Profitability Index of a portfolio is calculated using formula
PI = PV of future cash flows/initial investment
So, here, PV of future cash flows at cost of capital r = 6% is
PV = CF1/(1+r) + CF2/(1+r)^2 + CF3/(1+r)^3 + CF4/(1+r)^4 + CF5/(1+r)^5
=> PV = 390/1.06 + 520/1.06^2 + 690/1.06^3 + 340/1.06^4 + 140/1.06^5
=> PV = $1783.99
So, Profitability index = 1783.99/1200 = 1.49
Compute the Pl statistic for Project Z if the appropriate cost of capital is 6 percent....
Compute the Pl statistic for Project Q if the appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Q Time: 0 1 2 4 Cash flow: -$11,600 $3,650 $4,480 $1,820 $2,450 PI
Compute the Pl statistic for Project Z if the appropriate cost of capital is 8 percent (Do not round intermediate celculations and round your final answer to 2 decimal places.) Project z Time: Cash flow:-$1,600 $470 $600 $770 $420 $220 0 Pl Should the project be accepted or rejected? O accepted O rejected
Compute the PI statistic for Project Z if the appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Z Time: 0 1 2 3 4 5 Cash flow: −$2,300 $610 $740 $910 $560 $360 Should the project be accepted or rejected? accepted rejected
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow –$1,200 $390 $520 $560 $640 $140
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: −$1,200 $430 $1,680 −$560 $380 −$140 NPV? Should the project be accepted or rejected?
Compute the PI statistic for Project Q if the appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Q Time: 0 1 2 3 4 Cash flow –$11,600 $3,650 $4,480 $1,820 $2,450 PI Should the project be accepted or rejected? Rejected Accepted
Compute the PI statistic for Project Q if the appropriate cost of capital is 13 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Q Time: 0 1 2 3 4 Cash flow: –$12,700 $4,200 $5,030 $4,920 $3,000
Compute the PI statistic for Project Zer the appropriate cost of capital is 6 percent (Do not round intermediate calculations and round your final answer to 2 decimal places.) 23 Protect a Time: Cash flow: $1,800 $510 $640 $819 5160 5 260 PI Should the project be accepted or rejected? rejected accepted < Prey 5 of 7 !! Nept> to search ORHOM
Compute the NPV statistic for Project Y if the appropriate cost of capital is 13 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: Cash flow: 1 2 3 -$9,100 $3,570 $4,400 $1,740 4 $520 NPV Should the project be accepted or rejected? O accepted O rejected
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: Cash flow: -$8,100 $3,370 $4,200 $1,540 $320 NPV