Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations. Round your final answer to 2 decimal places.) |
Project Y | |||||
Time: | 0 | 1 | 2 | 3 | 4 |
Cash flow | –$8,100 | $3,650 | $4,480 | $1,820 | $600 |
Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)
=3,650/1.12+4,480/1.12^2+1,820/1.12^3+600/1.12^4
=8507.11
NPV=Present value of inflows-Present value of outflows
=8507.11-8,100
=$407.11(Approx).
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent....
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: Cash flow: -$8,100 $3,370 $4,200 $1,540 $320 NPV
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow: –$9,200 $3,590 $4,420 $1,760 $540
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amounts should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: Cash flow: 0 $8,000 1 $3,350 2 $4,180 3 $1,520 4 $300 NPV Should the project be accepted or rejected? O accepted O rejected
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow –$8,400 $3,710 $4,540 $1,880 $660 NPV $
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: Cash flow: -68,300 $3,690 64,520 61,960 6640 NPV Should the project be accepted or rejected? rejected Daccepted
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow –$8,200 $3,670 $4,500 $1,840 $620 NPV $ Should the project be accepted or rejected? Rejected Accepted
Compute the NPV statistic for Project Y if the appropriate cost of capital is 13 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: Cash flow: 1 2 3 -$9,100 $3,570 $4,400 $1,740 4 $520 NPV Should the project be accepted or rejected? O accepted O rejected
Compute the Pl statistic for Project Q if the appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Q Time: 0 1 2 4 Cash flow: -$11,600 $3,650 $4,480 $1,820 $2,450 PI
Compute the PI statistic for Project Q if the appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Q Time: 0 1 2 3 4 Cash flow –$11,600 $3,650 $4,480 $1,820 $2,450 PI Should the project be accepted or rejected? Rejected Accepted
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percen (Negative amount should be indicated by o minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.JA Time: Cash flow: $8,100 $3,370 $4,200 $1,540 $320 NPV Should the project be accepted or rejected? accepted rejected < Prev 7 7 search Arx