Question

Garcia, Inc. uses a job-order costing system for its products, which pass from the Machining Department,...

Garcia, Inc. uses a job-order costing system for its products, which pass from the Machining Department, to the Assembly Department, to finished-goods inventory. The Machining Department is heavily automated; in contrast, the Assembly Department performs a number of manual-assembly activities. The company applies manufacturing overhead using machine hours in the Machining Department and direct-labor cost in the Assembly Department. The following information relates to the year just ended:

Machining Department Assembly Department
Budgeted manufacturing overhead $ 4,000,000 $ 3,080,000
Actual manufacturing overhead 4,280,000 3,050,000
Budgeted direct-labor cost (based on practical capacity) 1,500,000 5,600,000
Actual direct-labor cost 1,450,000 5,780,000
Budgeted machine hours (based on practical capacity) 400,000 100,000
Actual machine hours 425,000 110,000


The data that follow pertain to job no. 775, the only job in production at year-end.

Machining Department Assembly Department
Direct material $ 23,500 $ 6,600
Direct labor $ 27,800 $ 58,600
Machine hours 360 150


Selling and administrative expense amounted to $2,500,000.

1. Compute the cost of the company’s year-end work-in-process inventory.

2. Determine whether overhead was under- or overapplied during the year in the Machining Department.

3. Determine whether overhead was under- or overapplied during the year in the Assembly Department.

4. How much overhead would have been charged to the company’s Work-in-Process account during the year?

0 0
Add a comment Improve this question Transcribed image text
Answer #1
1
Machining Assembly
a Budgeted Manufacturing Overhead 4,000,000 3,080,000
b Budgeted Machine Hours 400,000
c Budgeted Direct labor cost           5,600,000
d Overhead Rate of
Machining =(a/b)
Assembly= (a/c)
10                      0.55
2
Machining Assembly Total
a Direct Material 23,500 6,600 30,100
b Direct Labor 27,800 58600 86,400
c Overhead cost for Machining 3600 3,600
d Overhead cost for Assembly           32,230.00 32,230
e Total cost of work in Process 54,900           97,430.00 152,330
Total cost of work in Process 152,330
Working note
overhead cost of Machining = (Machine hour * Overhead rate)
Machining= 360*10= 3600
Overhead cost of Assembly = (direct labor cost * overhead rate)
Overhead cost of Assembly = 58600*0.55=32230
3 & 4
Machining Assembly
a applied overhead cost
Machining = Overhead rate * actual Machine hours
= 10*425,000
Assembly = overhead rate * actual direct labor cost = 0.55*5780000
          4,250,000.00    3,179,000.00
b actual overhead cost           4,280,000.00     3,050,000.00
c Over or under applied overhead (a-b)                  (30,000.00)         129,000.00
3 Matching department under -applied because Budgeted Manufacturing overhead cost is lower than actual overhead cost
4 Assembly Department over- applied Budgeted Manufacturing overhead cost is higher than actual overhead cost
5 Overhead Charged to Work in process during the year
Machining Assembly Total
applied Manufacturing Overhead           4,250,000.00    3,179,000.00    7,429,000.00
Overhead Charged to Work in process during the year =7,429,000 (sum of Both department)
Add a comment
Know the answer?
Add Answer to:
Garcia, Inc. uses a job-order costing system for its products, which pass from the Machining Department,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Garcia, Inc. uses a job-order costing system for its products, which pass from the Machining Department,...

    Garcia, Inc. uses a job-order costing system for its products, which pass from the Machining Department, to the Assembly Department, to finished-goods inventory. The Machining Department is heavily automated; in contrast, the Assembly Department performs a number of manual-assembly activities. The company applies manufacturing overhead using machine hours in the Machining Department and direct-labor cost in the Assembly Department. The following information relates to the year just ended: Machining Assembly Department Department Budgeted manufacturing $4,000,000 $3,080,000 overhead Actual manufacturing overhead...

  • Garcia, Inc. uses a job-order costing system for its products, which pass from the Machining Department,...

    Garcia, Inc. uses a job-order costing system for its products, which pass from the Machining Department, to the Assembly Department, to finished-goods inventory. The Machining Department is heavily automated; in contrast, the Assembly Department performs a number of manual-assembly activities. The company applies manufacturing overhead using machine hours in the Machining Department and direct-labor cost in the Assembly Department. The following information relates to the year just ended: Machining Department Assembly Department Budgeted manufacturing overhead $ 4,000,000 $ 3,024,000 Actual...

  • Juarez, Inc. uses a job-order costing system for its products, which pass from the Machining Department,...

    Juarez, Inc. uses a job-order costing system for its products, which pass from the Machining Department, to the Assembly Department, to finished-goods inventory. The Machining Department is heavily automated; in contrast, the Assembly Department performs a number of manual-assembly activities. The company applies manufacturing overhead using machine hours in the Machining Department and direct-labor cost in the Assembly Department. The following information relates to the year just ended: Machining Department Assembly Department   Budgeted manufacturing overhead $4,000,000 $3,136,000   Actual manufacturing overhead...

  • Juarez, Inc. uses a job-order costing system for its products, which pass from the Machining Department,...

    Juarez, Inc. uses a job-order costing system for its products, which pass from the Machining Department, to the Assembly Department, to finished-goods inventory. The Machining Department is heavily automated; in contrast, the Assembly Department performs a number of manual-assembly activities. The company applies manufacturing overhead using machine hours in the Machining Department and direct-labor cost in the Assembly Department. The following information relates to the year just ended: Machining Department Assembly Department   Budgeted manufacturing overhead $4,000,000 $3,136,000   Actual manufacturing overhead...

  • Required information (The following information applies to the questions displayed below.) Garcia, Inc. uses a job-order...

    Required information (The following information applies to the questions displayed below.) Garcia, Inc. uses a job-order costing system for its products, which pass from the Machining Department, to the Assembly Department, to finished-goods inventory. The Machining Department is heavily automated; in contrast, the Assembly Department performs a number of manual-assembly activities. The company applies manufacturing overhead using machine hours in the Machining Department and direct-labor cost in the Assembly Department. The following information relates to the year just ended: Machining...

  • Required information [The following information applies to the questions displayed below.] Garcia, Inc. uses a job-order...

    Required information [The following information applies to the questions displayed below.] Garcia, Inc. uses a job-order costing system for its products, which pass from the Machining Department, to the Assembly Department, to finished-goods inventory. The Machining Department is heavily automated; in contrast, the Assembly Department performs a number of manual-assembly activities. The company applies manufacturing overhead using machine hours in the Machining Department and direct-labor cost in the Assembly Department. The following information relates to the year just ended: Machining...

  • 2- Question la) Divine Products uses a job-costing system for its units, which pass from the...

    2- Question la) Divine Products uses a job-costing system for its units, which pass from the Machining Assembly Department, to finished-goods inventory. The Department is heavily automated; in contrast, the Assembly Department performs a number of manual-assembly activities. The company uses machine hours to apply manufacturing overhead to products in the Machining Department, and direct labour cost to apply manufacturing overhead to products in the Assembly Department. The following information relates to the Machining Department for the year just ended:...

  • Can someone help me determine the responses I co0uld not figure out on my own with...

    Can someone help me determine the responses I co0uld not figure out on my own with regards to this question? Garcia, Inc. uses a job-order costing system for its products, which pass from the Machining Department, to the Assembly Department, to finished-goods inventory. The Machining Department is heavily automated; in contrast, the Assembly Department performs a number of manual-assembly activities. The company applies manufacturing overhead using machine hours in the Machining Department and direct-labor cost in the Assembly Department. The...

  • Walker Enterprises, Inc., uses a job-order costing system and sets a predetermined overhead rate at the...

    Walker Enterprises, Inc., uses a job-order costing system and sets a predetermined overhead rate at the beginning of each year based on estimated manufacturing overhead costs. Each job requires work in both the Assembly and Machining Departments. The predetermined overhead rate is based on direct labor cost in Assembly Department and on machine hours in Machining Department. At the beginning of the year, the company made the following estimates: Assembly Department $120,000 Machining Department $32,000 Direct labor cost Manufacturing overhead...

  • The Lowell Company uses a normal job-costing system at its Minneapolis plant. The plant has a...

    The Lowell Company uses a normal job-costing system at its Minneapolis plant. The plant has a machining department and an assembly department. Its job-costing system has two direct-cost categories (direct materials and direct manufacturing labor, and two manufacturing overhead cost pools (the machining department overhead allocated to jobs based on actual machine-hours, and the assembly department overhead, allocated to jobs based on actual direct manufacturing labor costs). The 2017 budget for the plant is as follows: (Click the icon to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT