unit level cost are incurred each time unit is produced
batch level incurs when batch of goods are produced
product level costs are incurred to produce each type of product
facility level are incurred to sustain the facility general costs.
setting up machine | batch level |
inspecting components | unit level |
providing utilities | facility level |
2.cost of Job 615 ABC
Activity | cost | cost per activity |
setting up machine | 21600 | 800per batch [21600/27batches] |
inspecting componets | 5000 | $1 per part[5000/5000] |
providing utilities | 10000 | $2 per machine hour[10000/5000] |
TOTAL MANUFACTURING COST
Direct material | $2300 | |
Labor | $3600 | |
overhead | ||
setting up machine | $3200 | [$800*4] |
inspecting componets | $560 | [$1*560] |
providing utilities | $1280 | [$2*640] |
Total Manufacturing cost | $10940 | [2300+3600+3200+560+1280] |
After reading an article about activity-based costing in a trade journal for the furniture industry, Santana...
After reading an article about activity-based costing in a trade journal for the furniture industry, Santana Rey wondered if it was time to critically analyze overhead costs at Business Solutions. In a recent month, Santana found that setup costs, inspection costs, and utility costs made up most of its overhead. Additional information about overhead follows. Activity Setting up machines Inspecting components Providing utilities Cost $21,750 $5,300 $10,600 Driver 25 batches 5,300 parts 5,300 machine hours Overhead has been applied to...
After reading an article about activity-based costing in a trade journal for the furniture industry, Santana Rey wondered if it was time to critically analyze overhead costs at Business Solutions. In a recent month, Santana found that setup costs, inspection costs, and utility costs made up most of its overhead. Additional information about overhead follows. Activity Cost Driver Setting up machinfes $ 17,800 20 batches Inspecting components $ 4,900 4,900 parts Providing utilities $ 9,800 4,900 machine hours Overhead has...
Check my After reading an article about activity-based costing in a trade journal for the furniture industry, Santana Rey wondered if it was time to critically analyze overhead costs at Business Solutions. In a recent month, Santana found that setup costs, inspection costs, and utility costs made up most of its overhead. Additional information about overhead follows. Activity Setting up machines Inspecting components Providing utilities Cost $20,000 $ 7,500 $10,000 Driver 25 batches 5,000 parts 5,000 machine hours Overhead has...
questions 2 and 3 SP 17 After reading an article about activity-based costing in a trade journal for the furniture industry, Santana Rey wondered if it was time to critically analyze overhead costs at Business Solutions. In a recent month, Santana found that setup costs, inspection costs, and utility costs made up most of its overhead. Additional information about overhead follows. Activity Cost Driver Setting up machines $20,000 25 batches Inspecting components $ 7,500 5,000 parts Providing utilities $10,000 5,000...
What is the total cost of Job 615 if Business solutions applies overhead at 50% of direct labor cost? What is the total job of job 615 of business solution uses activity-based costing? SP 17 After reading an article about activity-based costing in a trade journal for the furniture industry, Santana Rey wondered if it was time to critically analyze overhead costs at Business Solutions. In a recent month, Santana found that setup costs, inspection costs, and utility costs made...
Activity Based Costing Activity Based Costing Help Save & Exit Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Indirect Tabor $320,000 Indirect Materials Other Overhead Part 2 of 3 Production Activity Grinding Polishing Product modification Providing power System calibration $135,000 600,000 $255,000 500,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification Providing power Systen calibration 1,500 engineering hours 17,000 direct...
Fischer Company identified the following activities, costs, and activity drivers: Activity Expected Costs Expected Activity Handling parts $525,000 25,000 parts in stock Inspecting product $390,000 940 batches Processing purchase orders $220,000 440 orders Designing packaging $230,000 5 models a. What is total overhead cost for Job 102 using a plantwide overhead rate assuming the company assigns overhead based on 60,000 budgeted direct labor hours (Round to two decimals)? b. What is the total overhead cost for JOB 102 using Activity...
! Required information Problem 17-3A Applying activity-based costing LO P1, P3, A1, A2, C3 [The following information applies to the questions displayed below.] Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Indirect Labor $370,000 Indirect Materials other overhead $220,000 Production Activity Grinding Polishing Product modification Providing power System calibration 550,000 $245,000 530,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification...
Required Information Problem 17-3A Applying activity-based costing LO P1, P3, A1, A2, C3 [The following Information applies to the questions displayed below.] Craft Pro Machining produces machine tools for the construction Industry. The following details about overhead costs were taken from its company records. Indirect Materials Other Overhead Indirect Labor $330,880 $175,00 Production Activity Grinding Polishing Product modification Providing power System calibration 589,800 $225,000 560,000 Additional Information on the drivers for its production activities follows. Grinding Polishing Product modification Providing...
Greife Corporation's activity-based costing system has three activity cost pools--Machining, Setting Up, and Other. The company's overhead costs have already been allocated to these cost pools as follows: Machining $ 47,250 Setting Up $ 125,354 Other $ 21,600 Costs in the Machining cost pool are assigned to products based on machine-hours (MHs) and costs in the Setting Up cost pool are assigned to products based on the number of batches. Costs in the Other cost pool are not assigned to...