Question

16- A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and w...

  • 16- A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $269,500. What is the direct labor rate variance?

    Multiple Choice

  • $27,500 unfavorable.

  • $22,000 favorable.

  • $16,000 unfavorable.

  • $16,000 favorable.

  • $6,000 unfavorable.

    20- Summerlin Company budgeted 4,000 pounds of material costing $5.00 per pound to produce 2,000 units. The company actually used 4,500 pounds that cost $5.10 per pound to produce 2,000 units. What is the direct materials quantity variance?

    Multiple Choice

  • $400 unfavorable.

  • $450 unfavorable.

  • $2,500 unfavorable.

  • $2,550 unfavorable.

  • $2,950 unfavorable.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Question 1

Correct answer-----------$27,500 unfavorable.

Working

Labor Rate Variance
( Standard Rate - Actual Rate ) x Actual Labor Hours
( $                  11.00 - $                   12.25 ) x 22000
-27500
Variance $           27,500.00 Unfavourable-U

.

8000 Units
Quantity (AQ) Rate (AR) Actual Cost
Direct labor 22000 $         12.25 $       269,500.00

Question 2

Correct answer-----------$2,500 unfavorable.

Working

Material Quantity Variance
( Standard Quantity - Actual Quantity ) x Standard Rate
( 4000 - 4500 ) x $              5.00
-2500
Variance $             2,500.00 Unfavourable-U
Add a comment
Know the answer?
Add Answer to:
16- A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and w...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A job was budgeted to require 3 hours of labor per unit at $11.00 per hour....

    A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $269,500. What is the total labor cost variance? Multiple Choice $2,000 unfavorable. $3,000 unfavorable. $5,500 unfavorable. $8,000 unfavorable. $9,000 unfavorable.

  • A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units a...

    A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and was completed in 22.000 hours at a total labor cost of $269,500. What is the total labor cost variance? Ο $2,000 unfavorable Ο $3,000 unfavorable Ο $5,500 unfavorable Ο $8,000 unfavorable. Ο ( 59.000 unfavorable. Georgia, Inc. has collected the following data on one of its products. The direct materials quantity variance is: Direct materials standard (4...

  • 3- Claremont Company sells refurbished copiers. During the month, the company sold 180 copiers at an...

    3- Claremont Company sells refurbished copiers. During the month, the company sold 180 copiers at an average price of $3,000 each. The budget for the month was to sell 175 copiers at an average price of $3,200. The expected total sales for 180 copiers were: Multiple Choice $540,000. $576,000. $525,000. $560,000. $550,000. 9- A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and was completed in 22,000...

  • A job was budgeted to require 2 hours of labor per unit at $11.00 per hour....

    A job was budgeted to require 2 hours of labor per unit at $11.00 per hour. The job consisted of 8,500 units and was completed in 16,000 hours at a total labor cost of $189,100. What is the direct labor efficiency variance? Multiple Choice Ο $13,100 unfavorable. Ο $13100 favorable. Ο $1,000 unfavorable. Ο $1000 favorable.

  • Summerlin Company budgeted 4,100 pounds of material costing $6.00 per pound to produce 2,000 units. The...

    Summerlin Company budgeted 4,100 pounds of material costing $6.00 per pound to produce 2,000 units. The company actually used 4,600 pounds that cost $6.10 per pound to produce 2,000 units. What is the direct materials quantity variance? Multiple Choice 0 $3,050 unfavorable. 0 $460 unfavorable. 0 $3,460 unfavorable. 0 $3,000 unfavorable. 0 $410 unfavorable. Summerlin Company budgeted 4,100 pounds of material costing $6.00 per pound to produce 2,000 units. The company actually used 4,600 pounds that cost $6.10 per pound...

  • QUESTION 21 A company provided the following direct materials cost information. Compute the direct materials price...

    QUESTION 21 A company provided the following direct materials cost information. Compute the direct materials price variance Standard coste an pireet naterials d cest res,000 nite 2.00/ Actual costan Direct Materials costs incurred (403, 750 uit 2.20/itu O $81,000 Favorable. $81,000 Unfavorable. $80,750 Unfavorable. $80,750 Favorable. O $78,250 Favorable. QUESTION 22 A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at...

  • Multiple Choice Question 115 The per-unit standards for direct materials are 2 pounds at $5 per...

    Multiple Choice Question 115 The per-unit standards for direct materials are 2 pounds at $5 per pound. Last month, 9800 pounds of direct materials that actually cost $47200 were used to produce 5400 units of product. The direct materials quantity variance for last month was $6800 unfavorable. $5000 favorable. $2700 favorable. $5000 unfavorable. NOISEA H BACK NE Multiple Choice Question 116 The per-unit standards for direct labor are 1.5 direct labor hours at $15 per hour. If in producing 3000...

  • PLEASE ANSWER QUESTIONS CORRECTLY !!!! 1. 2. 3. 4. PLEASE ANSWER QUESTIONS CORRECTLY !!!! Use the...

    PLEASE ANSWER QUESTIONS CORRECTLY !!!! 1. 2. 3. 4. PLEASE ANSWER QUESTIONS CORRECTLY !!!! Use the following data to find the total direct labor cost variance if the company produced 3,500 units during the period. Direct labor standard (4.00 hrs. @ $6.20/hr.) Actual hours worked Actual rate per hour $ 24.80 per unit 12,050 $ 6.30 Multiple Choice . $12,050 favorable 0 $10.885 unfavorable. 0 $10,885 favorable. 0 $1,400 favorable. O $1,400 unfavorable. Fletcher Company collected the following data regarding...

  • 1.A company produces widgets with budgeted standard direct materials of 2 pounds per widget at $5...

    1.A company produces widgets with budgeted standard direct materials of 2 pounds per widget at $5 per pound. Standard direct labor was budgeted at 0.5 hour per widget at $15 per hour. The actual usage in the current year was 25,000 pounds (an actual cost of $4.75 per pound) and 3,000 hours (an actual rate of $17 per pound )to produce 10,000 widgets. What was the direct labor usage variance? A. $30,000 favorable. B. $25,000 favorable. C. $25,000 unfavorable. D....

  • Javonte Co. set standards of 3 hours of direct labor per unit of product and $15.60...

    Javonte Co. set standards of 3 hours of direct labor per unit of product and $15.60 per hour for the labor rate. During October, the company uses 18,000 hours of direct labor at a $284,400 total cost to produce 6,200 units of product. In November, the company uses 22,000 hours of direct labor at a $348,700 total cost to produce 6,600 units of product. AH = Actual Hours SH = Standard Hours AR = Actual Rate SR = Standard Rate...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT