Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)
Project Y | |||||
Time: | 0 | 1 | 2 | 3 | 4 |
Cash flow: | –$9,200 | $3,590 | $4,420 | $1,760 | $540 |
Given for project Y
Time: | 0 | 1 | 2 | 3 | 4 |
Cash flow: | –$9,200 | $3,590 | $4,420 | $1,760 | $540 |
Cost of capital = 12%
NPV is Sum of PV of all cash flows
So, NPV = -9200 + 3590/1.12 + 4420/1.12^2 + 1760/1.12^3 + 540/1.12^4 = $-875.13
So NPV for Project Y is $-875.13
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent....
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow –$8,100 $3,650 $4,480 $1,820 $600
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: Cash flow: -$8,100 $3,370 $4,200 $1,540 $320 NPV
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amounts should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: Cash flow: 0 $8,000 1 $3,350 2 $4,180 3 $1,520 4 $300 NPV Should the project be accepted or rejected? O accepted O rejected
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow –$8,400 $3,710 $4,540 $1,880 $660 NPV $
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: Cash flow: -68,300 $3,690 64,520 61,960 6640 NPV Should the project be accepted or rejected? rejected Daccepted
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow –$8,200 $3,670 $4,500 $1,840 $620 NPV $ Should the project be accepted or rejected? Rejected Accepted
Compute the NPV statistic for Project Y if the appropriate cost of capital is 13 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: Cash flow: 1 2 3 -$9,100 $3,570 $4,400 $1,740 4 $520 NPV Should the project be accepted or rejected? O accepted O rejected
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: Cash flow: -$1,300 $470 $1,780 $580 $420 -$160 NPV Should the project be accepted or rejected? rejected accepted
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: −$1,200 $430 $1,680 −$560 $380 −$140 NPV? Should the project be accepted or rejected?
Compute the NPV statistic for Project U if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: –$2,200 $630 $2,180 –$660 $580 –$240 NPV= Should the project be accepted or rejected?