Scatter Diagrams and High-Low Cost Estimation From April 1 through October 31, Coles County Highway Department hires temporar

0 0
Add a comment Improve this question Transcribed image text
Answer #1

a) High Low Method :

Variable Cost = (Highest Activity Cost−Lowest Activity Cost)/(Highest Activity Units-Lowest Activity Units)

Highest Activity Units = 400 Miles

Highest Activity Cost = $ 10,400

Lowest Activity Units = 100 Miles

Lowest Activity Cost = $ 6200

Variable Cost = ($10,400 - $6200)/(400-100)

Variable Cost Per Mile = $ 14 per Mile.

Fixed Cost = Highest Activity Cost − (Variable Cost * Highest activity Units)​

Fixed Cost = $ 10,400 - ($14*400)

Fixed Cost = $ 4,800

b) Scatter Diagram :

Chart Title $6,000 $5,000 $4,000 $3,000 $2,000 0 50 100 150 300 350 400 450 200 250 Miles .Variable Cost ($14 per Mile) Fixed

Equation (y = mx+c ) = Labour Cost = $14*(Miles) + Fixed Cost

Eg: Labour Cost at 400 Miles = $14 * 400 + 4800

Labour Cost = $10,400

c) If the wage rate increases by 8%, Variable cost Per Mile = ($14 + 8%)

Revised Variable cost per Mile = $ 15.12

Cost Equation will be : Labour Cost = $15.12 * (Miles) + Fixed Cost

  Labour Cost = $15.12 * (Miles) + $ 4,800

Add a comment
Know the answer?
Add Answer to:
Scatter Diagrams and High-Low Cost Estimation From April 1 through October 31, Coles County Highway Department...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Scatter Diagrams and High-Low Cost Estimation Assume the local Pearle Vision has the following information on...

    Scatter Diagrams and High-Low Cost Estimation Assume the local Pearle Vision has the following information on the number of sales orders received and order-processing costs. Month Sales Orders Order-Processing Costs 3,000 $ 82,700 1,500 50,375 4,400 120,700 2,800 81,900 2,300 69,775 1,200 43,100 2,000 62,500 Required (a.) Use information from the high- and low-volume months to develop a cost-estimating equation for monthly order-processing costs. x + $ (b.) Plot the data on a scatter diagram. Using the information from representative...

  • Scatter Diagrams and High-Low Cost Estimation Assume the local Pearle Vision has the following information on...

    Scatter Diagrams and High-Low Cost Estimation Assume the local Pearle Vision has the following information on the number of sales orders received and order processing costs. Month Sales Orders Order Processing Costs 1 3.000 599 200 2 1500 60.450 3 144 2.800 9020 5 83.730 6 1.200 51.720 2000 75.000 100 Required (a.) Use information from the high- and low-volume months to develop a cost estimating equation for monthly order processing costs. 29.15 16.800 A Ib. Plot the data on...

  • Scatter Diagrams and High-Low Cost Estimation Assume the local Pearle Vision has the following information on...

    Scatter Diagrams and High-Low Cost Estimation Assume the local Pearle Vision has the following information on the number of sales orders received and order-processing costs. Month Sales Orders Order-Processing Costs 3,000 $ 82,700 1,500 50,375 4,400 120,700 2,800 2,300 1,200 2,000 81,900 69,775 43,100 62,500 Required (a.) Use information from the high- and low-volume months to develop a cost-estimating equation for monthly order-processing costs. = $ 14,000 ~ +$ 24.25 ♥ (b.) Plot the data on a scatter diagram. Using...

  • Assume the local Pearle Vision has the following information on the number of sales orders received...

    Assume the local Pearle Vision has the following information on the number of sales orders received and order-processing costs. Month Sales Orders Order-Processing Costs 3,000 $ 82,700 1,500 50,375 4,400 120,700 2,800 81,900 2,300 69,775 1,200 43,100 2,000 62,500 Required (a.) Use information from the high- and low-volume months to develop a cost-estimating equation for monthly order-processing costs. = $ + $ (b.) Plot the data on a scatter diagram. Using the information from representative high-and low-volume months, develop a...

  • Assume the local Pearle Vision has the following information on the number of sales orders received...

    Assume the local Pearle Vision has the following information on the number of sales orders received and order-processing costs. Month Sales Orders Order-Processing Costs 1 3,000 $ 99,240 2 1,500 60,450 3 4,400 144,840 4 2,800 98,280 5 2,300 83,730 6 1,200 51,720 7 2,000 75,000 Required (a.) Use information from the high- and low-volume months to develop a cost-estimating equation for monthly order-processing costs. Answer Answer (b.) Plot the data on a scatter diagram. Using the information from representative...

  • High-Low Cost Estimation Assume the local YRC Worldwilde delivery service hub has the following information available...

    High-Low Cost Estimation Assume the local YRC Worldwilde delivery service hub has the following information available about fleet miles and operating costs: Year Miles Operating Costs 2017 556,000 $175,600 2018 684,000 214,000 Use the high-low method to develop a cost-estimating equation for total annual operating costs. (Let X = annual fleet miles.) Total annual costs = Answer + Answer * X

  • Exercise 18-6 Cost behavior estimation-scatter diagram and high-low LO P1 Felix & Co. reports the following...

    Exercise 18-6 Cost behavior estimation-scatter diagram and high-low LO P1 Felix & Co. reports the following Information about its units produced and total costs. points Units Produced Period Period Total Costs $2,700 3,300 3,980 4.500 608 1.ece 1.489 1.800 Units Produced 2,200 2.680 3.898 3,480 3,888 Total Costs $5.799 6,300 6,988 7.500 9. 160 eBook 5.100 le Hint Estimate total costs of 3.200 units are produced. Complete the below table to calculate the fixed cost and variable cost of sales...

  • Exercise 21-6 Cost behavior estimation-scatter diagram and high-low LO P1 Felix & Co. reports the following...

    Exercise 21-6 Cost behavior estimation-scatter diagram and high-low LO P1 Felix & Co. reports the following information about its units produced and total costs. Units Produced Period 1 2 3 4 5 410 810 1,210 1,610 Total Costs $2,510 3,110 3,710 4,310 4,910 Period 6 7 8 9 Units Produced 2,010 2,410 2,810 3,210 3,610 Total Costs $5,510 6,110 6,710 7,310 8,286 LO Estimate total costs if 3,010 units are produced. Complete the below table to calculate the fixed cost...

  • Exercise 18-6 Cost behavior estimation-scatter diagram and high-low LO P1 Felix & Co. reports the following...

    Exercise 18-6 Cost behavior estimation-scatter diagram and high-low LO P1 Felix & Co. reports the following information about its units produced and total costs. Units Units Period Period Produced Produced Total Costs Total Costs $2,630 3,230 3,830 4,430 5,030 2,130 2,530 2,930 3,330 3,730 $5,630 6,230 6,830 7,430 8,598 1 0 6 2 530 7 3 930 8 1,330 1,730 4 5 10 Estimate total costs if 3,130 units are produced. Complete the below table to calculate the fixed cost...

  • Check my work Exercise 18-6 Cost behavior estimation-scatter diagram and high-low LO P1 Felix & Co....

    Check my work Exercise 18-6 Cost behavior estimation-scatter diagram and high-low LO P1 Felix & Co. reports the following information about its units produced and total costs. Period Period Units Produced 0 530 930 1,330 1,730 Total Costs $2,630 3,230 3,830 4,430 5,030 Oo oovo Units Produced 2,130 2,530 2,930 3,330 3,730 Total Costs $5,630 6,230 6,830 7,430 8,598 Estimate total costs if 3,130 units are produced. Complete the below table to calculate the fixed cost and variable cost of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT