exercise 10-22 Interest capitalization (LO10-7] On January 1, 2018, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2019. Construction expenditures for 2018, which were incurred evenly throughout the year, totaled $7,200,000. Marjlee had the following debt obligations which were outstanding during all of 2018 Construction loan, 116 Long-term note, 101 Long-term note, 73 $1.300.000 2.400,000 4.500.000 Required: Calculate the amount of interest capitalized in 2018 for...
Exercise 10-22 Interest capitalization [LO10-7] On January 1, 2018, the Marjlee Company began construction of an office building to be used as its corporate headquarters. The building was completed early in 2019. Construction expenditures for 2018, which were incurred evenly throughout the year, totaled $5,400,000. Marjlee had the following debt obligations which were outstanding during all of 2018: Construction loan, 12% $ 1,350,000 Long-term note, 11% 1,800,000 Long-term note, 8% 3,600,000 Required: Calculate the amount of interest capitalized in 2018...
Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 8% note $8,000,000, 4% bonds Construction expenditures incurred were as follows: July 1, 2021 September 30, 2021 November 30, 2021 January 30, 2022 $ 400,000 600,000 600,000 540,000 The company's fiscal year-end is December 31. Required: Calculate...