Question

You received partial credit in the previous attempt. Check my work View previous attempt Exercise 15-18 Job order costing for
You received partial credit in the previous attempt. Check my work View previous attempt Staff clerical 380 1,000 75 20 Frey
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:-

1 ) estimated cost

Direct labour = 190*(300) +380*(75) + 1000*(20) = 105500

Total cost = 105500 + 175% = $290125

2)bidding price = 290125 +20000 = 310125

Bid with 305000 it wont reach 20000 profit

3)selling price = 290125 + 20000 = 310125

Add a comment
Know the answer?
Add Answer to:
You received partial credit in the previous attempt. Check my work View previous attempt Exercise 15-18...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Hansel Corporation has requested bids from several architects to design its new corporate headquarters. Frey Architects...

    Hansel Corporation has requested bids from several architects to design its new corporate headquarters. Frey Architects is one of the firms bidding on the job. Frey estimates that the job will require the following direct labor. Hourly Rate $300 Labor Architects Staff Clerical Estimated Hours 190 380 1,000 75 20 Frey applies overhead to jobs at 175% of direct labor cost. Frey would like to earn at least $20,000 profit on the architectural job. Based on past experience and market...

  • Exercise 15-18 Job order costing for services LO A1 Hansel Corporation has requested bids from several...

    Exercise 15-18 Job order costing for services LO A1 Hansel Corporation has requested bids from several architects to design its new corporate headquarters. Frey Architects is one of the firms bidding on the job. Frey estimates that the job will require the following direct labor. Labor Estimated Hours Hourly Rate Architects 168 $ 300 Staff 336 75 Clerical 725 20    Frey applies overhead to jobs at 175% of direct labor cost. Frey would like to earn at least $55,000...

  • Hansel Corporation has requested bids from several architects to design its new corporate headquarters. Frey Architects...

    Hansel Corporation has requested bids from several architects to design its new corporate headquarters. Frey Architects is one of the firms bidding on the job. Frey estimates that the job will require the following direct labor. Labor Estimated Hours Hourly Rate Architects 176 $ 300 Staff 352 75 Clerical 825 20 Frey applies overhead to jobs at 175% of direct labor cost. Frey would like to earn at least $40,000 profit on the architectural job. Based on past experience and...

  • 5 8 11 5 April 30 $ $45,000 5.600 61,000 May 31 32.000 20,900 33,700 Part...

    5 8 11 5 April 30 $ $45,000 5.600 61,000 May 31 32.000 20,900 33,700 Part 3 of 4 Inventories Raw materiale Work in process Pinished goods Activities and information for May Raw materials purchases (paid with cash) Pactory payroli (paid with cash) Factory overhead Indirect materiala Indirect labor Other overhead costs Sales (received in canh) Predetermined overhead rate based on direct labor 100,000 181 points 15.000 23,000 P8,000 1,700,000 BOOK 1. Direct labor usage 2. Indirect labor usage. 3....

  • You received no credit for this question in the previous attempt. Check my work View previous...

    You received no credit for this question in the previous attempt. Check my work View previous Required information The following information applies to the questions displayed below. Rubio recently invested $20,000 (tax basis) in purchasing a limited partnership interest. His at-risk amount is $15,000 In addition, Rubio's share of the limited partnership loss for the year is $22,000, his share of income from a different imited partnership is $5,000, and he has $40,000 in wage income and $10,000 in long-term...

  • You received partial credit In the previous attempt Check my work TPW, a calendar year taxpayer,...

    You received partial credit In the previous attempt Check my work TPW, a calendar year taxpayer, sold land with a $535,000 tax basis for $750,000 in February. The purchaser paid $75,000 cash at closing and gave TPW an interest-bearing note for the $675,000 remaining price. In August, TPW received a $55,950 payment from the purchaser consisting of a $33,750 principal payment and a $22,200 interest payment. In the first year after the year of sale, TPW received payments totaling $106,900...

  • 3 Homework 6 You received no credit for this question in the previous attempt Check my...

    3 Homework 6 You received no credit for this question in the previous attempt Check my work Required information The following information applies to the questions displayed below The following information pertains to Trenton Glass Works for the year just ended Budgeted direct-labor cost: 75.000 hours (practical capacity) at $16 per hour Actual direct-labor cost 80,000 hours at $1750 per hour Budgeted manufacturing overhead: $997,500 Actual selling and administrative expenses: 434,000 ing overhead $234,000 Indirect labor ta below beginning inventory,...

  • * You received no credit for this question in the previous attempt. Help Required information The...

    * You received no credit for this question in the previous attempt. Help Required information The Foundational 15 (L03-1, LO3-2, LO3-3, LO3-4) The following information applies to the questions displayed below.) Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company's inventory balances were as follows: Raw materials Work in process Finished goods $ 40,000 $ 18,000 $ 35,000 The company applies overhead cost to jobs on the basis of direct labor-hours. For the current year,...

  • Problem 2-18 Job-Order Costing for a Service Company (LO2-1, LO2-2, LO2-3) Check my work View previous...

    Problem 2-18 Job-Order Costing for a Service Company (LO2-1, LO2-2, LO2-3) Check my work View previous Speedy Auto Repairs uses a job-order costing system. The company's direct materials consist of replacement parts installed in customer vehicles, and its direct labor consists of the mechanics' hourly wages. Speedy's overhead costs include various items, such as the shop manager's salary, depreciation of equipment, utilities, insurance, and magazine subscriptions and refreshments for the waiting room 26:20 The company applies all of its overhead...

  • You received partial credit in the previous attempt. Check my work Required information Use the following...

    You received partial credit in the previous attempt. Check my work Required information Use the following information for the Exercises below. The following information applies to the questions displayed below.) Laker Company reported the following January purchases and sales data for its only product. Units sold at Retail Units Acquired at Cost 180 units $10.50 - $1,890 140 units @ $19.50 Date Activities Jan. 1 Beginning inventory Jan. 10 Sales Jan. 20 Purchase Jan. 25 Sales Jan. 30 Purchase 110...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT