Earth and Artistry, Inc. provides commercial landscaping services. Sasha Cairns, the firm’s owner, wants to develop cost estimates that she can use to prepare bids on jobs. After analyzing the firm’s costs, Cairns has developed the following preliminary cost estimates for each 1,000 square feet of landscaping.
Direct material | $ | 460 | |
Direct labor (5 direct-labor hours at $10 per hour) | 50 | ||
Overhead (at $16 per direct-labor hour) | 80 | ||
Total cost per 1,000 square feet | $ | 590 | |
Cairns is quite certain about the estimates for direct material and direct labor. However, she is not as comfortable with the overhead estimate. The estimate for overhead is based on the overhead costs that were incurred during the past 12 months as presented in the following schedule. The estimate of $16 per direct-labor hour was determined by dividing the total overhead costs for the 12-month period ($640,000) by the total direct-labor hours (40,000).
Regular Direct- | Overtime Direct- | Total Direct- | |||||||
Total Overhead | Labor Hours | Labor Hours* | Labor Hours | ||||||
January | $ | 49,000 | 2,810 | 190 | 3,000 | ||||
February | 47,000 | 3,270 | 40 | 3,310 | |||||
March | 54,000 | 3,500 | 60 | 3,560 | |||||
April | 48,000 | 3,000 | 250 | 3,250 | |||||
May | 60,000 | 3,470 | 460 | 3,930 | |||||
June | 58,000 | 3,440 | 770 | 4,210 | |||||
July | 60,000 | 3,400 | 620 | 4,020 | |||||
August | 48,000 | 2,670 | 310 | 2,980 | |||||
September | 49,000 | 2,930 | 40 | 2,970 | |||||
October | 56,000 | 2,750 | 30 | 2,780 | |||||
November | 59,000 | 3,160 | 20 | 3,180 | |||||
December | 52,000 | 2,590 | 220 | 2,810 | |||||
Total | $ | 640,000 | 36,990 | 3,010 | 40,000 | ||||
*The overtime premium is 50 percent of the direct-labor wage rate.
Cairns believes that overhead is affected by total monthly
direct-labor hours. Cairns decided to perform a least-squares
regression of overhead (OH) on total direct-labor hours (DLH). The
following regression formula was obtained.
OH = $32,207 + $6.34 DLH
Required:
Using the overhead formula that was derived from the least-squares regression, determine a total variable-cost estimate for each 1,000 square feet of landscaping.
Cairns has been asked to submit a bid on a landscaping project for the city government consisting of 66,000 square feet. Cairns estimates that 50 percent of the direct-labor hours required for the project will be on overtime. Calculate the incremental costs that should be included in any bid that Cairns would submit on this project. Use the overhead formula derived from the least-squares regression.
After attending a seminar on activity-based costing, Cairns decided to further analyze the company’s activities and costs. She discovered that a more accurate portrayal of the firm’s cost behavior could be achieved by dividing overhead into three separate pools, each with its own cost driver. Separate regression equations were estimated for each of the cost pools, with the following results.
OH1 = $10,700 + $3.50 DLH,
where DLH denotes direct-labor hours
OH2= $9,100 + $13.90 SFS,
where SFS denotes the number of square feet of turf seeded (in
thousands)
OH3 = $8,400 + $7.00 PL,
where PL denotes the number of individual plantings (e.g., trees
and shrubs)
Assume that 5 direct-labor hours will be needed to landscape each
1,000 square feet, regardless of the specific planting material
used.
a. Suppose the landscaping project for the city will involve seeding all 66,000 square feet of turf and planting 90 trees and shrubs. Calculate the incremental variable overhead cost that Cairns should include in the bid.
b. Recompute the incremental variable overhead cost for the city’s landscaping project assuming half of the 66,000-square-foot landscaping area will be seeded and there will be 240 individual plantings. The plantings will cover the entire 66,000-square-foot area.
Complete this question by entering your answers in the tabs below.
1) Using the overhead formula that was derived from the least-squares regression, determine a total variable-cost estimate for each 1,000 square feet of landscaping. (Do not round intermediate calculations. Round your final answer to 2 decimal places.)
|
2.Cairns has been asked to submit a bid on a landscaping project for the city government consisting of 66,000 square feet. Cairns estimates that 50 percent of the direct-labor hours required for the project will be on overtime. Calculate the incremental costs that should be included in any bid that Cairns would submit on this project. Use the overhead formula derived from the least-squares regression. (Do not round intermediate calculations. Round your final answer to 2 decimal places.)
Show less
|
3. Suppose the landscaping project for the city will involve seeding all 66,000 square feet of turf and planting 90 trees and shrubs. Calculate the incremental variable overhead cost that Cairns should include in the bid. (Do not round intermediate calculations and round your final answer to 2 decimal places.)
|
4.Recompute the incremental variable overhead cost for the city’s landscaping project assuming half of the 66,000-square-foot landscaping area will be seeded and there will be 240 individual plantings. The plantings will cover the entire 66,000-square-foot area. (Do not round intermediate calculations and round your final answer to 2 decimal places.)
|
THE QUESTION IS COMPLETE IT DOESNT GIVE MORE INFORMATION!!!
1 | Regression formula: | ||||||
OH = $32207 + $6.34 DLH | |||||||
Variable overhead cost=$ 6.34 per DLH | |||||||
Total variable cost: | |||||||
$ | |||||||
Direct material | 460 | ||||||
Direct labor | (5*10) | 50 | |||||
Variable overhead | (5*6.34) | 31.7 | |||||
Total | 541.7 | ||||||
2 | Landscape in thousands of square feet=66000/1000=66 | ||||||
Incremental cost: | |||||||
$ | |||||||
Direct material | (66*460) | 30360 | |||||
Direct labor | (66*50) | 3300 | |||||
Variable overhead | (66*6.34) | 418.44 | |||||
Overtime | (Note:1) | 2475 | |||||
Total | 36553.44 | ||||||
Note:1 | |||||||
Overtime in hours=Total DLH*50%=66*5*50%=165 DLH | |||||||
Overtime rate per hour=DL wage rate+(DL wage rate*50%)=10+(10*50%)=10+5=$ 15 | |||||||
Overtime cost=Overtime in hours*Overtime rate per hour=165*15=$ 2475 | |||||||
3 | Incremental variable overhead cost: | ||||||
$ | |||||||
OH1 | (66*5*3.50) | 1155 | |||||
(Landscape in 1000 sq ft*DLH per 1000 sq ft*3.50) | |||||||
OH2 | (66*13.90) | 917.4 | |||||
(Landscape in 1000 sq ft*13.90) | |||||||
OH3 | (90*7) | 630 | |||||
(Number of individual plantings*7) | |||||||
Total | 2702.4 | ||||||
4 | Number of square feet of turf seeded (in thousands)=(66000*50%)/1000=33 | ||||||
Incremental variable overhead cost: | |||||||
$ | |||||||
OH1 | (33*5*3.50) | 577.5 | |||||
(Landscape in 1000 sq ft*DLH per 1000 sq ft*3.50) | |||||||
OH2 | (33*13.90) | 458.7 | |||||
(Landscape in 1000 sq ft*13.90) | |||||||
OH3 | (240*7) | 1680 | |||||
(Number of individual plantings*7) | |||||||
Total | 2716.2 | ||||||
Earth and Artistry, Inc. provides commercial landscaping services. Sasha Cairns, the firm’s owner, wants to develop...
Earth and Artistry, Inc. provides commercial landscaping services. Sasha Cairns, the firm’s owner, wants to develop cost estimates that she can use to prepare bids on jobs. After analyzing the firm’s costs, Cairns has developed the following preliminary cost estimates for each 1,000 square feet of landscaping. Direct material $ 440 Direct labor (5 direct-labor hours at $10 per hour) 50 Overhead (at $16 per direct-labor hour) 80 Total cost per 1,000 square feet $ 570 Cairns is quite...
Earth and Artistry, Inc. provides commercial landscaping services. Sasha Cairns, the firm’s owner, wants to develop cost estimates that she can use to prepare bids on jobs. After analyzing the firm’s costs, Cairns has developed the following preliminary cost estimates for each 1,000 square feet of landscaping. Direct material $ 440 Direct labor (5 direct-labor hours at $10 per hour) 50 Overhead (at $16 per direct-labor hour) 80 Total cost per 1,000 square feet $ 570 Cairns is quite...
Number 2 Larry's Lawn Services provides custom landscaping for homes and businesses and uses job order costing to capture the cost of its landscaping jobs. There are no jobs in process at the beginning of May. Listed below are data concerning the three landscaping jobs conducted during May Rocky Heights $6,480 $5,525 85 Oceanview $7,635 $5,980 92 Southside $5,450 $4,810 Direct materials Landscaper labor costs Landscaper hours 74 Overhead costs are applied to jobs on the basis of landscaper hours,...
Trimmer Lawn USA provides lawn care and landscaping services to commercial clients. Trimmer Lawn USA uses activity-based costing to bid on jobs and to evaluate their profitability. Trimmer Lawn USA reports the following budgeted annual costs: Wages and salaries $ 535,000 Depreciation 60,000 Supplies 75,000 Other overhead 67,000 Total overhead costs $ 737,000 John Gilroy, controller of Trimmer Lawn USA, has established four activity cost pools and the following budgeted activity for each cost pool: Activity Cost Pool Activity...
Greener Garden USA provides lawn care and landscaping services to commercial clients. Greener Garden USA uses activity-based costing to bid on jobs and to evaluate their profitability. Greener Garden USA reports the following budgeted annual costs: (Click the icon to view budgeted annual costs.) (Click the icon to view additional information.) Read the requirements. Requirement 1. Allocate Greener Garden USA's costs to the activity-cost pools and determine the activity rate for each pool. Start by allocating Greener Garden USA's costs...
Larry’s Lawn Services provides custom landscaping for homes and businesses and uses job order costing to capture the cost of its landscaping jobs. There are no jobs in process at the beginning of May. Listed below are data concerning the three landscaping jobs conducted during May. Southside Oceanview Rocky Heights Direct materials $5,730 $7,910 $6,490 Landscaper labor costs $4,662 $5,544 $5,355 Landscaper hours 74 88 85 Overhead costs are applied to jobs on the basis of landscaper hours, and the...
Question Help Green Thumb USA provides lawn care and landscaping services to commercial clients. Green Thumb USA uses activity-based costing to bid on jobs and to evaluate their profitability. Green Thumb USA reports the following budgeted annual costs: (Click the icon to view budgeted annual costs.) (Click the icon to view additional information.) Read the requirements Requirement 1. Allocate Green Thumb USA's costs to the activity-cost pools and determine the activity rate for each pool. Start by allocating Green Thumb...
Trimmer Lawn USA provides lawn care and landscaping services to commercial clients. Trimmer Lawn USA uses activity-based costing to bid on jobs and to evaluate their profitability, Trimmer Lawn USA reports the following budgeted annual costs: Click the icon to view budgeted annual costs.) Click the icon to view additional information.) Read the requirements. Requirement 1. Allocate Trimmer Lawn USA's costs to the activity-cost pools and determine the activity rate for each pool. Start by allocating Trimmer Lawn USA's costs...
Western Components, Inc. manufactures a variety of pinions, gears and other component parts used by companies around the world. Their major customer is a large west-coast aircraft manufacturer. Currently, Western has substantial unused capacity due to a downturn in production for this major customer. This in turn has caused a significant drop in profits at Western since their workers are highly skilled and Western does not want to reduce head-count during this downturn which they expect to be temporary. Sally...
Jenco, Inc., manufactures a combination fertilizer and weedkiller under the name Fertikil. This is the only product Jenco produces. Fertikil is sold nationwide through normal marketing channels to retail nurseries and garden stores. Taylor Nursery plans to sell a similar fertilizer and weedkiller compound through its regional nursery chain under its own private label. Taylor has asked Jenco to submit a bid for a 25,000-pound order of the private brand compound. Although the chemical composition of the Taylor compound differs...