Grinding | Unit level | ||||||||
Polishing | Unit level | ||||||||
Product modification | Product level | ||||||||
Providing power | Facility level | ||||||||
System calibration | Batch level | ||||||||
Computation of ABC rate | |||||||||
Job 3175 | Job 4286 | ||||||||
Activity | OH Costs(Col 1) | No. of activity base(Col 2) | Activity Rate(Col 1 / Col 2) | Activity driver incurred | Overhead assigned | Activity driver incurred | Overhead assigned | ||
Grinding & Polishing | $ 5,05,000 | 12,000 | $ 42.08 | per machine hrs | 400 | $ 16,832 | 4000 | $ 1,68,320 | |
Product modification | $ 5,00,000 | 1,600 | $ 312.50 | per engg hours | 30 | $ 9,375 | 18 | $ 5,625 | |
Providing power | $ 2,25,000 | 19,000 | $ 11.84 | per direct labor hours | 490 | $ 5,802 | 4410 | $ 52,214 | |
System calibration | $ 5,60,000 | 1,200 | $ 466.67 | per batch | 5 | $ 2,333 | 15 | $ 7,000 | |
Total Overhead Costs | $ 17,90,000 | $ 34,342 | $ 2,33,159 | ||||||
No. of units produced | 200 units | 2500 units | |||||||
Overhead Cost per unit | $ 171.71 | $ 93.26 | |||||||
Plantwide Overhead Rate =Total Manufacturing Overhead Cost / Total Direct labor hours | |||||||||
Plantwide Overhead Rate =$1,790,000 / 19000 hours =$94.21 per dlhs | |||||||||
Product | DL Hours | Plantwide Overhead Rate | Total Overhead Costs | Units Produced | OH Cost per unit | ||||
Job 3175 | 490 | $ 94.21 | $ 46,163 | 200 | $ 230.81 | ||||
Job 4286 | 4140 | $ 94.21 | $ 3,90,029 | 2500 | $ 156.01 | ||||
Required Information Problem 17-3A Applying activity-based costing LO P1, P3, A1, A2, C3 [The following Information...
! Required information Problem 17-3A Applying activity-based costing LO P1, P3, A1, A2, C3 [The following information applies to the questions displayed below.] Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Indirect Labor $370,000 Indirect Materials other overhead $220,000 Production Activity Grinding Polishing Product modification Providing power System calibration 550,000 $245,000 530,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification...
Required Information Problem 17-3A Applying activity-based costing LO P1, P3, A1, A2, C3 [The following information applies to the questions displayed below) Craft Pro Machining produces machine tools for the construction Industry. The following details about overhead costs were taken from its company records. Production Activity Indirect Labor Indirect Materials other Overhead Grinding $340,000 Polishing $190,000 Product modification 650,000 Providing power $200,000 Systen calibration 540,000 Additional Information on the drivers for its production activities follows Grinding Polishing Product modification Providing...
Problem 17-3A Applying activity-based costing LO P1, P3, A1, A2, C3 The following information applies to the questions displayed below.) Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Indirect Materials Other Overhead Production Activity Indirect Labor Grinding $360,000 Polishing Product modification 550,000 Providing power System calibration 560,000 $130,000 $250,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification Providing power System...
Problem 04-3A Applying activity-based costing LO P1, P3, A1, A2, C3 [The following information applies to the questions displayed below.] Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Production Activity Indirect Labor Indirect Materials Other Overhead Grinding $ 370,000 Polishing $ 110,000 Product modification 600,000 Providing power $ 265,000 System calibration 410,000 Additional information on the drivers for its production activities follows. Grinding 11,000 machine hours...
Required Information Problem 4-3A Applylng ectlvlty-based costing LO P1, P3, A1, A2, C3 The following Information applies to the questions displayed below Craft Pro Machining produces machlne tools for the construction Industry. The following detalls about overhead costs were taken from Its company records. Production Activity Grinding Polishing Product modification Providing power Systen calibration Indirect Labor Indirect Materials Other Overhead $358,60 55e.880 568,690 $115,880 $225,68e Additional Information on the drivers for Its production activitles follows. Grinding Polishing Product modification Providing...
Required information [The following information applies to the questions displayed below.] Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Indirect Materials Other Overhead Indirect Labor $390,000 Production Activity Grinding Polishing Product modification Providing power System calibration $185,000 650,000 $255,000 430,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification Providing power System calibration 17,000 machine hours 17,000 machine hours 2,100 engineering...
Please help complete quick! Required information (The following information applies to the questions displayed below.) Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Indirect Labor $ 400,000 Other Overhead Indirect Materials $170,000 Production Activity Grinding Polishing Product modification Providing power System calibration 650,000 $225,000 420,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification Providing power System calibration 19,000 machine hours...
[The following information applies to the questions displayed below.] Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Indirect Materials Other Overhead Indirect Labor $ 330,000 $110,000 Production Activity Grinding Polishing Product modification Providing power System calibration 600,000 $ 240,000 440,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification Providing power System calibration 10,000 machine hours 10,000 machine hours 1,900 engineering...
Question 10 Required information [The following information applies to the questions displayed below.] Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Indirect Materials Other Overhead Indirect Labor $340,000 $170,000 Production Activity Grinding Polishing Product modification Providing power System calibration 400,000 $210,000 460,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification Providing power System calibration 19,000 machine hours 19,000 machine hours...
! Required information {The following information applies to the questions displayed below.) Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Production Activity Indirect Labor Indirect Materials Other Overhead Grinding $340,000 Polishing $140,000 Product 450,000 modification Providing power $260,000 Syatem calibration 550,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification Providing power System calibration 10,000 machine hours 18,000 machine hours 2,200...