Question

Pinnacle Corp. budgeted $258,700 of overhead cost for the current year. Actual overhead costs for the...

Pinnacle Corp. budgeted $258,700 of overhead cost for the current year. Actual overhead costs for the year were $240,730. Pinnacle's plantwide allocation base, machine hours, was budgeted at 54,860 hours. Actual machine hours were 55,670.

A total of 108,360 units was budgeted to be produced and 98,000 units were actually produced. Pinnacle's plantwide factory overhead rate for the current year is:

a. $4.39 per machine hour b. $4.72 per machine hour c. $2.39 per machine hour d. $2.22 per machine hour

-------------------

Selected accounts with a credit amount omitted are as follows

Work in Process
Apr. 1 Balance 6,500 Apr. 30 Goods finished X
     30 Direct materials 55,700
     30 Direct labor 190,500
     30 Factory overhead 57,150
Finished Goods
Apr. 1 Balance 12,000
     30 Goods finished 309,600

What was the balance of Work in Process as of April 30?

a. $250

b. $309,600

c. $12,000

d. $57,150

-----------------

When Job 117 was completed, direct materials totaled $28,160; direct labor, $33,958; and factory overhead, $20,707. A total of 3,313 units were produced at a per-unit cost of

a. $82,825

b. $3,313

c. $25

d. $62,118

-----------------

Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below.


Activity Cost

Activity Base
Procurement $344,000 Number of purchase orders
Scheduling 245,500 Number of production orders
Materials handling 429,500 Number of moves
Product development 727,000 Number of engineering changes
Production 1,445,000 Machine hours

Number of
Purchase
Orders

Number of
Production
Orders

Number
of
Moves

Number of
Engineering
Changes


Machine
Hours

Number
of
Units
Disk drives 4,060    390       1,230 11         2,200 2,000
Tape drives 1,500    135       530 5         8,300 4,500
Wire drives 12,400    910       3,500 28         11,600 2,300

The activity rate for the procurement activity cost pool is

a. $65.38 per purchase order

b. $239.72 per purchase order

c. $171.08 per purchase order

d. $19.15 per purchase order

----------------------

Selected accounts with amounts omitted are as follows

Work in Process
Aug. 1 Balance 277,750 Aug. 31 Goods finished 153,780
     31 Direct materials X
       31 Direct labor 35,400
     31 Factory overhead X
Factory Overhead
Aug. 1 – 31 Costs incurred 96,990 Aug. 1 Balance 15,200
       31 Applied
(30% of direct labor cost) X

If the balance of Work in Process on August 31 is $194,620, what was the amount debited to Work in Process for direct materials in August?

a. $353,990

b. $507,770

c. $118,530

d. $24,630

1 0
Add a comment Improve this question Transcribed image text
Answer #1

1) Overhead rate = 258700/54860 = 4.72 per MH

So answer is b) $4.72 per machine hour

2) Ending work in process = 6500+55700+190500+57150-309600 = 250

So answer is b) $250

3) Unit cost

Direct material 28160
Direct labor 33958
Overhead 20707
Total Cost 82825
Unit 3313
Unit cost 25

So answer is c) $25

4) Activity rate for procurement = 344000/17960 = 19.15 per purchase order

So answer is d) $19.15 per purchase order

5) Applied overhead = 35400*30% = 10620

Direct material = 153780+194620-10620-35400-277750 = 24630

So answer is d) $24630

Add a comment
Know the answer?
Add Answer to:
Pinnacle Corp. budgeted $258,700 of overhead cost for the current year. Actual overhead costs for the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Thomlin Company forecasts that total overhead for the current year will be $11,070,000 with 175,000 total...

    Thomlin Company forecasts that total overhead for the current year will be $11,070,000 with 175,000 total machine hours. Year to date, the actual overhead is $7,860,000 and the actual machine hours are 81,000 hours. The predetermined overhead rate based on machine hours is Round the factory overhead rate to the nearest dollar before multiplying by the number of hours. a. $45 per machine hour b. $63 per machine hour c. $137 per machine hour d. $97 per machine hour -----------------...

  • 1) 2) 3) 4) 5) The Botosan Factory has determined that its budgeted factory overhead budget...

    1) 2) 3) 4) 5) The Botosan Factory has determined that its budgeted factory overhead budget for the year is $615,420 and budgeted direct labor hours are 473,400. If the actual direct labor hours for the period are 430,800, how much overhead would be allocated to the period? Oa, $576,841 Ob. $560,040 Oc. $476,034 Od. $677,648 Blue Ridge Marketing Inc. manufactures two products, A and B. Presently, the company uses a single plantwide factory overhead rate for allocating overhead to...

