Question

Can someone please help explain this???A company expected its annual overhead costs to be $767600 and machine hours to equal 101000 hours. Actual overhead was $7460

0 0
Add a comment Improve this question Transcribed image text
Answer #1

OPTION: $8800 underapplied

EXPLANATION:

Predetermined overhead rate = $767600/101000 = $7.6 per hour.

therefore, absorbed overheads = $7.6 x 97000 = $737200

actual overheads = $746000

therefore,

Overheads underapplied = actual overheads - absorbed overheads

= $746000 - $737200
= -$8800

Add a comment
Know the answer?
Add Answer to:
Can someone please help explain this??? A company expected its annual overhead costs to be $767600...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT