a. | Cost of each Job: | ||||||
Southside | Oceanview | Rocky heights | |||||
Direct materials | 5450 | 7635 | 6480 | ||||
Landscaper labor costs | 4810 | 5980 | 5525 | ||||
Overhead costs | 4440 | 5520 | 5100 | ||||
(Landscaper hours*Predetermined OH Rate) | (74*60) | (92*60) | (85*60) | ||||
Total cost | 14700 | 19135 | 17105 | ||||
b. | Landscape contracts in process balance=Cost of incomplete job=Cost of southside=$ 14700 | ||||||
c. | Actual overhead=$ 15400 | ||||||
Overhead applied=4440+5520+5100=$ 15060 | |||||||
Ending balance of operating overhead account=15400-15060=$ 340 | |||||||
d. | Landscaper labor cost per landscaper hour=Landscaper labor costs/Landscaper hours | ||||||
Southside | Oceanview | Rocky heights | |||||
Landscaper labor costs | a | 4810 | 5980 | 5525 | |||
Landscaper hours | b | 74 | 92 | 85 | |||
Landscaper labor cost per landscaper hour (a/b) | 65 | 65 | 65 | ||||
Total cost of the Job: | |||||||
$ | |||||||
Direct materials | 10450 | ||||||
Landscaper labor costs | 8125 | ||||||
(Landscaper hours*Landscaper Rate per hour) | (125*65) | ||||||
Overhead costs | 7500 | ||||||
(Landscaper hours*Predetermined OH Rate) | (125*60) | ||||||
Total | 26075 | ||||||
I appreciate your ratings |
Number 2 Larry's Lawn Services provides custom landscaping for homes and businesses and uses job order...
Larry’s Lawn Services provides custom landscaping for homes and businesses and uses job order costing to capture the cost of its landscaping jobs. There are no jobs in process at the beginning of May. Listed below are data concerning the three landscaping jobs conducted during May. Southside Oceanview Rocky Heights Direct materials $5,730 $7,910 $6,490 Landscaper labor costs $4,662 $5,544 $5,355 Landscaper hours 74 88 85 Overhead costs are applied to jobs on the basis of landscaper hours, and the...
Trimmer Lawn USA provides lawn care and landscaping services to commercial clients. Trimmer Lawn USA uses activity-based costing to bid on jobs and to evaluate their profitability. Trimmer Lawn USA reports the following budgeted annual costs: Wages and salaries $ 535,000 Depreciation 60,000 Supplies 75,000 Other overhead 67,000 Total overhead costs $ 737,000 John Gilroy, controller of Trimmer Lawn USA, has established four activity cost pools and the following budgeted activity for each cost pool: Activity Cost Pool Activity...
Trimmer Lawn USA provides lawn care and landscaping services to commercial clients. Trimmer Lawn USA uses activity-based costing to bid on jobs and to evaluate their profitability, Trimmer Lawn USA reports the following budgeted annual costs: Click the icon to view budgeted annual costs.) Click the icon to view additional information.) Read the requirements. Requirement 1. Allocate Trimmer Lawn USA's costs to the activity-cost pools and determine the activity rate for each pool. Start by allocating Trimmer Lawn USA's costs...
Greener Garden USA provides lawn care and landscaping services to commercial clients. Greener Garden USA uses activity-based costing to bid on jobs and to evaluate their profitability. Greener Garden USA reports the following budgeted annual costs: (Click the icon to view budgeted annual costs.) (Click the icon to view additional information.) Read the requirements. Requirement 1. Allocate Greener Garden USA's costs to the activity-cost pools and determine the activity rate for each pool. Start by allocating Greener Garden USA's costs...
Question Help Green Thumb USA provides lawn care and landscaping services to commercial clients. Green Thumb USA uses activity-based costing to bid on jobs and to evaluate their profitability. Green Thumb USA reports the following budgeted annual costs: (Click the icon to view budgeted annual costs.) (Click the icon to view additional information.) Read the requirements Requirement 1. Allocate Green Thumb USA's costs to the activity-cost pools and determine the activity rate for each pool. Start by allocating Green Thumb...
Heritage Gardens provides complete garden design and landscaping services. The company uses a job-order costing system to track the costs of its landscaping projects. The table below provides data concerning the three landscaping projects that were in progress during May. There was no work in process at the beginning of May. Project Williams Chandler Nguyen Designer-hours 300 180 220 Direct materials $ 5,800 $ 2,800 $ 4,600 Direct labor $ 3,400 $ 2,000 $ 2,500 Actual overhead costs were $33,000...
Heritage Gardens provides complete garden design and landscaping services. The company uses a job-order costing system to track the costs of its landscaping projects. The table below provides data concerning the three landscaping projects that were in progress during May. There was no work in process at the beginning of May. Designer-hours Direct materials Direct labor Project Williams Chandler Nguyen 330 210 250 $6,100 $3,100 $4,900 $3,700 $2,300 $2,800 Actual overhead costs were $36,000 for May. Overhead costs are applied...
Che Heritage Gardens provides complete garden design and landscaping services. The company uses a job-order costing system to track the costs of its landscaping projects. The table below provides data concerning the three landscaping projects that were in progress during May. There was no work in process at the beginning of May. Designer-hours Direct materials Direct labor Project Williams Chandler Nguyen 320 200 240 $6,000 $ 3,000 $ 4,800 $ 3,600 $2,200 $ 2,700 Actual overhead costs were $35,000 for...
Earth and Artistry, Inc. provides commercial landscaping services. Sasha Cairns, the firm’s owner, wants to develop cost estimates that she can use to prepare bids on jobs. After analyzing the firm’s costs, Cairns has developed the following preliminary cost estimates for each 1,000 square feet of landscaping. Direct material $ 460 Direct labor (5 direct-labor hours at $10 per hour) 50 Overhead (at $16 per direct-labor hour) 80 Total cost per 1,000 square feet $ 590 Cairns is quite...
Earth and Artistry, Inc. provides commercial landscaping services. Sasha Cairns, the firm’s owner, wants to develop cost estimates that she can use to prepare bids on jobs. After analyzing the firm’s costs, Cairns has developed the following preliminary cost estimates for each 1,000 square feet of landscaping. Direct material $ 440 Direct labor (5 direct-labor hours at $10 per hour) 50 Overhead (at $16 per direct-labor hour) 80 Total cost per 1,000 square feet $ 570 Cairns is quite...