Question

True or False and why? 3. An increase in the weighted average cost of capital will...

True or False and why?
3. An increase in the weighted average cost of capital will result in an increase in a projects internal rate of return, assuming all other conditions hold constant.
4. Conflicts between two independent projects occasionally occur, where the NPV method ranks one project higher but the IRR method puts the other one first. In theory, such conflicts should be resolved in favor of the project with the higher NPV.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

An increase in the weighted average cost of capital will result in an increase in a projects internal rate of return, assuming all other conditions hold constant.

Statement is false

IRR dosent depends on Cost of Capital IRR is the internal rate of return of a project

Conflicts between two independent projects occasionally occur, where the NPV method ranks one project higher but the IRR method puts the other one first. In theory, such conflicts should be resolved in favor of the project with the higher NPV.

Statement is True

when comparing two projects, the Net present value and internal rate of return may provide conflicting results. that is one project has higher NPV while the other has a higher IRR. This difference occur because of different cash flow patterns in the two projects.

Add a comment
Know the answer?
Add Answer to:
True or False and why? 3. An increase in the weighted average cost of capital will...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • An increase in the weighted average cost of capital will result in an increase in a...

    An increase in the weighted average cost of capital will result in an increase in a project’s Internal Rate of Return, assuming all other conditions hold constant. T/F

  • Question 2 (1 point) 1. Conflicts between two mutually exclusive projects, where the NPV method chooses...

    Question 2 (1 point) 1. Conflicts between two mutually exclusive projects, where the NPV method chooses one project but the IRR method chooses the other, should generally be resolved in favor of the project with the higher NPV. 5 True False Question 3 (1 point) If a project's NPV is negative, then its payback must be longer that its economic life True False

  • IRR A project's internal rate of return (IRR) is the -Select- The IRR is an estimate...

    IRR A project's internal rate of return (IRR) is the -Select- The IRR is an estimate of the project's rate of return, and it is comparable to the -Select-on a bond. The equation for calculating the IRR is: ;that forces the PV of its inflows to equal its cost. CF2 CFN 1 IRF 1 IRF 1IR CFt t-1 (1 +IRR) CFt is the expected cash flow in Period t and cash outflows are treated as negative cash flows. There must...

  • Capital Budgeting Decision Criteria: IRR IRR A project's internal rate of return (IRR) is the -Select-compound...

    Capital Budgeting Decision Criteria: IRR IRR A project's internal rate of return (IRR) is the -Select-compound ratediscount raterisk-free rateCorrect 1 of Item 1 that forces the PV of its inflows to equal its cost. The IRR is an estimate of the project's rate of return, and it is comparable to the -Select-YTMcoupongainCorrect 2 of Item 1 on a bond. The equation for calculating the IRR is: CFt is the expected cash flow in Period t and cash outflows are treated...

  • СР, 0 A project's internal rate of return (IRR) is the -Select- that forces the PV...

    СР, 0 A project's internal rate of return (IRR) is the -Select- that forces the PV of its inflows to equal its cost. The IRR is an estimate of the project's rat of return, and it is comparable to the - Select on a bond. The equation for calculating the IRR is: NPV = CF. + CF + СР + ... + =0 (1 + IRR) (1 + ru (1 + R) CF (1 + IRR) CFt is the expected...

  • Question 3 5 pts Our firm's cost of capital is 10%. We are thinking about taking...

    Question 3 5 pts Our firm's cost of capital is 10%. We are thinking about taking a project that gives a 10% rate of return. Which of the following statements are correct. The NPV of this project is zero. The firm will increase its value if it takes this project. The firm should not take this project because it will lose value if the project is taken. The IRR of the project is greater than the cost of capital. Two...

  • True or False question The after-tax cost of debt generally increases when a firm's bond rating...

    True or False question The after-tax cost of debt generally increases when a firm's bond rating decreases. The weighted average cost of capital for a firm is the discount rate which the firm should apply to all of the projects it undertakes. Assigning discount rates to individual projects based on the risk level of each project may cause the firm's overall weighted average cost of capital to either increase or decrease over time. Other things being equal, the weighted average...

  • 1. Which of the following statements is true about independent projects? a.Independent projects are projects that, if ac...

    1. Which of the following statements is true about independent projects? a.Independent projects are projects that, if accepted, have to accept one small project to assist other independent projects. b.Independent projects are projects that, if accepted or rejected, do not affect the cash flows of other projects. c.Independent projects are projects that, if accepted, have a negative effect on the company's profit. d.Independent projects are projects that, if accepted or rejected, affect the net profit of other projects. 2. An...

  • Case Study 3--Capital Budgeting (Comprehensive Spreadsheet Problem 11-23, page 408) Your division is considering two projects....

    Case Study 3--Capital Budgeting (Comprehensive Spreadsheet Problem 11-23, page 408) Your division is considering two projects. Its WACC is 10%, and the projects' after-tax cash flows (in millions of dollars) would be as follows: Expected Cash Flows Time Project A Project B 0 ($30) ($30) 1 $5 $20 2 $10 $10 3 $15 $8 4 $20 $6 a.   Calculate the projects' NPVs, IRRs, MIRRs, regular paybacks, and discounted paybacks. WACC = 10% Use Excel's NPV function as explained in NPVA...

  • 1. Cash flow to creditors must be negative when: a. net new borrowings exceed the amount...

    1. Cash flow to creditors must be negative when: a. net new borrowings exceed the amount of interests paid b. the amount of dividends paid exceeds the net new borrowings. c. dividends payment exceed the interests payments. d. both the cash flow from assets and the cash flow to shareholders are negative. 2. The greater the level of debt incurred by a firm means: a. the greater the number of shares of common stock issued The higher the financial leverage...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT