Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records.

Production Activity Indirect Labor Indirect Materials Other Overhead
Grinding $ 370,000
Polishing $ 110,000
Product modification 600,000
Providing power $ 265,000
System calibration 410,000


Additional information on the drivers for its production activities follows.

Grinding 11,000 machine hours
Polishing 11,000 machine hours
Product modification 2,100 engineering hours
Providing power 21,000 direct labor hours
System calibration 1,000 batches
Job 3175 Job 4286
Number of units 140 units 1,750 units
Machine hours 250 MH 2,500 MH
Engineering hours 26 eng. hours 36 eng. hours
Batches 25 batches 75 batches
Direct labor hours 450 DLH 4,050 DLH

Problem 04-3A Part 5

Required:
5.
If the company uses a plantwide overhead rate based on direct labor hours, what is the overhead cost for each unit of Job 3175? Of Job 4286? (Do not round intermediate calculations. Round "OH Cost per unit" answers to 2 decimal places.)

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Production Activity Indirect labor Indirect materials Other Overhead Total
Grinding 370,000 370,000
Polishing 110,000 110,000
Product modification 600,000 600,000
Providing power 265,000 265,000
System calibration 410,000 410,000
Total 1,380,000 110,000 265,000 1,755,000

Total budgeted overheads = $1,755,000

Budgeted direct labor hours = 21,000

Predetermined overhead rate = Total budgeted overheads / Budgeted direct labor hour

= 1,755,000/21,000

= $83.5714285714 per direct labor hour

Overhead allocated to job 3175 = Actual direct labor hour x Predetermined overhead rate

= 450 x 83.5714285714

= $37,607

Overhead allocated to job 4286 = Actual direct labor hour x Predetermined overhead rate

= 4,050 x 83.5714285714

= $338,464

Overhead cost per unit of job 3175 = Overhead allocated to job 3175 / Number of units in job 3175

= 37,607/140

= $268.62

Overhead cost per unit of Job 4286 = Overhead allocated to job 4286/ Number of units in job 4286

= 338,464/1,750

= $193.41

Kindly comment if you need further assistance. Thanks‼!

Add a comment
Know the answer?
Add Answer to:
Problem 04-3A Applying activity-based costing LO P1, P3, A1, A2, C3 [The following information applies to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • ! Required information Problem 17-3A Applying activity-based costing LO P1, P3, A1, A2, C3 [The following...

    ! Required information Problem 17-3A Applying activity-based costing LO P1, P3, A1, A2, C3 [The following information applies to the questions displayed below.] Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Indirect Labor $370,000 Indirect Materials other overhead $220,000 Production Activity Grinding Polishing Product modification Providing power System calibration 550,000 $245,000 530,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification...

  • Required Information Problem 17-3A Applying activity-based costing LO P1, P3, A1, A2, C3 [The following Information...

    Required Information Problem 17-3A Applying activity-based costing LO P1, P3, A1, A2, C3 [The following Information applies to the questions displayed below.] Craft Pro Machining produces machine tools for the construction Industry. The following details about overhead costs were taken from its company records. Indirect Materials Other Overhead Indirect Labor $330,880 $175,00 Production Activity Grinding Polishing Product modification Providing power System calibration 589,800 $225,000 560,000 Additional Information on the drivers for its production activities follows. Grinding Polishing Product modification Providing...

  • Required Information Problem 17-3A Applying activity-based costing LO P1, P3, A1, A2, C3 [The following information...

    Required Information Problem 17-3A Applying activity-based costing LO P1, P3, A1, A2, C3 [The following information applies to the questions displayed below) Craft Pro Machining produces machine tools for the construction Industry. The following details about overhead costs were taken from its company records. Production Activity Indirect Labor Indirect Materials other Overhead Grinding $340,000 Polishing $190,000 Product modification 650,000 Providing power $200,000 Systen calibration 540,000 Additional Information on the drivers for its production activities follows Grinding Polishing Product modification Providing...

  • Required Information Problem 4-3A Applylng ectlvlty-based costing LO P1, P3, A1, A2, C3 The following Information...

    Required Information Problem 4-3A Applylng ectlvlty-based costing LO P1, P3, A1, A2, C3 The following Information applies to the questions displayed below Craft Pro Machining produces machlne tools for the construction Industry. The following detalls about overhead costs were taken from Its company records. Production Activity Grinding Polishing Product modification Providing power Systen calibration Indirect Labor Indirect Materials Other Overhead $358,60 55e.880 568,690 $115,880 $225,68e Additional Information on the drivers for Its production activitles follows. Grinding Polishing Product modification Providing...

  • Problem 17-3A Applying activity-based costing LO P1, P3, A1, A2, C3 The following information applies to...

    Problem 17-3A Applying activity-based costing LO P1, P3, A1, A2, C3 The following information applies to the questions displayed below.) Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Indirect Materials Other Overhead Production Activity Indirect Labor Grinding $360,000 Polishing Product modification 550,000 Providing power System calibration 560,000 $130,000 $250,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification Providing power System...

  • 9 ! Part 1 of 3 3 Required information [The following information applies to the questions...

    9 ! Part 1 of 3 3 Required information [The following information applies to the questions displayed below.] Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Production Activity Indirect Labor Indirect Materials Other Overhead Grinding $370,000 Polishing $180,000 Product modification 550,000 Providing power $230,000 Systen calibration 550,000 points 04:36:22 Skipped Additional information on the drivers for its production activities follows, eBook Grinding Polishing Product modification Providing...

  • 10 Part 2 of 3 3 points Required information [The following information applies to the questions...

    10 Part 2 of 3 3 points Required information [The following information applies to the questions displayed below.) Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Production Activity Indirect Labor Indirect Materials Other Overhead Grinding $370,000 Polishing $180,000 Product modification 550,000 Providing power $230,000 System calibration 550,000 8 4:35.07 Skipped Additional Information on the drivers for its production activities follows. eBook Grinding Polishing Product modification Providing...

  • Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs...

    Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Production Activity Indirect Labor Indirect Materials Other Overhead Grinding $ 370,000 Polishing $ 110,000 Product modification 600,000 Providing power $ 265,000 System calibration 410,000 Additional information on the drivers for its production activities follows. Grinding 11,000 machine hours Polishing 11,000 machine hours Product modification 2,100 engineering hours Providing power 21,000 direct labor hours System calibration 1,000 batches Job...

  • ! Required information {The following information applies to the questions displayed below.) Craft Pro Machining produces...

    ! Required information {The following information applies to the questions displayed below.) Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Production Activity Indirect Labor Indirect Materials Other Overhead Grinding $340,000 Polishing $140,000 Product 450,000 modification Providing power $260,000 Syatem calibration 550,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification Providing power System calibration 10,000 machine hours 18,000 machine hours 2,200...

  • Craftmore Machining produces machine tools for the construction industry. The following details about overhead costs were...

    Craftmore Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Production Activity Indirect Labor Indirect Materials Other Overhead Grinding $ 360,000 Polishing $ 215,000 Product modification 550,000 Providing power $ 255,000 System calibration 440,000 Additional information on the drivers for its production activities follows. DRIVERS Grinding and Polishing 11,000 machine hours Product modification 1,900 engineering hours Providing power 21,000 direct labor hours System calibration 1,300 batches Required: 1. Compute...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT