Question

       Budget   Actual Units produced        10,000    11,050 Materials used in production         &nbs

       Budget

  Actual

Units produced

       10,000

   11,050

Materials used in production

            400 kg

            ?

Material Costs

$      8,000

            ?

Direct Labour (Hours)

      35,000 hrs

    41,010 hrs

Direct Labour Costs

$  385,000

$450,951

Variable Overhead Costs

$  350,000

$411,441

Fixed Overhead Costs

$  160,000

$136,358

Other Information

Overhead is Allocated on Direct Labour Hours

During the year, 602 kg of materials were purchased for $12,000

Beginning Direct Material Inventory:  none

Ending Direct Material Inventory:     39kg

Required:    Calculate the following variances

  1. Material Rate
  2. Material Efficiency
  3. Labour Price
  4. Labour Efficiency
  5. Variable Overhead Rate
  6. Variable Overhead Efficiency
  7. Fixed Overhead Rate
  8. Fixed Overhead Production Volume
0 0
Add a comment Improve this question Transcribed image text
Answer #1

A. Material rate variance = Actual cost - Actual Quantity x Standard rate
= $12000 - 602 x $20 = $40 (F)
Standard Rate = $8000 / 400 = $20 per kg

B. Material Efficiency Variance = (Actual Quantity used - Standard Quantity) x Standard Rate
= (563 - 442) x $20 = $2420 (U)
Actual Quantity used = 602-39 = 563
Standard Quantity = 400/10000x11050 = 442

C. Labor Price Variance = Actual Cost - Standard rate x Actual hours
= $450951 - 41010 x $11 = $159 (F)
Standard rate = $385000/35000 = $11 per hour

D. Labor efficiency Variance = (Actual hours - Standard hours) x Standard rate
= (41010 - 38675) x $11 = $25685 (U)
Standard hours = 35000/10000 x 11050 = 38675

As per HOMEWORKLIB RULES we are supposed to solve 4 parts, i have done 4 parts, so kindly post other parts separately

Add a comment
Know the answer?
Add Answer to:
       Budget   Actual Units produced        10,000    11,050 Materials used in production         &nbs
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A manufacturer had the following information:        Budget Actual Units produced        10,000    11,050 Materials used...

    A manufacturer had the following information:        Budget Actual Units produced        10,000    11,050 Materials used in production             400 kg             ? Material Costs $      8,000             ? Direct Labour (Hours)       35,000 hrs     41,010 hrs Direct Labour Costs $ 385,000 $450,951 Variable Overhead Costs $ 350,000 $411,441 Fixed Overhead Costs $ 160,000 $136,358 Other Information Overhead is Allocated on Direct Labour Hours During the year, 602 kg of materials were purchased for $12,000 Beginning Direct Material Inventory:...

  • please full calculation and explanation. Containers, Inc. produced 62,500 and sold 59,000 plastic microcomputer cases at...

    please full calculation and explanation. Containers, Inc. produced 62,500 and sold 59,000 plastic microcomputer cases at a selling price of 510.00 each. Manufacturing overhead is allocated on the basis of machine hours. The standard variable costs per computer case were: Quantity 1.5 kg Total Rate Direct Materials Direct Labour Variable Overhead $1.20 per kg $15.00 per hour $6.00 per hour $1.80 0.50 labour hours 7,50 0.20 machine hours 1.20 Information regarding fixed overhead includes the following: Budgeted Fixed Overhead: $337,500...

  • please full calculation and explanations Containers, Inc. produced 62.500 and sold 59.000 plastic microcomputer cases at...

    please full calculation and explanations Containers, Inc. produced 62.500 and sold 59.000 plastic microcomputer cases at a selling price of $10.00 each. Manufacturing overhead is allocated on the basis of machine hours. The standard variable costs per computer case were: Quantity Rate Total Direct Materials 1.5 kg $ 1.20 per kg $1.80 Direct Labour 0.50 labour hours $15.00 per hour 7.50 Variable Overhead 0.20 machine hours $6.00 per hour 1.20 Information regarding fixed overhead includes the following: Budgeted Fixed Overhead:...

