Sanchez & Company produces paints. On July 1, it had no work-in-process inventory. It starts production of 111,000 gallons of paint in July and completes 88,000 gallons. The costs of the resources used by Sanchez in July consist of the following:
Materials | $ | 209,398 |
Conversion costs (labor and overhead) | 281,100 | |
Required:
The production supervisor estimates that the ending work-in-process is 81 percent complete. Compute the cost of paint transferred to finished goods and the amount in work-in-process ending inventory as of July 31. (Do not round intermediate calculations.)
Solution
Transferred out | $ 397,996 |
Work in process | $ 92,502 |
Working
Reconciliation of Units | ||
A | Beginning WIP | - |
B | Introduced | 111,000 |
C=A+B | TOTAL | 111,000 |
D | Transferred out | 88,000 |
E=C-D | Ending WIP | 23,000 |
.
Statement of Equivalent Units(Weighted average) | |||||||
Material | Conversion cost | ||||||
Units | Complete % | Equivalent units | Complete % | Equivalent units | |||
Transferred out | 88,000 | 100% | 88,000 | 100% | 88,000 | ||
Ending WIP | 23,000 | 100% | 23,000 | 81% | 18,630 | ||
Total | 111,000 | Total | 111,000 | Total | 106,630 |
.
Cost per Equivalent Units (Weighted average) | ||||
COST | Material | Conversion cost | TOTAL | |
Beginning WIP Inventory Cost | $ 0 | |||
Cost incurred during period | $ 209,398 | $ 281,100 | $ 490,498 | |
Total Cost to be accounted for | $ 209,398 | $ 281,100 | $ 490,498 | |
Total Equivalent Units | 111,000 | 106,630 | ||
Cost per Equivalent Units | $ 1.89 | $ 2.64 | $ 4.52 |
.
Statement of cost (Weighted average) | |||||
Cost | Equivalent Cost/unit | Ending WIP | Transferred | ||
Units | Cost Allocated | Units | Cost Allocated | ||
Material | $ 1.89 | 23,000 | $ 43,388.77 | 88,000 | $ 166,009.23 |
Conversion cost | $ 2.64 | 18,630 | $ 49,112.75 | 88,000 | $ 231,987.25 |
TOTAL | $ 490,498 | TOTAL | $ 92,502 | TOTAL | $ 397,996 |
Sanchez & Company produces paints. On July 1, it had no work-in-process inventory. It starts production...
Sanchez & Company produces paints. On July 1, it had no work-in-process inventory. It starts production of 111,000 gallons of paint in July and completes 86,000 gallons. The costs of the resources used by Sanchez in July consist of the following: Materials $ 293,650 Conversion costs (labor and overhead) 280,100 Required: The production supervisor estimates that the ending work-in-process is 81 percent complete. Compute the cost of paint transferred to finished goods and the amount in work-in-process ending inventory as...
Sanchez & Company produces paints. On July 1, it had no work-in-process inventory. It starts production of 107,000 gallons of paint in July and completes 82,000 gallons. The costs of the resources used by Sanchez in July consist of the following: Materials Conversion costs 192,775 287,800 (labor and overhead) Required: The production supervisor estimates that the ending work-in-process is 81 percent complete. Compute the cost of paint transferred to finished goods and the amount in work-in-process ending inventory as of...
Sanchez & Company produces paints. On July 1, it had no work-in-process inventory. It starts production of 107,000 gallons of paint in July and completes 89,000 gallons. The costs of the resources used by Sanchez in July consist of the following Materials Conversion costs (labor and overhead) S 271,660 270,700 Required The production supervisor estimates that the ending work-in-process is 85 percent complete. Compute the cost of paint transferred to finished goods and the amount in work-in-process ending inventory as...
1. Tiger Furnishings produces two models of cabinets for home theater components, the Basic and the Dominator. Data on operations and costs for March follow: Basic Dominator Total Units produced 1,250 150 1,400 Machine-hours 5,000 2,000 7,000 Direct labor-hours 4,000 2,000 6,000 Direct materials costs $ 11,000 $ 3,500 $ 14,500 Direct labor costs 63,000 35,000 98,000 Manufacturing overhead costs 170,422 Total costs $ 282,922 Required: Compute the individual product costs per unit assuming that Tiger Furnishings uses machine-hours to...
Sara's Sodas produces a popular soft drink. Operating data for January follow Materials Labor Manufacturing overhead $ 640,000 100,000 2,900,000 Sara's Sodas produced 14 million liters of the beverage in January Required: Compute the cost per liter of beverage produced in January (Round your answer to 2 decimal places.) Cost per liter Sanchez & Company produces paints. On July 1, it had no work-in-process inventory. It starts production of 98,000 gallons of paint in July and completes 79,000 gallons. The...
Graham Petroleum produces oil. On May 1, it had no work-in-process inventory. It started production of 205 million barrels of oil in May and shipped 185 million barrels in the pipeline. The costs of the resources used by Graham in May consist of the following: Materials $ 3,004 million Conversion costs (labor and overhead) $ 3,300 million Required: The production supervisor estimates that the ending work in process is 60 percent complete on May 31. Compute the cost of oil...
Graham Petroleum produces oil. On May 1, it had no work-in-process inventory. It started production of 201 million barrels of oil in May and shipped 181 million barrels in the pipeline. The costs of the resources used by Graham in May consist of the following: Materials Conversion costs (labor and overhead) $2,174 million $3,230 million Required: The production supervisor estimates that the ending work in process is 60 percent complete on May 31. Compute the cost of oil shipped in...
Graham Petroleum produces oil. On May 1, it had no work-in-process inventory. It started production of 215 million barrels of oil in May and shipped 185 million barrels in the pipeline. The costs of the resources used by Graham in May consist of the following: Materials $ 2,532 million Conversion costs (labor and overhead) $ 3,320 million Required: The production supervisor estimates that the ending work in process is 80 percent complete on May 31. Compute the cost of oil...
Graham Petroleum produces oil. On May 1, It had no work-in-process Inventory. It started production of 199 million barrels of oil in May and shipped 174 million barrels In the pipeline. The costs of the resources used by Graham In May consist of the following: Materials Conversion costs (labor and overhead) $2,658 million $3.399 million Required: The production supervisor estimates that the ending work in process is 60 percent complete on May 31. Compute the cost of oil shipped in...
Joplin Corporation produces syrups that it sells to candy makers. On November 1, it had no work-in-process inventory. It started production of 46,200 gallons of syrup in November and completed production of 44,000 gallons. The costs of the resources used by Joplin in November consist of the following: Materials $ 64,604 Conversion costs (labor and overhead) 53,800 Required: The production supervisor estimates that the ending work-in-process is 70 percent complete on November 30. Compute the cost of syrup completed and...