1. | |||
Job 33 | Job 34 | Job 35 | |
Work in process balance on 3/1 | 5000 | 5000 | 0 |
(+) Materials used during March | 2800 | 3900 | 3300 |
(+) Labor cost during March | 5700 | 3800 | 2800 |
(+) Overhead applied ( 50% * Labor cost ) | 2850 | 1900 | 1400 |
Total manufacturing cost | 16350 | 14600 | 7500 |
2. | |
Work in process inventory ( Job 35 ) | 7500 |
Finished goods inventory (Job 34) | 14600 |
Cost of goods sold (Job 33) | 16350 |
Balance on 3/1 $ 5,000 5,000 $ 10,000 Work in Process Job 33 Job 34 Source...
Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the cost of each customer order. On March 1, OCFF had two jobs in process with the following costs: Work in Process Balance on 3/1 Job 33 $ 5,700 Job 34 4,600 $ 10,300 Source documents revealed the following during March: Materials Requisitions Forms Labor Time Tickets Status of Job at Month-End Job 33 $ 3,900 $ 4,700 Completed and sold Job 34 2,900 4,500...
Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the cost of each customer order. On March 1, OCFF had two jobs in process with the following costs: Work in Process Balance on 3/1 Job 33 $ 4,600 Job 34 4,200 $ 8,800 Source documents revealed the following during March: Materials Requisitions Forms Labor Time Tickets Status of Job at Month-End Job 33 $ 3,900 $ 5,300 Completed and sold Job 34 2,400 4,100...
Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the cost of each customer order. On March 1, OCFF had two jobs in process with the following costs: Work in Process Job 33 Job 34 Balance on 3/1 $ 7,500 6, eee $ 13,500 Source documents revealed the following during March Materials Requisitions Labor Time Forms Tickets Status of Job at Month-End Job 33 $ 3,500 $ 6,50e Completed and sold Job 34 6,eee...
i just need help with this question on my accounting homework ACC202 K Chapter 02 Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the cost of each customer order On March 1, OCFF had two jobs in process with the following costs: points Work in Process Job 33 Job 34 $ on 3/1 4,900 4.400 9,300 $ Source documents revealed the following during March: Materials Requisitions Labor Time Forms Tickets Status of Job...
The company applies overhead to products at a rate of 60 percent of direct labor cost. Required: 1. Compute the cost of Jobs 33, 34, and 35 at the end of the month. 2. Calculate the balance in the Work in Process Inventory, Finished Goods Inventory, and Cost of Goods Sold accounts at month-end. Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the cost of each customer order. On March 1, OCFF had...
I Oak Creek Furniture Factory (OCFF, a custom furniture manufacturer, uses job order costing to track the cost of each customer order On March 1 OCFF had two be in process with the following costs Work in Process Job 33 Job 4 0020 Source documents revealed the following during March Job 33 Job 35 3b 35 Requisitos Labor Tin Forns Tickets $ 2, 55,500 3.300 4. 2.100 Statue of Job at Mont Completed and sold Completed, but not sol In...
Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the cost of each customer order. On March 1, OCFF had two jobs in process with the following costs Work in Process Balance on 3/1 $ 4,400 Job 33 Job 34 $ 8,000 Source documents revealed the following during March Materials Labor Time Requisitions Tickets Forms 2,500 4,300 Completed and sold Status of Job at Month-End Job 33 Job 34 Job 35 Indirect 3,000 4,500...
Exercise 15-10 Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Month Number April May June Completed $7,200 $5,700 May 5,700 4,300 $3,600 June 1,600 April 6,000 5,500 June 6,100 3,800 Not complete Job 12 was completed in April, Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion. What is the...
Morrow Corporation had only one job in process during May-Job X322—and had no finished goods inventory on May 1. Job X32Z was started in April and finished during May. Data concerning that job appear below: Job X32Z S 5,700 $ Beginning balance Charged to the job during May Direct materials Direct labor Manufacturing overhead applied Units completed Units in process at the end of May Units sold during May 9,000 2.700 4,700 170 0 75 In May, overhead was overapplied...
Can someone please help with this problem? Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the cost of each customer order. On March 1, OCFF had two jobs in process with the following costs: Work in Process Job 33 Job 34 Balance on 3/1 $ 4,800 5,000 $9,800 Source documents revealed the following during March: Materials Requisitions Labor Time Forms Tickets Status of Job at Month-End Job 33 $ 3,300 $5,300 Completed and...