Question

Waterway Company decided to analyze certain costs for June of the current year. Units started into production equaled 28300 aSheridan Company assigns overhead based on machine hours. The Milling Department logs 2470 machine hours and Cutting DepartmeCoronado and Miller Manufacturing is trying to determine the equivalent units for conversion costs with 11500 units of ending

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution 1:

Equivalent units of conversion = Units completed and transferred out *100% + Units in ending WIP * % of completion

= (24300*100%) + (4000*20%) = 25100 units

conversion cost per equivalent unit = $128,010 / 25100 = $5.10 per unit

Hence 3rd option is correct.

Solution 2:

Total overhead assigned = (2470+4000)*$3 = $19,410

Therefore entry to assign overhead include "Credit to manufacturing overhead $19,410"

Hence 2nd option is correct.

Solution 3:

Equivalent units of conversion = (32500 - 11500) + 11500*80% = 30200 units

Hence last option is correct.

Add a comment
Know the answer?
Add Answer to:
Waterway Company decided to analyze certain costs for June of the current year. Units started into...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Sheridan Company assigns overhead based on machine hours. The Milling Department logs 2470 machine hours and...

    Sheridan Company assigns overhead based on machine hours. The Milling Department logs 2470 machine hours and Cutting Department shows 4000 machine hours for the period. If the overhead rate is $3 per machine hour, the entry to assign overhead will show a O debit to Work in Process for $12000. O credit to Manufacturing Overhead for $19410. O credit to Work in Process-Cutting Department for $12000. O debit to Manufacturing Overhead for $19410. Coronado and Miller Manufacturing is trying to...

  • Question 16 --/1 View Policies Current Attempt in Progress Marigold Company assigns overhead based on machine...

    Question 16 --/1 View Policies Current Attempt in Progress Marigold Company assigns overhead based on machine hours. The Milling Department logs 2320 machine hours and Cutting Department shows 4110 machine hours for the period. If the overhead rate is $3 per machine hour, the entry to assign overhead will show a O credit to Work in Process-Cutting Department for $12330. O debit to Work in Process for $12330. O credit to Manufacturing Overhead for $19290. Odebit to Manufacturing Overhead for!...

  • Waterway Manufacturing is trying to determine the equivalent units for conversion costs with 2700 units of...

    Waterway Manufacturing is trying to determine the equivalent units for conversion costs with 2700 units of ending Work in Process at 70% completion and 15500 physical units that are 100% complete as to materials. There are no beginning units in the department. Materials are added at the beginning of the process, and conversion costs occur evenly throughout the entire production period. What are the equivalent units for conversion costs for the current period if the weighted-average method is used? 18200...

  • Question 34 Fullerton Company has the following equivalent units for October: materials 40,000 and conversion costs...

    Question 34 Fullerton Company has the following equivalent units for October: materials 40,000 and conversion costs 15,000. Production cost data are: Materials Conversion Work in process, October 1 $ 50,000 $ 7.500 Costs added in October 130.000 22,500 The unit production costs for October are: $3.25 Materials Cost per unit and $1.50 Conversion Costs per unit $4.50 Materials Cost per unit and $2.00 Conversion Costs per unit $3.25 Materials Cost per unit and $.50 Conversion Costs per unit 01.25 Materials...

  • Wyle Company uses the weighted-average method in its process costing system. The following information was available...

    Wyle Company uses the weighted-average method in its process costing system. The following information was available for one of its processing departments: • The beginning work in process inventory consisted of 16,000 units, which were 75% complete with respect to conversion costs. • The department converted the equivalent of 59,000 units of production during the current month. • A total of 50,000 units were completed and transferred out of that department during the current month. • The ending work in...

  • eBook Calculator Physical Flow, Equivalent Units, Unit Costs, No Beginning WIP Inventory, Activity-Based Costing Lacy, Inc.,...

    eBook Calculator Physical Flow, Equivalent Units, Unit Costs, No Beginning WIP Inventory, Activity-Based Costing Lacy, Inc., produces a subassembly used in the production of hydraulic cylinders. The subassemblies are produced in three departments: Plate Cutting, Rod Cutting, and Welding. Materials are added at the beginning of the process. Overhead is applied using the following drivers and activity rates: Actual Usage Driver Rate (by Plate Cutting) Direct labor cost 160% of direct labor $732,000 Inspection hours $40 per hour 7,450 hours...

  • Calculate Equivalent Units, Unit Costs, and Transferred Costs - Weighted Average Method Monroe Company processes a...

    Calculate Equivalent Units, Unit Costs, and Transferred Costs - Weighted Average Method Monroe Company processes a food seasoning powder through its Compounding and Packaging departments. In yhe Compounding Department, direct materials are added at the beginning of the process, and direct labor and manufacturing overhead are incurred evenly throughout the process. Monroe uses the weighted average method. Costs in the Compounding Department can be summarized as follows: At August 31, 2019, 3,00 units were in process, 30% complete with respect...

  • Part IV. Problem - Total - 30 points. Otylia Manufacturing Company assembles its product in several...

    Part IV. Problem - Total - 30 points. Otylia Manufacturing Company assembles its product in several departments. It has two departments that process all units. During February, the beginning work in process in the cutting department was half completed as to conversion, and complete as to direct materials. The beginning inventory included $12,000 for materials and $3,000 for conversion costs. Ending work-in-process inventory in the cutting department was 40% complete. Direct materials are added at the beginning of the process....

  • Barnes and Miller Manufacturing is trying to determine the equivalent units for conversion costs with 10,000...

    Barnes and Miller Manufacturing is trying to determine the equivalent units for conversion costs with 10,000 units of ending work in process at 80% completion and 28,000 physical units. There are no beginning units in the department. Conversion costs occur evenly throughout the entire production period. What are the equivalent units for conversion costs for the current period?

  • Equivalent Units of Production and Related Costs The charges to Work in Process-Assembly Departme...

    Equivalent Units of Production and Related Costs The charges to Work in Process-Assembly Department for a period, together with information concerning production, are as follows. All direct materials are placed in pro production. Work in Process-Assembly Department Bal., 6,000 units, 55% completed Direct materials, 141,000 units $1.3 Direct labor Factory overhead Bal, 2 units, 40% completed 19,350 183,300 To Finished Goods, 138,000 units 378,400 147,140 Determine the following a. The number of units in work in process inventory at the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT