Question

 As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs.

image.png

 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $9,000; direct labor,

 $3,700; and overhead, $1,184. Jobs 103 and 104 were started in June. Overhead cost is applied with a predetermined rate based on

 direct labor cost. Jobs 102 and 103 were finished in June, and Job 104 is expected to be finished in July. No raw materials were used

 indirectly in June. Using this information, answer the following questions. (Assume this company's predetermined overhead rate did

 not change across these months.)


 1&2. Complete the table below to calculate the cost of the raw materials requisitioned and direct labor cost incurred during June for

 each of the three jobs?

 3. Using the accumulated costs of the jobs, what predetermined overhead rate is used?

 4. How much total cost is transferred to finished goods during June?


Check Complete this question by entering your answers in the tabs below. Req 1 and 2 Req 3 Req 4 Complete the table below to calculate the cost of the raw materials requisitioned and direct labor cost incurred during June for each of the three jobs? Direct Materials May June Total 102 103 104 Total 60,000 60,000 60,000 $ 60,000 Direct Labor June 3,700 28,500 38,000 70,200 3,700 102 103 104 Total 28,500 38,000 66,500 $ 3,700 $ Req 3 > Req 1 and 2 Prev 1 of 3 Next>

Complete this question by entering your answers i n the tabs below 3.33 points Req 1 and 2 Req 3 Req 4 Using the accumulated costs of the jobs, what predetermined overhead rate is eBook Hint Print References Ove tor: Choose De Job 102 Job 103 Overhead rate Job 104 Req 1 and 2 Req 4 Prev 1of 3 Next > Hill

4. How much total cost is transferred to finished goods during June? Complete this question by entering your answers in the tabs below. Req 1 and 2 Req 3 Req 4 How much totacostis transterred to finished goods during June. Applied Total CostFinished Goods Overhead Direct Direct Labor Cost Transfe to Job 102 103 104 Total $ 17,000 $13,000 28,500 38,000 $ 127,000 $ 79,500 50,000 60,000 K Req 3 Req 4 X くPrev 1 of 3 Next >


3 0
Add a comment Improve this question Transcribed image text
Answer #1

Requirement 1 & 2:

Direct material

Job may june total
102 9000 8000(17000-9000) 17000
103 - 50000 60000
104 - 60000 60000
Total 900000 118000 157000


Direct labour

Job may June total
102 3700 9300(13000-3700) 13000
103 - 28500 28500
104 - 38000 38000
Total 3700 75800 79500

Requirement 3:

Overhead rates

Numerator denominator overhead rate
102
Accumulated overhead Direct labour cost. Overhead rate
4160 13000 0.32
103
Accumulated overhead direct labour cost overhead rate
9120 28500 0.32
104
Accumulated depreciation direct labour costs overhead rate
12160 38000

0.32

Note: Direct labourcost is taken as the base for calculating predetermined overhead rate, as mentioned in the question.

​​​​​Retirement 4: cost of goods transferred to finishes goods.

Job direct material direct labour overhead applied total cost cost of goods transferred to finished goods
102 8000 9300 2976(4160-1184) 20276 20276
103 50000 13000 9120 72120 72120
104 60000 38000 12160 110160 110160
Total 202556

Note: there is nothing mentioned in the question about work in progress. Therefore, it is assumed that there is no work in progress and all the costs incurred in the ninth are transferred to the finished goods.

Add a comment
Know the answer?
Add Answer to:
As of the end of June, the job cost sheets at Racing Wheels, Inc.
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...

    As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. JOD 102 922,000 Diegt materials Direct labor Overhead applied JOB 103 $71,000 27.300 10.920 JOD 104 $55,000 41.000 16.400 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $11.000; direct labor, $3,900; and overhead, $1,560. Jobs 103 and 104 were started in June. Overhead cost...

  • As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...

    As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 31,000 $ 56,000 $ 57,000 Direct labor 19,000 25,300 43,000 Overhead applied 7,410 9,867 16,770 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $14,000; direct labor, $3,500; and overhead, $1,365. Jobs 103 and 104 were...

  • As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...

    As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs Job 102 Sob 103 Job 104 Direct materials $15,000 $33,000 $27,000 Direct labor 8.000 14,200 21,000 Overhead 4,000 7,100 10,500 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials. $6.000; direct labor, $1,800, and overhead, 5900. Jobs 103 and 104 are started in June Overhead...

  • As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...

    As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 43,000 $ 65,000 $ 52,000 Direct labor 17,000 29,600 46,000 Overhead applied 7,480 13,024 20,240 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $11,000; direct labor, $3,900; and overhead, $1,716. Jobs 103 and 104 were...

  • As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...

    As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs ts Direct materials Direct labor Overhead applied Job 102 $18,000 14,000 6,020 Job 103 $51,000 26,200 11, 266 Job 104 $64,000 43,090 18,490 Job 102 was started in production in May, and the following costs were assigned to it in May: direct materials, $14,000; direct labor, $4,000; and overhead, $1,720. Jobs 103 and 104 were started...

  • As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...

    As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 $16,000 20,000 9,200 Job 103 Job 104 Direct materials $56,000 $60,000 44,000 20,240 Direct labor 30,000 Overhead applied 13,800 Job 102 was started in production in May, and the following costs were assigned to it in May: direct materials, $11,000; direct labor, $3,900; and overhead, $1,794. Jobs 103 and 104 were started in June....

  • Che As of the end of June, the job cost sheets at Racing Wheels, Inc., show...

    Che As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $56,000 $38,000 13,000 5, 200 $58,000 41,000 16,400 Direct labor 25,600 10,240 Overhead applied Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $12,000; direct labor, $3,300; and overhead, $1,320. Jobs 103 and 104 were started...

  • As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...

    As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Direct materials Direct labor Overhead applied Job 102 $38,000 13,000 5,280 Job 103 $56,000 25,600 10,240 Job 104 $58,000 41,000 16,480 Job 102 was started in production in May and the following costs were assigned to it in May direct materials, $12,000, direct labor $3,300, and overhead, $1,320. Jobs 103 and 104 were started in June....

  • as of the end of June, the job cost sheets at racing wheels Inc. show the...

    as of the end of June, the job cost sheets at racing wheels Inc. show the following total costs accumulated on three custom jobs. Check my work As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Direct materials Direct labor Overhead applied Job 102 $41,000 17,000 7,990 Job 103 $74,000 28,500 13,395 Job 104 $53,000 45,000 21,150 Job 102 was started in production in May,...

  • As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...

    As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Direct materials Direct labor Overhead applied Job 102 $17,000 16,000 5,280 Job 103 $53,000 27,100 8,943 Job 104 $53,000 40,000 13,200 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials. $8,000; direct labor. $2,900; and overhead, $957. Jobs 103 and 104 were started in June....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT