2021
% of completion = cost incurred till now / total estimated cost
= $3000000/($3000000+$6000000)
= 33.33%
So revenue to be recognized = $12000000*33.33% = $4000000
Answer is option A.
2022
% completion = ($5000000+$3000000)/($3000000+$5000000+$2000000)
= 80%
Total revenue to be recognized = $1200000*80% = $9600000
Revenue already recognized in 2021 = $4000000
Revenue to be recognized in 2022 = $9600000 - $4000000
= $5600000
Answer is option b.
2023
Cost completion = 100%
Revenue to be recognized total = $12000000
Revenue already recognized till now = $9600000
Revenue to be recognized in 2023 = $2400000
Answer is option C.
Feel free to ask any queries..
Also plz upvote it means a lot ..thank you
LO5-9 Concept Check: Revenue Recognition Over Time Robertson Construction entered into a contract to construct a...
LOS-9 Concept Check: Percentage Completion Robertson Construction entered into a contract to construct a tunnel for a fixed price of $12,000,000. Robertson recognizes revenue over time according to percentage of completion. Here are some facts: Estimated Additional Cost to Complete $6,000,000 6,500,000 Cost Incurred $ 3,000,000 500,000 6,500,000 2021 2022 2023 What is Robertson's percentage completion in 2021? a. b. c. d. 5% 35% 65% 100% LO5-9 Concept Check: Percentage Completion (2) Robertson Construction entered into a contract to construct...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate recognizes revenue over time according to...
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9) The following information applies to the questions displayed below) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $1,870,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021...
Brief Exercise 5-33 Long-term contract; revenue recognition upon completion [LO5-9] A construction company entered into a fixed-price contract to build an o million. Construction costs incurred during the first year were $18 million and estimated costs to complete at the end of the year were $27 million. The building was completed during the second year. Construction costs incurred during the second year were $28 million. ng How much revenue and gross profit or loss will the company recognize in the...
Exercise 6-20 (Algo) Long-term contract; revenue recognition over time vs. upon project completion [LO6-9] On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $390 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated...
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9] The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $ 2,640,000...
Help In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,613,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,016,000 5,184,000 2,180,000 1,890,000 2022 $2,808,000 2,376,000 2,644,000 2,500,000 0 5,176,000 5,610,000 Westgate recognizes revenue over time according to percentage of...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,200,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,400,000 5,600,000 2,000,000 1,800,000 2022 $3,600,000 2,000,000 4,000,000 3,600,000 4,000,000 4,600,000 Assume that Westgate Construction's contract with Santa Clara County does not...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $320 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 80 $ 40 $ 90 Estimated costs to complete as of...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $320 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 80 $ 40 $ 90 Estimated costs to complete as of...