Under the plant-wide overhead rate, single overhead is
calculated and used for the whole company on a single basis. Hence
the single overhead rate for whole company based on machine hours
is as follows:
Total overhead cost = $430,000 + $657,900 = $1,087,900
Total machine hours = 430,000 + 64,500 = 494,500
Plantwide overhead rate = Total overhead cost / Total machine
hours
= $1,087,900 / 494,500
= $2.2 per machine hour
Total overhead allocated to product = (Assembly dept. machine
hours + Finished dept. machine hours) * Overhead rate
= (2.5 hours + 0.5 hours) * $2.2
= $6.6
Hence the answer is $6.6.
So please check your options available as these options are not
correct as per answer calculated on basis of question details
given.
C) 7.50 D) 10.50 Required information [The following information applies to the questions displayed below.) Angle...
(The following information applies to the questions displayed below.) Angle Max Industries produces a product which goes through two operations, Assembly and Finishing, before it is ready to be shipped. Next year's expected costs and activities are shown below. Direct labor hours Machine hours Overhead costs Assembly 140,000 DLH 340,000 MH $340,000 Finishing 144,000 DLH 74,800 MH $489,600 Assume that the Assembly Department allocates overhead based on machine hours, and the Finishing Department allocates overhead based on direct labor hours....
Required information [The following information applies to the questions displayed below.) Angle Max Industries produces a product which goes through two operations, Assembly and Finishing, before it is ready to be shipped. Next year's expected costs and activities are shown below. Direct labor hours Machine hours Overhead costs Assembly 290,000 DLH 490,000 MH $ 490,000 Finishing 159,000 DLH 144, 550 MH $779,100 Assume that Angle Max Industries allocates overhead using a plantwide overhead rate based on machine hours. How much...
! Required information [The following information applies to the questions displayed below.) Angle Max Industries produces a product which goes through two operations, Assembly and Finishing, before it is ready to be shipped. Next year's expected costs and activities are shown below. Direct labor hours Machine hours Overhead costs Assembly 290,000 DLH 490,000 MH $ 490,000 Finishing 159,000 DLH 144,550 MH $779,100 Assume that the Assembly Department allocates overhead based on machine hours, and the Finishing Department allocates overhead based...
Required information [The following information applies to the questions displayed below.) Angle Max Industries produces a product which goes through two operations, Assembly and Finishing, before it is ready to be shipped. Next year's expected costs and activities are shown below. Direct labor hours Machine hours Overhead costs Assembly 100,000 DLH 3ee, MH $300,000 Finishing 140,000 DLH 60, еее мн $420, eee Assume that the Assembly Department allocates overhead using a plantwide overhead rate based on machine hours. How much...
Required information [The following information applies to the questions displayed below.] Angle Max Industries produces a product which goes through two operations, Assembly and Finishing, before it is ready to be shipped. Next year's expected costs and activities are shown below. Assembly Finishing Direct labor hours 189, eeeDLH 140,000 DLH Machine hours Зее, еве МН 60, eee MH $300,000 $420,000 Overhead costs Assume that the Assembly Department allocates overhead based on machine hours, and the Finishing Department allocates overhead based...
Required information SB Angle Max Industries produces a product... [The following information applies to the questions displayed below.] Angle Max Industries produces a product which goes through two operations, Assembly and Finishing, before it is ready to be shipped. Next year’s expected costs and activities are shown below. Assembly Finishing Direct labor hours 190,000 DLH 149,000 DLH Machine hours 390,000 MH 95,550 MH Overhead costs $ 390,000 $ 581,100 TB MC Qu. 17-117 Assume that the Assembly Department allocates... Assume...
y Saudents Cn 17/ thru 20 Help Seve&Exit Required informetion (The following information applies to the questions displayed below) Angle Max Industries produces a product which goes through two operations, Assembly and Finishing, before it is ready to be shipped. Next year's expected costs and activities are shown below Finliklng 341,00 OLN ,sse $437,10 Assenbly 110,00 10,00 $310,000 Direct laber hours i Hachine hour s Overhead costs Assume that the Assembly Degpartment allocates overhead using a plantwide overhead rate based...
Angle Max Industries produces a product which goes through two operations, Assembly and Finishing, before it is ready to be shipped. Next year’s expected costs and activities are shown below. Assembly Finishing Direct labor hours 250,000 DLH 155,000 DLH Machine hours 450,000 MH 60,000 MH Overhead costs $ 450,000 $ 697,500 Assume that the Assembly Department allocates... Assume that the Assembly Department allocates overhead based on machine-hours, and the Finishing Department allocates overhead based on direct labor hours. How much...
rt 1 of 2 Required information SB Angle Max Industries produces a product... The following information applies to the questions displayed below) Angle Max Industries produces a product which goes through two operations, Assembly and Finishing, before it is ready to be shipped. Next year's expected costs and activities are shown below Assembly Finishing Direct labor hours 190,000 DLH 149,000 DLH Machine hours 390,000 MH 95,550 MH Overhead costs $390,000 $581,100 nts eBook TB MC Qu. 17-117 Assume that the...
Required information [The following information applies to the questions displayed below.] Tarnish Industries produces miniature models of farm equipment. These collectibles are in great demand. It takes two operations, molding and finishing, to complete the miniatures. Next year's expected activities are shown in the following table: Molding Finishing Direct labor hours 79,000 DLH 164,500 DLH Machine hours 102,000 MH 85,500 MH Tarnish Industries uses departmental overhead rates and is planning on a $2 per direct labor hour overhead rate for...