PI = Present value of future cash flows / Initial investment
PI = ($3,650/1.12 + $4,480/1.122 + $1,820/1.123 + $2,450/1.124) / $11,600
PI = 0.83
Compute the Pl statistic for Project Q if the appropriate cost of capital is 12 percent....
Compute the PI statistic for Project Q if the appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Q Time: 0 1 2 3 4 Cash flow –$11,600 $3,650 $4,480 $1,820 $2,450 PI Should the project be accepted or rejected? Rejected Accepted
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow –$8,100 $3,650 $4,480 $1,820 $600
Compute the Pl statistic for Project Z if the appropriate cost of capital is 6 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project 2 Time: Cash flow: 0 -$1,200 1 $390 2 $520 3 $690 4 $340 5 $140 PI
Compute the PI statistic for Project Q if the appropriate cost of capital is 13 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Q Time: 0 1 2 3 4 Cash flow: –$12,700 $4,200 $5,030 $4,920 $3,000
Compute the Pl statistic for Project Z if the appropriate cost of capital is 8 percent (Do not round intermediate celculations and round your final answer to 2 decimal places.) Project z Time: Cash flow:-$1,600 $470 $600 $770 $420 $220 0 Pl Should the project be accepted or rejected? O accepted O rejected
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "O" (zero).) Project D Time: Cash flow: 0 -$11,600 1 $3,410 $4,300 34 $1,640 $0 $1,120 Discounted payback period 0 years Should the project be accepted or rejected? accepted rejected...
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow: –$9,200 $3,590 $4,420 $1,760 $540
Compute the PI statistic for Project Z if the appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Z Time: 0 1 2 3 4 5 Cash flow: −$2,300 $610 $740 $910 $560 $360 Should the project be accepted or rejected? accepted rejected
Compute the IRR statistic for Project F. The appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: 0 1 2 3 4 Cash flow: −$10,300 $3,950 $4,780 $2,120 $2,750 Should the project be accepted or rejected? rejected accepted
Compute the MIRR statistic for Project lif the appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project I Time: Cash flow: 0 -$11,300 1 $5,480 2 $4,330 3 $1,670 4 $2,150 MIRR % Should the project be accepted or rejected? rejected accepted