Question

27. The cost of production of completed and finished goods during the period amounted to $450,000, and the finished products
0 0
Add a comment Improve this question Transcribed image text
Answer #1

27. c. Cost of goods sold                357,000

                Finished goods                                  357,000

The cost of goods sold is to be debited to finished goods when finished goods is transferred to cost of goods sold. The total cost of production is irrelevant as it also results in work in process. Only the amount that is transferred to finished goods from production is relevant after giving due for work in process. SO, the correct option is c.

28.

Job 360 has not been completed yet,. Hence it is work in process.

Ending balance of work in process = Job 360 = $ 456

The correct option is b. $ 456.

29.

Job 356 & Job 357 has been sold. Hence, the cost of goods sold will include their balance

Balance of cost of goods sold = Job 356 + Job 357 = 450 + 1235 = $ 1685

The correct option is c. $ 1685.

30.

Gross Margin is the profit from the two jobs sold i.e. Job 356 and job 357 for $ 500 each , so $1,000.

The correct option is c. $ 1000.

31

FIFO means first units get out first.

This means that for opening balance where 60% completed, 40% work need to be done. This 600 units is included in the units completion.

Equivalent units

Units

Opening balance (600 *40%)

240

Completed during the year (6000-600)

5400

Ending balance (700*30%)

210

Equivalent units for conversion

5850

Hence, correct option is d. 5850

kindly upvote

Add a comment
Know the answer?
Add Answer to:
27. The cost of production of completed and finished goods during the period amounted to $450,000,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Adams Company is a manufacturing company that has worked on several production jobs during the first...

    Adams Company is a manufacturing company that has worked on several production jobs during the first quarter of the year. Below is a list of all the jobs for the quarter: Balance Job 356 $450     Job 357 1,235     Job 358 378     Job 359 689     Job 360 456     Jobs 356, 357, 358, and 359 were completed. Jobs 356 and 357 were sold at a profit of $500 on each job. What is the gross profit for Adams Company at the end...

  • Adams Company is a manufacturing company that has worked on several production jobs during the first...

    Adams Company is a manufacturing company that has worked on several production jobs during the first quarter of the year. Below is a list of all the jobs for the quarter: Balance $450 Job 356 Job 357 Job 358 1,235 378 689 456 Job 359 Job 360 Jobs 356, 357 358 and 359 were completed. Jobs 356 and 357 were sold at a profit of $500 on each job. What is the ending balance of cost of Goods Sold for...

  • 31. The amount of time spent by an employee in the factory is usually recorded on...

    31. The amount of time spent by an employee in the factory is usually recorded on a. time tickets b. employees' earnings records c. statement of owners' equity d. job order cost sheets 32. When Job 117 was completed, direct materials totaled $4,400; direct labor, $5,600; and factory overhead, $2,400. A total of 1,000 units were produced at a per-unit cost of a. $124 b. $12,400 c. $1,240 d. $12.40 33. Materials purchased on account during the month amounted to...

  • Chapter 17- the cost of production of completed jobs moved to finished goods doing the period amounted to $600,000, and...

    Chapter 17- the cost of production of completed jobs moved to finished goods doing the period amounted to $600,000, and the finished products shipped to customer had total production (job cost) cost of $397,000. What is the cost of the goods sold?

  • Chapter 17- the cost of production of completed jobs moved to finished goods doing the period...

    Chapter 17- the cost of production of completed jobs moved to finished goods doing the period amounted to $600,000, and the finished products shipped to customer had total production (job cost) cost of $397,000. What is the cost of the goods sold? What is the cost of the finished goods?

  • 14. The cost of production of completed and finished goods during the period amou to $...

    14. The cost of production of completed and finished goods during the period amou to $ 400,000 and the finished products shipped to customers had total production cost $ 337,000. From the following, select the entry to record the transfer of costs from fini goods to Cost of Goods Sold. (2 pts) A. COGS 337,000 Finished Goods Shipped to customers. 337,000 B. Finished Goods 337,000 Work in Process Finished all jobs on the line. 337,000 C. Work in Process 400,000...

  • Finished Goods and Cost of Goods Sold Before the completed production for August is recorded, the...

    Finished Goods and Cost of Goods Sold Before the completed production for August is recorded, the work in process inventory account for Bayfield Company appears as follows: Work in Process Inventory Balance August 1 $15,000 Direct material 33,000 Direct labor 20,000 Manufacturing overhead applied 20,000 Assume that completed production for August includes Jobs 317, 318, and 319 with total costs of $31,000, $18,000, and $22,000, respectively. QUESTION 10 Partially correct Mark 12.00 out of 19.00P Flag question Finished Goods and...

  • E2-11 (Algo) Calculating Cost of Jobs in Work in Process, Finished Goods, and Cost of Goods...

    E2-11 (Algo) Calculating Cost of Jobs in Work in Process, Finished Goods, and Cost of Goods Sold [LO 2- Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A...

  • apter 21 E2-11 (Algo) Calculating Cost of Jobs in Work in Process, Finished Goods, and Cost...

    apter 21 E2-11 (Algo) Calculating Cost of Jobs in Work in Process, Finished Goods, and Cost of Goods Sold [LO 2- Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April Jobs A and B were in process at the beginning of April....

  • Match the phrase to the right answer. (finished goods, actual, cost of goods manufactured, work in...

    Match the phrase to the right answer. (finished goods, actual, cost of goods manufactured, work in process, direct, estimated, raw materials inventory, cost of goods sold, allocated, and timecard) - Accounts where job are born - Type of labor incurred by hands on factory workers - Document for capturing labor hours - Type of Overhead put into WIP when using Job Costing - Landing place for sold jobs - Cost of finished products for the period - Location of all...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT