Question

please answer all questions: 1-independent projects: a) dont compete with each other b)do compete with each...

please answer all questions:

1-independent projects:
a) dont compete with each other
b)do compete with each other
c) can be mutually exclusive under certain condition
d) always have negative NPVs

2- the hurdle rate is:
a) the number of years required to get the initial investment in the payback period
b) the IRR
c)the NPV
d) the required rate of return

3- you get a 25 year loan of $150000 with an 8% annual interest rate what are the annual payments?
a) $14042
b)$2052
c)$13965
d)$13427
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1.The answer is b) do compete with each other

Independent projects do not affect the other projects of the firm and hence can be completed against each other

2.d)required rate of return

NPV = present value of cash inflows- present value of cash outflows

IRR is the rate at which NPV is equal to zero

3. Annual payment = amount of loan/Present value annuity factor

= 150,000/PVAF(8%, 25 periods)

=150,000/10.67477

=$14051.8

I.e. $14042 approx.

Add a comment
Know the answer?
Add Answer to:
please answer all questions: 1-independent projects: a) dont compete with each other b)do compete with each...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Which of the following statements is INCORRECT? Select one: a. For independent projects, the decision to...

    Which of the following statements is INCORRECT? Select one: a. For independent projects, the decision to accept or reject will always be the same using either the MIRR method or the NPV method. b. The IRR method is appealing to some managers because it produces a rate of return upon which to base decisions rather than a dollar amount like the NPV method. c. One of the disadvantages of choosing between mutually exclusive projects on the basis of discounted payback...

  • Show all work and highlight final answer. Do not answer the question unless you answer all...

    Show all work and highlight final answer. Do not answer the question unless you answer all of them. 4. Which one of the following will decrease the net present value of a project? (a) Increasing the value of each of the project's discounted cash inflows (b) Moving each of the cash inflows forward to a sooner time period (c) Decreasing the required discount rate (d) Increasing the project's initial cost at time zero 5. Which of the following is true...

  • Isaac has analyzed two mutually exclusive projects that have 3-year lives. Project A has an NPV...

    Isaac has analyzed two mutually exclusive projects that have 3-year lives. Project A has an NPV of $81,406, a payback period of 2.48 years, and an IRR of 9.31 percent. Project B has an NPV of $82,909, a payback period of 2.57 years, and an IRR of 9.22 percent. The firm’s cost of capital is 9.15 percent and required payback period is 2.8 years. Isaac must make a recommendation and justify it in 15 words or less. What should his...

  • by hand #1 Questions a) to c) refer to two projects with the following cash flows:...

    by hand #1 Questions a) to c) refer to two projects with the following cash flows: Year Project B Project A - $200 80 -$200 100 80 100 80 100 Projects A and B are mutually exclusive. a) Calculate the Payback, Discounted Payback, NPV, IRR, and Profitability Index for Projects A and B using an opportunity cost of capital of 10% (where applicable). Which of these projects is worth pursuing? Explain. b) Calculate the Payback, Discounted Payback, NPV, IRR, and...

  • All techniques with NPV profile - Mutually exclusive projects Projects A and B, of equal risk,...

    All techniques with NPV profile - Mutually exclusive projects Projects A and B, of equal risk, are alternatives for expanding Rosa Company's capacity. The firm's cost of capital is 16%. The cash flows for each project are shown in the following table: PF a. Calculate each project's payback period. b. Calculate the net present value (NPV) for each project. c. Calculate the internal rate of return (IRR) for each project. d. Indicate which project you would recommend. a. The payback...

  • All techniques, conflicting rankings - Nicholson Roofing Materials, Inc. is considering two mutually exclusive projects, each...

    All techniques, conflicting rankings - Nicholson Roofing Materials, Inc. is considering two mutually exclusive projects, each with an initial investment of $180,000. The company's board of directors has set a 4 year payback requirement and has set its cost of capital at 9%. The cash inflows associated with the two projects are shown in the following table. Capital inflows (CF) Year Project A Project B 1 $60,000 $75,000 2 $60,000 $70,000 3 $60,000 $50,000 a. calculate the payback period for...

  • If the projects were independent, which project(s) would be accepted according to the IRR method? a)...

    If the projects were independent, which project(s) would be accepted according to the IRR method? a) Neither b) Project A c) Project B d) Both Projects A or B If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method? a) Neither b) Project A c) Project B d) Both Projects A or B The reason is a) TheNPV and IRR approaches use the same reinvestment rate assumption and so both approaches reach the same...

  • 11.07 CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this...

    11.07 CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows:    0 1 2 3 4 5 Project M -$6,000 $2,000 $2,000 $2,000 $2,000 $2,000 Project N -$18,000 $5,600 $5,600 $5,600 $5,600 $5,600 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers...

  • 14) Cedric is considering between two mutually exclusive projects. The following table gives the cash flows...

    14) Cedric is considering between two mutually exclusive projects. The following table gives the cash flows of each project: 0 1 2 3 4 A -$50 25 20 20 15 B -$100 20 40 50 60 a. If your discount rate is 6%, what are the NPVs of the two projects? b. What are the IRRs of the two projects? c. Why do IRR and NPV rank the two projects differently? NPV IRR

  • A company is considering two mutually exclusive expansion projects. Plan A requires a 21 million expenditure...

    A company is considering two mutually exclusive expansion projects. Plan A requires a 21 million expenditure on a large scale integrated plant that would provide expected cash flows of $6.40 million per year for 6 years. Plan B requires a $7 million expenditure to build a somewhat less efficient, more labor-intensive plant with expected cash flows of $2.72 million per year for 6 years. The firm’s WACC is 10%. (Timeline required) a. Calculate each project’s NPV and IRR. b. Calculate...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT