Answers
A |
Estimated overhead |
$615,420.00 |
B |
Estimated total DLHs |
473,400 |
C = A/B |
Overhead rate per DLHs |
$1.30 |
D |
Actual DLHs by small lamp production |
430,800 |
E = C x D |
Overhead alloccated |
$560,040.00 |
Working |
Painting |
|
A |
Overhead |
$241,500 |
B |
DLHs |
11200 |
C = A/B |
Overhead rate per DLHs |
$21.56 |
D |
DLHs used by 'Product B' |
3 |
E = CxD |
Overhead allocated |
$64.68 |
Correct Answer = Option ‘b’ $
260,610
A |
Estimated overhead |
$644,000.00 |
B |
Estimated total DLHs |
542,000 |
C = A/B |
Overhead rate per DLHs |
$1.19 |
D |
Actual DLHs by small lamp production |
219,000 |
E = C x D |
Overhead alloccated |
$260,610.00 |
Correct Answer = Option ‘d’ $
279.57
Overhead cost |
Total drivers |
Activity rates |
Cost drivers for Disk drives |
Overhead allocated |
|
Producrement |
$ 370,000.00 |
20000 |
$ 18.50 |
4000 |
$ 74,000.00 |
Scheduling |
$ 250,000.00 |
1250 |
$ 200.00 |
300 |
$ 60,000.00 |
Material handling |
$ 500,000.00 |
6200 |
$ 80.65 |
1400 |
$ 112,910.00 |
Product development |
$ 730,000.00 |
45 |
$ 16,222.22 |
10 |
$ 162,222.20 |
Production |
$ 1,500,000.00 |
20000 |
$ 75.00 |
2000 |
$ 150,000.00 |
Total Overhead allocated |
$ 559,132.20 |
||||
Total units of Disk drivers |
2000 |
||||
Overhead cost per unit |
$ 279.57 |
Correct answer = Option ‘a’ $ 5.17 per
MH
A |
Estimated overhead |
$268,490.00 |
B |
Estimated total machine hours |
51,910 |
C = A/B |
Overhead rate per machine hours |
$5.17 |
1) 2) 3) 4) 5) The Botosan Factory has determined that its budgeted factory overhead budget...
1) 2) Blue Ridge Marketing Inc. manufactures two products, A and B. Presently, the company uses a single plantwide factory overhead rate for allocating overhead to products. However, management is considering moving to a multiple department rate system for allocating overhead. The following table presents information about estimated overhead and direct labor hours Product Direct Labor Hours (dlh) 11,600 dlh Overhead $348,580 40,964 $389,544 Painting Dept 13 dh 3 dlh Finishing Dept 4,900 16 Totals 16,500 dlh 16 dlh 19...
Blackwelder Factory produces two similar products-small lamps and desk lamps. The total plant overhead budget is $602,000 with 523,000 estimated direct labor hours. It is further estimated that small lamp production will require 261,000 direct labor hours and desk lamp production will need 262,000 direct labor hours. Using the single plantwide factory overhead rate with an allocation base of direct labor hours, how much factory overhead will Blackwelder Factory allocate to desk lamp production if actual direct hours for the...
Blackwelder Factory produces two similar products-small lamps and desk lamps. The total plant overhead budget is $656,000 with 464,000 estimated direct labor hours. It is further estimated that small lamp production will require 291,000 direct labor hours and desk lamp production will need 173,000 direct labor hours. Using the single plantwide factory overhead rate with an allocation base of direct labor hours, how much factory overhead will Blackwelder Factory allocate to desk lamp production if actual direct hours for the...
Blackwelder Factory produces two similar products-small lamps and desk lamps. The total plant overhead budget is $550,000 with 491,000 estimated direct labor hours. It is further estimated that small lamp production will require 258,000 direct labor hours and desk lamp production will need 233,000 direct labor hours. Using the single plantwide factory overhead rate with an allocation base of direct labor hours, how much factory overhead will Blackwelder Factory allocate to small lamp production if actual direct hours for the...
Calculator Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The Indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Procurement Scheduling Materials handling Product development Production Activity Cost Activity Base $363,600 Number of purchase orders 220,900 Number of production orders 439,300 Number of moves 770,800 Number of engineering changes 1,448,300 Machine hours Number of Production Orders Number...
Blackwelder Factory produces two similar products - small lamps and desk lamps. The total plant overhead budget is $640,000 with 400,000 estimated direct labor hours. It is further estimated that small lamp production will require 275,000 direct labor hours and desk lamp production will need 125,000 direct labor hours. Using the single plantwide factory overhead rate with an allocation base of direct labor hours, how much factory overhead will Blackwelder Factory allocate to small lamp production if actual direct hours...
The total factory overhead for Big Light Company is budgeted for the year at $894,880. Big Light manufactures two different products: night lights and desk lamps. Night lights are budgeted for 10,700 units. Each night light requires 2 hours of direct labor. Desk Lamps are budgeted for 24,600 units. Each desk lamp requires 3 hours of direct labor. a Determine the total number of budgeted direct labor hours for the year. direct labor hours b Determine the single plantwide factory...
The total factory overhead for Big Light Company is budgeted for the year at $1,701,700. Big Light manufactures two different products: night lights and desk lamps. Night lights are budgeted for 13,100 units. Each night light requires 3 hours of direct labor. Desk lamps are budgeted for 16,100 units. Each desk lamp requires 2 hours of direct labor a Determine the total number of budgeted direct labor hours for the year. direct labor hours b Determine the single plantwide factory...
Pinnacle Corp. budgeted $258,700 of overhead cost for the current year. Actual overhead costs for the year were $240,730. Pinnacle's plantwide allocation base, machine hours, was budgeted at 54,860 hours. Actual machine hours were 55,670. A total of 108,360 units was budgeted to be produced and 98,000 units were actually produced. Pinnacle's plantwide factory overhead rate for the current year is: a. $4.39 per machine hour b. $4.72 per machine hour c. $2.39 per machine hour d. $2.22 per machine...
The total factory overhead for Big Light Company is budgeted for the year at $1,146,000. Big Light manufactures two different products: night lights and desk lamps. Night lights are budgeted for 9,900 units. Each night light requires 3 hours of direct labor. Desk lamps are budgeted for 13,800 units. Each desk lamp requires 2 hours of direct labor. a Determine the total number of budgeted direct labor hours for the year. direct labor hours b Determine the single plantwide factory...