Compute the PI statistic for Project Q if the appropriate cost of capital is 13 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)
Project Q | |||||
Time: | 0 | 1 | 2 | 3 | 4 |
Cash flow: | –$12,700 | $4,200 | $5,030 | $4,920 | $3,000 |
PI = Present value / initial investment
Present value = 4200 / (1 + 0.13)1 + 5,030 / (1 + 0.13)2 + 4,920 / (1 + 0.13)3 + 3,000 / (1 + 0.13)4
Present value = $3,716.814159 + 3,939.227817 + 3,409.806798 + 1,839.956183
Present value = $12,905.80496
PI = 12,905.80496 / 12,700
PI = 1.02
Compute the PI statistic for Project Q if the appropriate cost of capital is 13 percent....
Compute the PI statistic for Project Q if the appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Q Time: 0 1 2 3 4 Cash flow –$11,600 $3,650 $4,480 $1,820 $2,450 PI Should the project be accepted or rejected? Rejected Accepted
Compute the Pl statistic for Project Q if the appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Q Time: 0 1 2 4 Cash flow: -$11,600 $3,650 $4,480 $1,820 $2,450 PI
Compute the PI statistic for Project Z if the appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Z Time: 0 1 2 3 4 5 Cash flow: −$2,300 $610 $740 $910 $560 $360 Should the project be accepted or rejected? accepted rejected
Compute the PI statistic for Project Zer the appropriate cost of capital is 6 percent (Do not round intermediate calculations and round your final answer to 2 decimal places.) 23 Protect a Time: Cash flow: $1,800 $510 $640 $819 5160 5 260 PI Should the project be accepted or rejected? rejected accepted < Prey 5 of 7 !! Nept> to search ORHOM
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: Cash flow: -$8,100 $3,370 $4,200 $1,540 $320 NPV
Compute the Pl statistic for Project Z if the appropriate cost of capital is 6 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project 2 Time: Cash flow: 0 -$1,200 1 $390 2 $520 3 $690 4 $340 5 $140 PI
Compute the NPV statistic for Project Y if the appropriate cost of capital is 13 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: Cash flow: 1 2 3 -$9,100 $3,570 $4,400 $1,740 4 $520 NPV Should the project be accepted or rejected? O accepted O rejected
Compute the IRR for Project F. The appropriate cost of capital is 13 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: 2 4 Cash flow: -$9,900 $3,7s0 $4,580 $1,920 $2,550 IRR Should the project be accepted or rejected? ассepted Orejected Compute the IRR static for Project E. The appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project...
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 11 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "0" (zero).) Project D Time: 0 1 2 3 4 5 Cash flow: –$12,700 $3,520 $4,520 $1,860 $0 $1,340 Discounted Payback Statistic:
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "O" (zero).) Project D Time: Cash flow: 0 -$11,600 1 $3,410 $4,300 34 $1,640 $0 $1,120 Discounted payback period 0 years Should the project be accepted or rejected? accepted rejected...