Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)
=710/1.1+2380/1.1^2+660/1.1^4
=3063.19
Present value of outflows=2400+700/1.1^3+280/1.1^5
=3099.78
NPV=Present value of inflows-Present value of outflows
=3063.19-3099.78
=-36.59(Negative)(Approx).
Hence since NPV is negative;project must be rejected.
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: Cash flow: -$1,300 $470 $1,780 $580 $420 -$160 NPV Should the project be accepted or rejected? rejected accepted
Compute the NPV statistic for Project U if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: –$2,200 $630 $2,180 –$660 $580 –$240 NPV= Should the project be accepted or rejected?
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign Do not round intermediate calculations and round your final answer to 2 decimal places.) Protect Time: Cash flow: $1,900 $530 $660 $700 $780 $280 NPV Should the project be accepted or rejected? accepted rejected
Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow: −$1,900 $530 $660 $700 $780 $280 NPV? Should the project be accepted or rejected? accepted rejected
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: −$1,200 $430 $1,680 −$560 $380 −$140 NPV? Should the project be accepted or rejected?
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Ne minus sign. Do not round intermediate calculations and round your final answer to 20 Project Y Time: Cash flow: $8,400 $3,710 $4,540 $1,880 $660 NPV Should the project be accepted or rejected? rejected • accepted
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: Cash flow: -68,300 $3,690 64,520 61,960 6640 NPV Should the project be accepted or rejected? rejected Daccepted
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow –$8,200 $3,670 $4,500 $1,840 $620 NPV $ Should the project be accepted or rejected? Rejected Accepted
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amounts should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: Cash flow: 0 $8,000 1 $3,350 2 $4,180 3 $1,520 4 $300 NPV Should the project be accepted or rejected? O accepted O rejected
Compute the NPV statistic for Project Y if the appropriate cost of capital is 13 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: Cash flow: 1 2 3 -$9,100 $3,570 $4,400 $1,740 4 $520 NPV Should the project be accepted or rejected? O accepted O rejected