Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: −$1,200 $430 $1,680 −$560 $380 −$140
NPV?
Should the project be accepted or rejected?
Time | 0 | 1 | 2 | 3 | 4 | 5 |
Cash Flow | -$1200 | $430 | $1680 | -$560 | $380 | -$140 |
Cost of capital = 9%
NPV = -$1200 + $430/1.09 + $1680/1.092 -$560/1.093 + $380/1.094 -$140/1.095
= -$1200 + $394.50 + $ 1414.02 - $432.42 + $ 269.20 - $90.99
= $ 354.31
Since NPV > 0 , project should be accepted.
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: Cash flow: -$1,300 $470 $1,780 $580 $420 -$160 NPV Should the project be accepted or rejected? rejected accepted
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: . Cash flow: 1. $710 2. $2,380 3. $700 4. $660 5 $280 $2,400 NPV Should the project be accepted or rejected? Orejected accepted
Compute the NPV statistic for Project U if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: –$2,200 $630 $2,180 –$660 $580 –$240 NPV= Should the project be accepted or rejected?
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: Cash flow: -68,300 $3,690 64,520 61,960 6640 NPV Should the project be accepted or rejected? rejected Daccepted
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow –$8,200 $3,670 $4,500 $1,840 $620 NPV $ Should the project be accepted or rejected? Rejected Accepted
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amounts should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: Cash flow: 0 $8,000 1 $3,350 2 $4,180 3 $1,520 4 $300 NPV Should the project be accepted or rejected? O accepted O rejected
Compute the NPV statistic for Project Y if the appropriate cost of capital is 13 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: Cash flow: 1 2 3 -$9,100 $3,570 $4,400 $1,740 4 $520 NPV Should the project be accepted or rejected? O accepted O rejected
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percen (Negative amount should be indicated by o minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.JA Time: Cash flow: $8,100 $3,370 $4,200 $1,540 $320 NPV Should the project be accepted or rejected? accepted rejected < Prev 7 7 search Arx
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Ne minus sign. Do not round intermediate calculations and round your final answer to 20 Project Y Time: Cash flow: $8,400 $3,710 $4,540 $1,880 $660 NPV Should the project be accepted or rejected? rejected • accepted
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow –$1,200 $390 $520 $560 $640 $140