Answer:
Unit Produced (X) | Labor Time Required to Produce the Xth Unit (i.e., the last single unit produced) (Y) | Cumulative Total Time in Labor- Hours | Total Cost | Average Cost per Unit |
1 | 100 | 100 | 5000.00 | 5000.00 |
2 | 78.00 | 178.00 | 8900.00 | 4450.00 |
3 | 67.45 | 245.45 | 12272.44 | 4090.81 |
4 | 60.84 | 306.29 | 15314.44 | 3828.61 |
5 | 56.16 | 362.45 | 18122.60 | 3624.52 |
6 | 52.61 | 415.06 | 20753.10 | 3458.85 |
7 | 49.78 | 464.84 | 23242.19 | 3320.31 |
8 | 47.46 | 512.30 | 25614.95 | 3201.87 |
Y = aXb
Calulation of Y
Y1 =1^-0.358454*100 = 100
Y2 =2^-0.358454*100 = 78.00
Cumulative Total Time in Labor- Hours Calculation
Cumulative Total Time in Labor- Hours units 1= Y1
Cumulative Total Time in Labor- Hours units 2= Y1+Y2
Cumulative Total Time in Labor- Hours units 3= Y1+Y2+Y3
Total Cost Calculation:
Cost calculation for 1st unit is given, so will find the unit cost basis from unit 1=
=5000/100 =50
So for rest of the units: Cumulative cost * 50(calculated above same for all units)
Units 2 = 178.00*50 = 8900
same formula used for rest of the units
Average Cost per Unit Calculation:
=Total cost/No of units
Refer to the table below. Assume that the company involved now finds that the learning rate...
Refer to the table below. Assume that the company involved now finds that the learning rate is 92 percent. The 92 percent learning rate coefficient is −0.120294; that is b = −0.120294 in the formula Y = aXb. Using the formula, Y = aXb, compute the labor time and costs for 5, 6, and 7 units. Unit Produced (X) Labor Time Required to Produce the Xth Unit (i.e., the last single unit produced)1 (Y) Cumulative Total Time in Labor- Hours(2)...
Refer to the table below. Assume that the company involved now finds that the learning rate is 91 percent. The 91 percent learning rate coefficient is −0.136062; that is b = −0.136062 in the formula Y = aXb. Required: Using the formula, Y = aXb, compute the labor time and costs for 5, 6, and 7 units. (Round your intermediate calculations (except for coefficient) and final answers to 2 decimal places.) Unit Produced (X) Labor Time Required to Produce the...
Refer to the table below. Assume that the company involved now finds that the learning rate is 70 percent. The 70 percent learning rate coefficient is -0.514573; that is b= -0.514573 in the formula Y= ax Required: Using the formula, Y= ax", compute the labor time and costs for 5, 6, and 7 units. (Round your Intermediate calculations (except for coefficient) and final answers to 2 decimal places.) Unit Produced Labor Time Required to Produce the Xth Unit i.e., the...
Refer to the table below. Assume that the company involved now finds that the learning rate is 85 percent. The 85 percent learning rate coefficient is-0.234465; that is b-0.234465 in the formula Required Using the formula, Y= aX. compute the labor time and costs for 5, 6, and 7 units. (Round your intermediate calculations (except for coefficient) and final answers to 2 decimal places.) ime Required to roduce the Xth Unit (i.e., the last Cumulative Total Time in Labor Hours(2)...