  • Pinacle Corp. budgeted $240,550 of overhead cost for the current year. Actual overhead costs for the...

    Pinacle Corp. budgeted $240,550 of overhead cost for the current year. Actual overhead costs for the year were $215,420. Pinacle's plantwide allocation base, machine hours, was budgeted at 53,640 hours. Actual machine hours were 55,160. A total of 96,670 units was budgeted to be produced and 98,000 units were actually produced. Pinacle's plantwide factory overhead rate for the current year is: a. $4.48 per machine hour b. $4.02 per machine hour c. $2.23 per machine hour d. $2.49 per machine...

  • Pinacle Corp. budgeted $218,870 of overhead cost for the current year. Actual overhead costs for the...

    Pinacle Corp. budgeted $218,870 of overhead cost for the current year. Actual overhead costs for the year were $202,840. Pinacle's plantwide allocation base, machine hours, was budgeted at 46,230 hours. Actual machine hours were 48,160. A total of 105,910 units was budgeted to be produced and 98,000 units were actually produced. Pinacle's plantwide factory overhead rate for the current year is: O a $4.73 per machine hour Ob. $2.07 per machine hour Oc. $4.39 per machine hour Od. $1.92 per...

  • Calculator Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and...

    Calculator Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The Indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Procurement Scheduling Materials handling Product development Production Activity Cost Activity Base $363,600 Number of purchase orders 220,900 Number of production orders 439,300 Number of moves 770,800 Number of engineering changes 1,448,300 Machine hours Number of Production Orders Number...

  • The Thomlin Company forecasts that total overhead for the current year will be $11,241,000 with 172,000...

    The Thomlin Company forecasts that total overhead for the current year will be $11,241,000 with 172,000 total machine hours. Year to date, the actual overhead is $7,730,000 and the actual machine hours are 85,000 hours. The predetermined overhead rate based on machine hours is Round the factory overhead rate to the nearest dollar before multiplying by the number of hours. a. $45 per machine hour Ob. $132 per machine hour C. $65 per machine hour Od. $91 per machine hour...

  • The Thomlin Company forecasts that total overhead for the current year will be $11,298,000 with 156,000...

    The Thomlin Company forecasts that total overhead for the current year will be $11,298,000 with 156,000 total machine hours. Year to date, the actual overhead is $7,722,000 and the actual machine hours are 100,000 hours. If the Thomlin Company uses a predetermined overhead rate based on machine hours for applying overhead, as of this point in time (year to date), the overhead is Round the factory overhead rate to the nearest dollar before multiplying by the number of hours. a...

  • Company manufactures specialty tools to customer order. Budgeted overhead for the coming year is: za Firenza...

    Company manufactures specialty tools to customer order. Budgeted overhead for the coming year is: za Firenza Company manufactures specialty tools to customer order. Budgeted overhead for the coming year is: Purchasing $40,000 Setups 40,000 Engineering 50,000 Other 40,000 Previously, Sanjay Bhatt, Firenza Company's controller, had applied overhead on the basis of machine hours. Expected machine hours for the coming year are 50,000. Sanjay has been reading about activity-based costing, and he wonders whether or not it might offer some advantages...

  • ABC, Inc. is estimating activity costs associated with producing disk drives, tapes drives, and wire drives....

    ABC, Inc. is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to five separate activity pools. The budgeted activity cost and activity base data by product are provided below. Activity Cost Activity Base Number of purchase orders Procurement $ 370,000 Number of production orders Scheduling 250,000 Number of moves Materials handling 500,000 Number of engineering changes Product development 730,000 Machine hours Production 1,500,000 Number of Number of Purchase Orders...

  • Overhead Application, Activity-Based Costing, Bid Prices Firenza Company manufactures specialty tools to customer order. Budgeted overhead...

    Overhead Application, Activity-Based Costing, Bid Prices Firenza Company manufactures specialty tools to customer order. Budgeted overhead for the coming year is: Purchasing $40,000 Setups 40,000 Engineering 45,000 Other 40,000 Previously, Sanjay Bhatt, Firenza Company's controller, had applied overhead on the basis of machine hours. Expected machine hours for the coming year are 50,000. Sanjay has been reading about activity-based costing, and he wonders whether or not it might offer some advantages to his company. He decided that appropriate drivers for...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT