Question

1. Cash flow to creditors must be negative when: a. net new borrowings exceed the amount of interests paid b. the amount of d

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1) Cash flow to creditors = Interest paid-Net new borrowing From the above formula we can say that, cash flows to creditors w

Add a comment
Know the answer?
Add Answer to:
1. Cash flow to creditors must be negative when: a. net new borrowings exceed the amount...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 14. Consider four projects with the following sequences of cash flows: n 0 NET CASH FLOWS...

    14. Consider four projects with the following sequences of cash flows: n 0 NET CASH FLOWS A B C -$25,000|-$23,000-$56,500 $12,000 $32,000 -$2,500 $23,000 $32,000-$6,459 $34,000 $25,000 $88,345 3 (a) Identify all the simple investments. (b) Identify all the non-simple investments. (c) Compute the Internal Rate of Return (IRR) for each project using NPV method and Excel. Note the following: A simple (or conventional) investment is simply when one sign change occurs in the net cash flow series. If the...

  • (Numbers in parentheses are negative) These two projects are independent. Year Cash Flow of A Cash...

    (Numbers in parentheses are negative) These two projects are independent. Year Cash Flow of A Cash Flow of B 0 ($5000) ($2000) 1 $1000 $1000 2 $2000 $1000 3 $2000 $2000 4 $2000 $1000 5 $1000 ($1000) Based on the firms' NPV profiles which project should be taken if the required rate of return is 9.5%? Project B because it will raise the value of the firm by the greatest amount based on NPV. Both projects should be taken because...

  • IRR A project's internal rate of return (IRR) is the -Select- The IRR is an estimate...

    IRR A project's internal rate of return (IRR) is the -Select- The IRR is an estimate of the project's rate of return, and it is comparable to the -Select-on a bond. The equation for calculating the IRR is: ;that forces the PV of its inflows to equal its cost. CF2 CFN 1 IRF 1 IRF 1IR CFt t-1 (1 +IRR) CFt is the expected cash flow in Period t and cash outflows are treated as negative cash flows. There must...

  •    Year Cash Flow (A) Cash Flow (B) 0 –$37,200        –$37,200        1 19,570       ...

       Year Cash Flow (A) Cash Flow (B) 0 –$37,200        –$37,200        1 19,570        7,060        2 15,070        13,560        3 12,570        20,050        4 9,570        24,050          a. What is the IRR for Project A?    b. What is the IRR for Project B?    c. If the required return is 12 percent, what is the NPV for Project A?    d. If the required return is 12 percent, what is the NPV...

  • Geraldine Consultants, Inc. is considering a project that has the following cash flows: Year Cash Flow...

    Geraldine Consultants, Inc. is considering a project that has the following cash flows: Year Cash Flow 0 -$1,000 1 400 2 300 3 500 4 400 The company's WACC is 10%. What are the project's payback, internal rate of return, and net present value? Select one: a. Payback = 2.6, IRR = 21.22%, NPV = $300. b. Payback = 2.4, IRR = 21.22%, NPV = $260. c. Payback = 2.6, IRR = 24.12%, NPV = $300. d. Payback = 2.4,...

  • Help and verified and be clear. The net present value (NPV) and internal rate of return...

    Help and verified and be clear. The net present value (NPV) and internal rate of return (IRR) methods of investment analysis are interrelated and are sometimes used together to make capital budgeting decisions. Consider the case of Blue Hamster Manufacturing Inc.: Last Tuesday, Blue Hamster Manufacturing Inc. lost a portion of its planning and financial data when both its main and its backup servers crashed. The company's CFO remembers that the internal rate of return (IRR) of Project Lambda is...

  • Show all work and highlight final answer. Do not answer the question unless you answer all...

    Show all work and highlight final answer. Do not answer the question unless you answer all of them. 4. Which one of the following will decrease the net present value of a project? (a) Increasing the value of each of the project's discounted cash inflows (b) Moving each of the cash inflows forward to a sooner time period (c) Decreasing the required discount rate (d) Increasing the project's initial cost at time zero 5. Which of the following is true...

  • Assume a project has normal (conventional) cash flows (i.e., initial cash flow is negative, and all...

    Assume a project has normal (conventional) cash flows (i.e., initial cash flow is negative, and all other cash flows are positive). Which of the following statements is most correct? All else equal, a project's IRR increases as the required rate of return declines. All else equal, a project's IRR increases as the required rate of return increases All else equal, a project's NPV increases as the required rate of return declines. None of the above Question 11 (2 points) Suppose...

  • 8) Project A has an internal rate of return (IRR) of 15 percent. Project B has...

    8) Project A has an internal rate of return (IRR) of 15 percent. Project B has an IRR of 14 percent. Both projects have a required retum of 12 percent. Which of the following statements is MOST correct? A) Project A must have a higher NPV than Project B. B) Both projects have a positive net present value (NPV) C) Project B has a higher profitability index than Project A. D) If the required return were less than 12 percent,...

  • Each of two mutually exclusive projects involves an investment of $124,000. Net cash flows for the...

    Each of two mutually exclusive projects involves an investment of $124,000. Net cash flows for the projects are as follows: Year Project A Project B 1 60,000 57,000 2 62,000 64,000 3 40,000 47,000 A.    Calculate each project's payback period. (2 Points) B.    Compute the Net Present Value (NPV) of each project when the firm's cost of capital is 10 percent. (2 Points) C.    Internal Rate of Return (IRR) -Your choice; based on your answer to part (B). (2 Points) D.    Modified Internal Rate...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT