Question

3- Claremont Company sells refurbished copiers. During the month, the company sold 180 copiers at an...

3-

Claremont Company sells refurbished copiers. During the month, the company sold 180 copiers at an average price of $3,000 each. The budget for the month was to sell 175 copiers at an average price of $3,200. The expected total sales for 180 copiers were:

Multiple Choice

  • $540,000.

  • $576,000.

  • $525,000.

  • $560,000.

  • $550,000.

    9- A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $269,500. What is the total labor cost variance?

    Multiple Choice

  • $2,000 unfavorable.

  • $3,000 unfavorable.

  • $5,500 unfavorable.

  • $8,000 unfavorable.

  • $9,000 unfavorable.

    13- Parallel Enterprises has collected the following data on one of its products. During the period the company produced 25,000 units. The direct materials quantity variance is:

    Direct materials standard (7 kg. @ $2/kg) $ 14 per finished unit
    Actual cost of materials purchased $ 322,500
    Actual direct materials purchased and used 150,000 kg

    Multiple Choice

  • $27,500 unfavorable.

  • $50,000 unfavorable.

  • $50,000 favorable.

  • $22,500 unfavorable.

  • $22,500 favorable.

    12- Use the following data to find the direct labor rate variance if the company produced 7,000 units of product during the period.

    Standard:
    Direct labor (3.2 hrs. per unit @ $12/hr.) $ 38.40 per unit
    Actual cost incurred:
    Direct labor (24,500 hrs. @ $12.50/hr.) $ 306,250

    Multiple Choice

  • $12,250 unfavorable.

  • $14,700 unfavorable.

  • $14,700 favorable.

  • $12,250 favorable.

  • $26,950 favorable.

    16- A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $269,500. What is the direct labor rate variance?

    Multiple Choice

  • $27,500 unfavorable.

  • $22,000 favorable.

  • $16,000 unfavorable.

  • $16,000 favorable.

  • $6,000 unfavorable.

    20- Summerlin Company budgeted 4,000 pounds of material costing $5.00 per pound to produce 2,000 units. The company actually used 4,500 pounds that cost $5.10 per pound to produce 2,000 units. What is the direct materials quantity variance?

    Multiple Choice

  • $400 unfavorable.

  • $450 unfavorable.

  • $2,500 unfavorable.

  • $2,550 unfavorable.

  • $2,950 unfavorable.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The answer has been presented in the supporting sheet. First 4 parts has been solved with detailed explanation and format. For detailed answer refer to the supporting sheet.

Answer 2 Part 3) 3 The correct answer is $576,000 4 6 Explanation 7 Expected sales = budgeted selling price * units sold 8 =

Add a comment
Know the answer?
Add Answer to:
3- Claremont Company sells refurbished copiers. During the month, the company sold 180 copiers at an...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 16- A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and w...

    16- A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $269,500. What is the direct labor rate variance? Multiple Choice $27,500 unfavorable. $22,000 favorable. $16,000 unfavorable. $16,000 favorable. $6,000 unfavorable. 20- Summerlin Company budgeted 4,000 pounds of material costing $5.00 per pound to produce 2,000 units. The company actually used 4,500 pounds that cost $5.10...

  • QUESTION 21 A company provided the following direct materials cost information. Compute the direct materials price...

    QUESTION 21 A company provided the following direct materials cost information. Compute the direct materials price variance Standard coste an pireet naterials d cest res,000 nite 2.00/ Actual costan Direct Materials costs incurred (403, 750 uit 2.20/itu O $81,000 Favorable. $81,000 Unfavorable. $80,750 Unfavorable. $80,750 Favorable. O $78,250 Favorable. QUESTION 22 A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at...

  • A job was budgeted to require 3 hours of labor per unit at $11.00 per hour....

    A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $269,500. What is the total labor cost variance? Multiple Choice $2,000 unfavorable. $3,000 unfavorable. $5,500 unfavorable. $8,000 unfavorable. $9,000 unfavorable.

  • Claremont Company specializes in seling refurbished copiers. During the month, the company sold 195 coplers at...

    Claremont Company specializes in seling refurbished copiers. During the month, the company sold 195 coplers at an average price of $3,300 each. The budget for the month was to sell 190 coplers at an average price of $3,500. The expected total sales for 195 coplers were: Multiple Choice Ο Ο $643,500. Ο Ο $682,500. Ο Ο $627000. Ο $665,000. Ο Ο Sssa000. Regarding overhead costs, as volume increases: Multiple Choice C) Unit fixed cost increases, unit variable cost decreases Ο...

  • A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units a...

    A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and was completed in 22.000 hours at a total labor cost of $269,500. What is the total labor cost variance? Ο $2,000 unfavorable Ο $3,000 unfavorable Ο $5,500 unfavorable Ο $8,000 unfavorable. Ο ( 59.000 unfavorable. Georgia, Inc. has collected the following data on one of its products. The direct materials quantity variance is: Direct materials standard (4...

  • Fletcher Company collected the following data regarding production of one of its products. Compute the variable...

    Fletcher Company collected the following data regarding production of one of its products. Compute the variable overhead efficiency variance. Direct labor standard (2 hrs. @ $12.40/hr.) $ 24.80 per finished unit Actual direct labor hours 96,500 hrs. Budgeted units 56,000 units Actual finished units produced 47,500 units Standard variable OH rate (2 hrs. @ $15.00/hr.) $ 30.00 per finished unit Standard fixed OH rate ($526,400/56,000 units) $ 9.40 per unit Actual cost of variable overhead costs incurred $ 1,417,000 Actual...

  • PLEASE ANSWER QUESTIONS CORRECTLY !!!! 1. 2. 3. 4. PLEASE ANSWER QUESTIONS CORRECTLY !!!! Use the...

    PLEASE ANSWER QUESTIONS CORRECTLY !!!! 1. 2. 3. 4. PLEASE ANSWER QUESTIONS CORRECTLY !!!! Use the following data to find the total direct labor cost variance if the company produced 3,500 units during the period. Direct labor standard (4.00 hrs. @ $6.20/hr.) Actual hours worked Actual rate per hour $ 24.80 per unit 12,050 $ 6.30 Multiple Choice . $12,050 favorable 0 $10.885 unfavorable. 0 $10,885 favorable. 0 $1,400 favorable. O $1,400 unfavorable. Fletcher Company collected the following data regarding...

  • PLease answer all queations ASAP! wil rate 1. Georgia, Inc. has collected the following data on...

    PLease answer all queations ASAP! wil rate 1. Georgia, Inc. has collected the following data on one of its products. The actual cost of the direct materials used is: Direct materials standard (3 lbs @ $2/lb) $6 per finished unit Total direct materials cost variance—unfavorable $14,250 Actual direct materials used 100,000 lbs. Actual finished units produced 25,000 units Multiple Choice $135,750. $164,250. $150,000. $182,000. $100,000. 2. Use the following data to find the total direct labor cost variance if the...

  • Summerlin Company budgeted 4,100 pounds of material costing $6.00 per pound to produce 2,000 units. The...

    Summerlin Company budgeted 4,100 pounds of material costing $6.00 per pound to produce 2,000 units. The company actually used 4,600 pounds that cost $6.10 per pound to produce 2,000 units. What is the direct materials quantity variance? Multiple Choice 0 $3,050 unfavorable. 0 $460 unfavorable. 0 $3,460 unfavorable. 0 $3,000 unfavorable. 0 $410 unfavorable. Summerlin Company budgeted 4,100 pounds of material costing $6.00 per pound to produce 2,000 units. The company actually used 4,600 pounds that cost $6.10 per pound...

  • Janitor Supply produces an industrial cleaning powder that requires 40 grams of material at $010 per...

    Janitor Supply produces an industrial cleaning powder that requires 40 grams of material at $010 per gram and 0.25 direct labor hours at $12.00 per hour. Overhead is applied at the rate of $18 per direct labor hour What is the total standard cost for one unit of product that would appear on a standard cost card? Multiple Choice $700 $8.50 $11.50. $7.50 $25.00 Claremont Company sells refurbished copiers. During the month, the company sold 180 copiers for total sales...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT