Question

( I need help with questions 8, 9, 10,11, 12) CALIFORNIA COMPANY …. Uses job order...

( I need help with questions 8, 9, 10,11, 12)

CALIFORNIA COMPANY

…. Uses job order costing. At the start of the year, January 1, the company had work-in-process which consisted of the following jobs and costs:

Job 1

Job 2

Job 3

Direct materials

$ 1,600

$ 2,000

$    850

Direct labor

    1,900

    1,200

       900

Applied overhead

    1,710

    1,080

       810

During the first quarter 3 more jobs were started – Job 4, Job 5 and Job 6. The following cost information is available for costs incurred during the month of January:

Job 1

Job 2

Job 3

Job 4

Job 5

Job 6

Direct materials

1,800

1,735

6,550

4,500

1,300

600

Direct labor

1,000

1,400

4,200

1,800

800

860

During the quarter, jobs 1, 3, 4 and 6 were all completed. In addition, Jobs 3 and 6 were sold before the end of the quarter.

The company uses normal costing and closes under- and over-applied overhead directly to Cost of Goods Sold. There was no finished-goods inventory at the start of the period. Selling and administrative expenses totaled $3,986 for the quarter. Actual overhead for the quarter totaled $19,000. The company had no other non-operating gains or losses. Assume a tax rate of 35%.

Required:

  1. The company applies overhead based on direct labor cost – compute the predetermined overhead rate.
  2. Set up summary work in process T-accounts and job cost sheets for each job for the first quarter.
  3. Post all first quarter costs to the summary work in process AND individual job cost sheets. When posting, make sure you do a total column for each cost element and ONLY POST TOTALS to the general ledger T accounts.
  4. Calculate the ending balance for each job as of March 31.
  5. Calculate the ending balance in work-in process as of March 31.
  6. Calculate the cost of goods manufactured for the quarter.
  7. Calculate the normal (unadjusted) cost of goods sold for the quarter. Calculate the adjusted cost of goods sold. WHY are they different? Why do we need both? What is the reason for the normal cost of goods sold?
  8. During the quarter, did finished goods inventory increase or decrease AND by how much? WHY?
  9. Compute the over/underapplied overhead for the quarter.
  10. Assuming that the company prices its jobs at full cost plus 50%, calculate the sales revenue for the quarter.
  11. Prepare an income statement for the first quarter.
  12. WHY would the company use normal costing versus actual costing?
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Total Applied Overhead $3,600 (1710+1080+810)
Direct labor Cost $4,000 (1900+1200+900)
PREDETERMINED OVERHEAD RATE $0.90 (3600/4000)
WOTK IN PROCESS T ACCOUNTS
DEBIT CREDIT
Beginning Balance $12,050 (4450+4000+3600)
Direct Materials $16,485 Transferred to Finished Goods $36,154 (8910+17090+7920+2234)
Direct labor $10,060
Aplied Overhead $9,054
Ending Balance Balance $11,495
JOB COST SHEET
JOB1 JOB2 JOB3 JOB4 JOB5 JOB6 TOTAL
a Beginning Direct Materials $1,600 $2,000 $850 $4,450
b Direct materials cost incurred $1,800 $1,735 $6,550 $4,500 $1,300 $600 $16,485
C=a+b Total Direct materials Cost $3,400 $3,735 $7,400 $4,500 $1,300 $600 $20,935
d Beginning Direct labor $1,900 $1,200 $900 $4,000
e Direct Labor cost incurred $1,000 $1,400 $4,200 $1,800 $800 $860 $10,060
F=d+e Total Direct Labor Cost Cost $2,900 $2,600 $5,100 $1,800 $800 $860 $14,060
g Beginning Applied overhead $1,710 $1,080 $810 $3,600
h=0.9*e Applied Overhead during the quarter $900 $1,260 $3,780 $1,620 $720 $774 $9,054
I=g+h Total Applied Overhead Cost $2,610 $2,340 $4,590 $1,620 $720 $774 $12,654
J=C+F+I Total Manufacturing Cost(Ending Balance) $8,910 $8,675 $17,090 $7,920 $2,820 $2,234 $47,649
Cost of goods manufactured $36,154
Unadjusted Cost of Goods Sold $19,324 (Job3:17090+Job6:2234)
Applied Overhead during the quarter $9,054
Actual Overhead Incurred in the qtr $19,000
Underappled Overhead=19000-9054 $9,946
Adjusted Cost of goods sold $29,270 (19324+9946)
Sales Revenue=29270*1.5 $43,905
INCOME STATEMENT
Sales Revenue $43,905
Cost of goods sold $29,270
Gross Profit $14,635
Less:Selling & admininstration expenses $3,986
Net Income $10,649
Add a comment
Know the answer?
Add Answer to:
( I need help with questions 8, 9, 10,11, 12) CALIFORNIA COMPANY …. Uses job order...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate...

    Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: beginning work in process Job #1-A $3,250 Job #3-G $2,690 Job #7-L $3,720 COSTS ADDED DURING JUNE: direct materials direct labor ..... $4,680 3,530 $3,950 4,180 $2,870 2,410 During June,...

  • Question 4 Moor Company uses a job-order costing system and applies overhead costs to jobs at...

    Question 4 Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1 - A $3,250 Job #3-G $2,690 Job #7-L $3,720 beginning work in process ..... COSTS ADDED DURING JUNE: direct materials ...... direct labor ......... $4,689 3,530...

  • Question 4 Moor Company uses a job-order costing system and applies overhead costs to jobs at...

    Question 4 Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1-A $3,250 Job #3-6 $2,690 Job #7-L $3,720 beginning work in process ..... COSTS ADDED DURING JUNE: direct materials ...... direct labor $4,680 3,530 $3,950 4,180 $2,870...

  • I need help with this question. The Polaris Company uses a job order costing system. The...

    I need help with this question. The Polaris Company uses a job order costing system. The following transactions occurred in October a. Raw materials purchased on account, $210,000 b. Raw materials used in production, $189.000 (S151.200 direct materials and $37.800 indirect materials). c. Accrued direct labor cost of $49,000 and indirect labor cost of $21.000. d. Depreciation recorded on factory equipment. $105.000. e. Other manufacturing overhead costs accrued during October $131,000. . The company applies manufacturing overhead cost to production...

  • Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor...

    Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started th e month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1 - A $3,250 Job #3-G $2,690 Job #7-L $3,720 beginning work in process COSTS ADDED DURING JUNE: $3,950 4,180 $4,680 3,530 $2,870 2,410 direct materials direct labor...

  • Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate...

    Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1-A Job #3-G Job #7-L beginning work in process ..... $3,250 $2,690 $3,720 COSTS ADDED DURING JUNE: direct materials .............. $4,680 $3,950 $2,870 direct labor .................. 3,530 4,180 2,410...

  • Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate...

    Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1-A Job #3-G Job #7-L beginning work in process ..... $3,250 $2,690 $3,720 COSTS ADDED DURING JUNE: direct materials .............. $4,680 $3,950 $2,870 direct labor .................. 3,530 4,180 2,410...

  • Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate...

    Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1-A Job #3-G Job #7-L beginning work in process ..... $3,250 $2,690 $3,720 COSTS ADDED DURING JUNE: direct materials .............. $4,680 $3,950 $2,870 direct labor .................. 3,530 4,180 2,410...

  • Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate...

    Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1-A Job #3-G Job #7-L beginning work in process ..... $3,250 $2,690 $3,720 COSTS ADDED DURING JUNE: direct materials .............. $4,680 $3,950 $2,870 direct labor .................. 3,530 4,180 2,410...

  • Question 5 Moor Company uses a job-order costing system and applies overhead costs to jobs at...

    Question 5 Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job Job #1-A $3,250 Job #3-G $2,690 beginning work in process .. $3,720 COSTS ADDED DURING JUNE: direct materials ... direct labor ........ $4,680 3,530 $3,950 $2,870 2,410...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT