(A) | (B) | c=a/b | ||||||||||
Total | estimated | overhead | ||||||||||
Activity cost pool | cost | cost driver | rate | |||||||||
Machining | 250,600 | 71,600 | 3.5 | per machine hour | ||||||||
Designing costs | 61,600 | 7,000 | 8.8 | per design hour | ||||||||
Setup costs | 66,402 | 465 | 142.8 | per batch | ||||||||
378,602 | ||||||||||||
Product A | Product B | Product C | ||||||||||
OH rate | activity | overhead | OH rate | activity | overhead | OH rate | activity | overhead | ||||
Activity cost pool | Assigned | Assigned | Assigned | |||||||||
Machining | 3.5 | 26,000 | 91000 | 3.5 | 36,000 | 126000 | 3.5 | 9,600 | 33600 | |||
Designing costs | 8.8 | 2,800 | 24640 | 8.8 | 1,600 | 14080 | 8.8 | 2,600 | 22880 | |||
Setup costs | 142.8 | 40 | 5712 | 142.8 | 170 | 24276 | 142.8 | 255 | 36414 | |||
overhead assigned | 121352 | 164356 | 92894 | |||||||||
Total overhead | ||||||||||||
1) | Assigned | |||||||||||
Product A | 121352 | |||||||||||
Product B | 164356 | |||||||||||
Product C | 92894 | |||||||||||
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $ 250,680 Number of machine hours 61,600 Number of design hours 66,482 Number of batches Estimated Cost Driver 71,600 7.ee 465 Required: 1. Compute the activity rate for each activity 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering...
Required Information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,eee Number of machine hours 73,6ee Number of design hours 71,600 Number of batches Estimated Cost Driver Be, evo 8, eae 500 Re 1. red: mpute the activity rate for each activity. 1551fy each activity as facility, product, batch, or unit level. complete this question by...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Part 2 of 2 136 points Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8.000 500 Suppose that Gable Company manufactures three products, A, B, and C. Information about these products follows: Number of machine hours...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $280, 460 Number of machine hours 67,500 Number of design hours 70,070 Number of batches Estimated Cost Driver 75,800 7,500 490 Suppose that Gable Company manufactures three products, A, B, and C. Information about these products follows: Number of machine hours Number of design hours Number...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total cost of Pool Cost Driver $454,960 Number of machine hours 100,000 Number of design hours 72,720 Number of batches Estimated Cost Driver 96,800 10,000 505 E4-4 (Algo) Assigning Costs Using Activity Rates (LO 4-4) Suppose that Gable Company manufactures three products, A, B, and C. Information about these products follows: Number of machine...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $183,300 Number of machine hours 47,725 Number of design hours 71,150 Number of batches Estimated Cost Driver 61,100 5,750 500 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8,000 500 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $171,100 Number of machine hours 45,100 Number of design hours 66,123 Number of batches Estimated Cost Driver 59,000 5,500 465 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your answers in...
! Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $416,700 Number of machine hours 93,100 Number of design hours 73,338 Number of batches Estimated Cost Driver 92,600 9,500 510 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $171,100 Number of machine hours 45,100 Number of design hours 66,123 Number of batches Estimated Cost Driver 59,000 5,500 465 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...