As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs.
Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $9,000; direct labor,
$3,700; and overhead, $1,184. Jobs 103 and 104 were started in June. Overhead cost is applied with a predetermined rate based on
direct labor cost. Jobs 102 and 103 were finished in June, and Job 104 is expected to be finished in July. No raw materials were used
indirectly in June. Using this information, answer the following questions. (Assume this company's predetermined overhead rate did
not change across these months.)
1&2. Complete the table below to calculate the cost of the raw materials requisitioned and direct labor cost incurred during June for
each of the three jobs?
3. Using the accumulated costs of the jobs, what predetermined overhead rate is used?
4. How much total cost is transferred to finished goods during June?
Requirement 1 & 2:
Direct material
Job | may | june | total |
102 | 9000 | 8000(17000-9000) | 17000 |
103 | - | 50000 | 60000 |
104 | - | 60000 | 60000 |
Total | 900000 | 118000 | 157000 |
Direct labour
Job | may | June | total |
102 | 3700 | 9300(13000-3700) | 13000 |
103 | - | 28500 | 28500 |
104 | - | 38000 | 38000 |
Total | 3700 | 75800 | 79500 |
Requirement 3:
Overhead rates
Numerator | denominator | overhead rate | |
102 | |||
Accumulated overhead | Direct labour cost. | Overhead rate | |
4160 | 13000 | 0.32 | |
103 | |||
Accumulated overhead | direct labour cost | overhead rate | |
9120 | 28500 | 0.32 | |
104 | |||
Accumulated depreciation | direct labour costs | overhead rate | |
12160 | 38000 |
0.32 |
Note: Direct labourcost is taken as the base for calculating predetermined overhead rate, as mentioned in the question.
Retirement 4: cost of goods transferred to finishes goods.
Job | direct material | direct labour | overhead applied | total cost | cost of goods transferred to finished goods |
102 | 8000 | 9300 | 2976(4160-1184) | 20276 | 20276 |
103 | 50000 | 13000 | 9120 | 72120 | 72120 |
104 | 60000 | 38000 | 12160 | 110160 | 110160 |
Total | 202556 |
Note: there is nothing mentioned in the question about work in progress. Therefore, it is assumed that there is no work in progress and all the costs incurred in the ninth are transferred to the finished goods.
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. JOD 102 922,000 Diegt materials Direct labor Overhead applied JOB 103 $71,000 27.300 10.920 JOD 104 $55,000 41.000 16.400 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $11.000; direct labor, $3,900; and overhead, $1,560. Jobs 103 and 104 were started in June. Overhead cost...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 31,000 $ 56,000 $ 57,000 Direct labor 19,000 25,300 43,000 Overhead applied 7,410 9,867 16,770 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $14,000; direct labor, $3,500; and overhead, $1,365. Jobs 103 and 104 were...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs Job 102 Sob 103 Job 104 Direct materials $15,000 $33,000 $27,000 Direct labor 8.000 14,200 21,000 Overhead 4,000 7,100 10,500 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials. $6.000; direct labor, $1,800, and overhead, 5900. Jobs 103 and 104 are started in June Overhead...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 43,000 $ 65,000 $ 52,000 Direct labor 17,000 29,600 46,000 Overhead applied 7,480 13,024 20,240 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $11,000; direct labor, $3,900; and overhead, $1,716. Jobs 103 and 104 were...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs ts Direct materials Direct labor Overhead applied Job 102 $18,000 14,000 6,020 Job 103 $51,000 26,200 11, 266 Job 104 $64,000 43,090 18,490 Job 102 was started in production in May, and the following costs were assigned to it in May: direct materials, $14,000; direct labor, $4,000; and overhead, $1,720. Jobs 103 and 104 were started...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 $16,000 20,000 9,200 Job 103 Job 104 Direct materials $56,000 $60,000 44,000 20,240 Direct labor 30,000 Overhead applied 13,800 Job 102 was started in production in May, and the following costs were assigned to it in May: direct materials, $11,000; direct labor, $3,900; and overhead, $1,794. Jobs 103 and 104 were started in June....
Che As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $56,000 $38,000 13,000 5, 200 $58,000 41,000 16,400 Direct labor 25,600 10,240 Overhead applied Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $12,000; direct labor, $3,300; and overhead, $1,320. Jobs 103 and 104 were started...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Direct materials Direct labor Overhead applied Job 102 $38,000 13,000 5,280 Job 103 $56,000 25,600 10,240 Job 104 $58,000 41,000 16,480 Job 102 was started in production in May and the following costs were assigned to it in May direct materials, $12,000, direct labor $3,300, and overhead, $1,320. Jobs 103 and 104 were started in June....
as of the end of June, the job cost sheets at racing wheels
Inc. show the following total costs accumulated on three custom
jobs.
Check my work As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Direct materials Direct labor Overhead applied Job 102 $41,000 17,000 7,990 Job 103 $74,000 28,500 13,395 Job 104 $53,000 45,000 21,150 Job 102 was started in production in May,...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Direct materials Direct labor Overhead applied Job 102 $17,000 16,000 5,280 Job 103 $53,000 27,100 8,943 Job 104 $53,000 40,000 13,200 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials. $8,000; direct labor. $2,900; and overhead, $957. Jobs 103 and 104 were started in June....