  • please full calculation and explanation Containers, Inc. produced 62,500 and sold 59.000 plastic microcomputer cases at...

    please full calculation and explanation Containers, Inc. produced 62,500 and sold 59.000 plastic microcomputer cases at a selling price on 10.00 each. Manufacturing overhead is allocated on the basis of machine hours. The standard variable costs Per computer case were: Total Quantity Rate Direct Materials 1.5 kg $ 1.20 per kg $1.80 Direct Labour 0.50 labour hours $ 15.00 per hour 7.50 Variable Overhead 0.20 machine hours $ 6.00 per hour 1.20 Information regarding fixed overhead includes the following: Budgeted...

  • Question 5 (23 marks) Cleanup Ltd produces an industrial chemical and uses a standard costing system...

    Question 5 (23 marks) Cleanup Ltd produces an industrial chemical and uses a standard costing system to keep tight control over its costs. At the beginning of 2017, the following standard cost sheet (for one unit) was prepared: Direct materials (10kg @ $1.60/kg) Direct labour (0.75 hrs @$18.00hr) Fixed overhead (? /hr) Variable overhead (? /hr) Standard cost per unit $16.00 13.50 3.00 2.25 $34.75 Manufacturing overhead is allocated based on direct labour hours. The budgeted overhead rate is determined...

  • Question 1 (40 marks) Magnate Ltd is a manufacturing company which produces a fixed budget for...

    Question 1 (40 marks) Magnate Ltd is a manufacturing company which produces a fixed budget for planning purposes. Set out below is the monthly fixed budget of production costs, together with the actual results observed for the month of November 2019. Budget Actual Units produced 5,000 5,500 £ £ Cost Direct material 20,000 22,764 Direct labour 60,000 75,900 Variable Production overhead 14,000 14,950 Fixed Production overhead 10,000 9,000 Depreciation 4,000 4,000 In preparing the flexed budget, the following standards were...

  • tic microcomputer cases at a selling price of $10.00 machine hours. The standard variable costs per...

    tic microcomputer cases at a selling price of $10.00 machine hours. The standard variable costs per Containers, Inc. produced 62,500 and sold 59,000 plastic micr each. Manufacturing overhead is allocated on the basis of machine hours. computer case were: Quantity Rate Direct Materials 1.5 kg $ 1.20 per kg Direct Labour 0.50 labour hours $ 15.00 per hour Variable Overhead 0.20 machine hours $6.00 per hour Total $1.80 7.50 1.20 Information regarding fixed overhead includes the following: Budgeted Fixed Overhead:...

  • ABC Manufacturing Company's costing system has two direct cost categories: direct materials and direct manufacturing labour....

    ABC Manufacturing Company's costing system has two direct cost categories: direct materials and direct manufacturing labour. Manufacturing overhead (both variable and fixed) is allocated to products on the basis of standard DMLH At the beginning of 2018, ABC adopted the following standards for its manufacturing costs: Input Cost per Output Unit S 15 75 3 kg at $5 per kg 5 hours at $15 per hour Direct materials Direct manufacturing labour Manufacturing overhead: Variable Fixed Standard manufacturing cost per output...

  • Rogen uses the standard cost system. The Static original budgeted production was 5,000 units for October....

    Rogen uses the standard cost system. The Static original budgeted production was 5,000 units for October. The Input standards were: Std Quantity * Std Price per input =Std Cost per Output U Direct materials 1 lb./Output unit x $7/lb. = $7 per output unit Direct labor 1.6 hrs. /Output unit x $12 /hr. = $19.20 per unit Variable manufacturing (Mfg.) overhead 1.6 hrs. * $7.50 per hr = $12 per unit Fixed mfg. overhead (Budget $20,000) 1.6 hrs.. x $2.50...

  • Rogen uses the standard cost system. The Static original budgeted production was 5,000 units for October....

    Rogen uses the standard cost system. The Static original budgeted production was 5,000 units for October. The Input standards were: Std Quantity x Std Price per input =Std Cost per Output U Direct materials 1 lb./Output unit x $7/lb. = $7 per output unit Direct labor 1.6 hrs. /Output unit x $12/hr. = $19.20 per unit Variable manufacturing (Mfg.) overhead 1.6 hrs. x $7.50 per hr = $12 per unit Fixed mfg. overhead (Budget $20,000) 1.6 hrs.. x $2.50 per...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT