Question

I Oak Creek Furniture Factory (OCFF, a custom furniture manufacturer, uses job order costing to track the cost of each custom
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1) Calculate cost

Job 33 Job 34 Job 35
Beginning balance 5100 4900
Direct material 2600 2200 4900
Direct labor 5500 3300 2100
Applied overhead 3300 1980 1260
Total manufacturing cost 16500 12380 8260

2) Balance

Work in process 8260
Finished goods 12380
Cost of goods sold 16500
Add a comment
Know the answer?
Add Answer to:
I Oak Creek Furniture Factory (OCFF, a custom furniture manufacturer, uses job order costing to track...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the...

    Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the cost of each customer order. On March 1, OCFF had two jobs in process with the following costs: Work in Process Balance on 3/1 Job 33 $ 4,600 Job 34 4,200 $ 8,800 Source documents revealed the following during March:          Materials Requisitions Forms Labor Time Tickets Status of Job at Month-End Job 33 $ 3,900 $ 5,300 Completed and sold Job 34 2,400 4,100...

  • Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the...

    Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the cost of each customer order. On March 1, OCFF had two jobs in process with the following costs: Work in Process Balance on 3/1 Job 33 $ 5,700 Job 34 4,600 $ 10,300 Source documents revealed the following during March:          Materials Requisitions Forms Labor Time Tickets Status of Job at Month-End Job 33 $ 3,900 $ 4,700 Completed and sold Job 34 2,900 4,500...

  • Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the...

    Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the cost of each customer order. On March 1, OCFF had two jobs in process with the following costs: Work in Process Job 33 Job 34 Balance on 3/1 $ 7,500 6, eee $ 13,500 Source documents revealed the following during March Materials Requisitions Labor Time Forms Tickets Status of Job at Month-End Job 33 $ 3,500 $ 6,50e Completed and sold Job 34 6,eee...

  • Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the...

    Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the cost of each customer order. On March 1, OCFF had two jobs in process with the following costs Work in Process Balance on 3/1 $ 4,400 Job 33 Job 34 $ 8,000 Source documents revealed the following during March Materials Labor Time Requisitions Tickets Forms 2,500 4,300 Completed and sold Status of Job at Month-End Job 33 Job 34 Job 35 Indirect 3,000 4,500...

  • Can someone please help with this problem? Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer,...

    Can someone please help with this problem? Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the cost of each customer order. On March 1, OCFF had two jobs in process with the following costs: Work in Process Job 33 Job 34 Balance on 3/1 $ 4,800 5,000 $9,800 Source documents revealed the following during March: Materials Requisitions Labor Time Forms Tickets Status of Job at Month-End Job 33 $ 3,300 $5,300 Completed and...

  • E2-2 (Algo) Preparing Journal Entries [LO 2-S1) Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer,...

    E2-2 (Algo) Preparing Journal Entries [LO 2-S1) Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the cost of each customer On March 1, OCFF had two jobs in process with the following costs: Work in Process Job 33 Job 34 Balance on 3/1 $ 4,000 3,200 $ 7,200 Source documents revealed the following during March: Materials Requisitions Labor Time Forms Tickets Status of Job at Month-End Job 33 $ 3,800 $ 5,800 Completed...

  • Oak Crook Furniture Factory IOCFF, a custom future manufacturer, uses job order cosaing to track the...

    Oak Crook Furniture Factory IOCFF, a custom future manufacturer, uses job order cosaing to track the cost of each customer order On March LOCFF had two jobs in PTOCOCS with the following co Work in Process Job 34 334 Source documents revealed the following during March Materials Requisitions Labor Time Tickets Status of job at Month-End S plete Completed, but not sold Job 33 $ 11,300 The company applies Overhead to products at a rate of 65 percent of direct...

  • i just need help with this question on my accounting homework ACC202 K Chapter 02 Oak...

    i just need help with this question on my accounting homework ACC202 K Chapter 02 Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the cost of each customer order On March 1, OCFF had two jobs in process with the following costs: points Work in Process Job 33 Job 34 $ on 3/1 4,900 4.400 9,300 $ Source documents revealed the following during March: Materials Requisitions Labor Time Forms Tickets Status of Job...

  • The company applies overhead to products at a rate of 60 percent of direct labor cost....

    The company applies overhead to products at a rate of 60 percent of direct labor cost. Required: 1. Compute the cost of Jobs 33, 34, and 35 at the end of the month. 2. Calculate the balance in the Work in Process Inventory, Finished Goods Inventory, and Cost of Goods Sold accounts at month-end. Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the cost of each customer order. On March 1, OCFF had...

  • Balance on 3/1 $ 5,000 5,000 $ 10,000 Work in Process Job 33 Job 34 Source...

    Balance on 3/1 $ 5,000 5,000 $ 10,000 Work in Process Job 33 Job 34 Source documents revealed the following during March: Materials Labor Time Tickets $ 5,700 3,800 2,800 2,500 $ 14,800 Requisitions Forms $ 2,800 3,900 3,300 1,100 $ 11,100 Status of Job at Month-End Completed and sold Completed, but not sold In process Job 33 Job 34 Job 35 Indirect The company applies overhead to products at a rate of 50 percent of direct labor cost. Required:...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT