What is the NPV of the following project, assuming a required return of 6%?
Year |
Cash Flow |
0 |
-$-150,993 |
1 |
$41,400 |
2 |
$50,706 |
3 |
$92,833 |
Ans. | Year | Cash inflows | PV @ 6% | Present value of cash inflows | |
1 | $41,400 | 0.9434 | $39,057 | ||
2 | $50,706 | 0.8900 | $45,128 | ||
3 | $92,833 | 0.8396 | $77,944 | ||
Total Present value of cash inflows | $162,129 | ||||
Present value of cash inflows | $162,129 | ||||
Less: Investment | -$150,993 | ||||
Net present value | $11,136 | ||||
*Calculation of Present value factors: (PV @ 6%) | |||||
Year | PV @ 6% | ||||
1 | 1 / (1 + 0.06)^1 | 0.9434 | |||
2 | 1 / (1 + 0.06)^2 | 0.8900 | |||
3 | 1 / (1 + 0.06)^3 | 0.8396 | |||
What is the NPV of the following project, assuming a required return of 6%? Year Cash...
What is the net present value (NPV) of a project that has the following cash flows? The required return is 12.0%. Year Cash Flow 0 $ (14,000) 1 $ 3,000 2 $ 3,000 3 $ 3,000 4 $ 3,000 5 $ 3,000 6 $ 3,000
What is the net present value (NPV) of a project that has the following cash flows? The required return is 10.0% Year 0 1 2 Cash Flow $ (5,000) $2,000 $ 2,000 $ 2,000 $3,000 $1,000 $1,000 3 4 5 6
c. If the required return is 7 percent, what is the NPV for Project A? d. If the required return is 7 percent, what is the NPV for Project B? e. At what discount rate would the company be indifferent between these two projects? Bruin, Inc., has identified the following two mutually exclusive projects: Year -o Cash Flow (A) -$41,000 19,400 14,900 12,400 9,400 Cash Flow (B) -$41,000 5,600 12.100 18,600 22,600 mt a. What is the IRR...
Carland, Inc., has a project available with the following cash flows. If the required return for the project is 9.6 percent, what is the project's NPV? Year Cash Flow 0 −$275,000 1 86,700 2 109,100 3 126,300 4 77,700 5 −13,700
Carland, Inc., has a project available with the following cash flows. If the required return for the project is 8.2 percent, what is the project's NPV? Year Cash Flow 0 −$261,000 1 69,900 2 93,700 3 119,300 4 72,100 5 −12,300
What is the net present value (NPV) of a project that has the following cash flows? The required return is 10.0%. Year Cash Flow 0 $ (12,000) 1 $ 3,000 2 $ 3,000 3 $ 3,000 4 $ 3,000 5 $ 3,000 6 $ 3,000 Group of answer choices None of these are correct. $ (1,666) $ 334 $ 1,066 $ (934)
What is the net present value (NPV) of a project that has the following cash flows? The required return is 12.0%. Year Cash Flow 0 $ (12,000) 1 $ 3,000 2 $ 3,000 3 $ 3,000 4 $ 3,000 5 $ 3,000 6 $ 3,000 Group of answer choices $ (1,666) $ 334 None of these are correct. $ (934) $ 1,066
Calculate the NPV given the following cash flows, if the appropriate required rate of return is 9 percent. Should the project be accepted? What is the project's NPV? YEAR CASH FLOWS 0 -40,000 1 20,000 2 20,000 3 15,000 4 15,000 5 30,000 6 30,000
What is the net present value (NPV) of a project that has the following cash flows? The required return is 10.0%. Year 0 1 2 3 Cash Flow $(5,000) $2,000 $2,000 $2,000 $3,000 $ 1,000 $1,000 4 5 6 O $2,920 O None of these are correct. O $2,916 O $2,655 $ 3,208
A project has the following cash flows: year. Cash flow 0. $71,000 1. -50,000. 2. -29,200 a. What is the IRR for the project? (Do not round intermediate calculations and enter answer as a percent round to 2 decimal places) b. What is the NPV of this project if the required return is 6 percent? c. What is the NPV of the project if the required return is 0 percent? d. What is the NPV of the project if the...