Product A =$224,360
Product B =$272,080
Product C =$131,240
Explanation:
Activity based overhead rate = total overhead cost / cost driver
1. Machining = $454,960/96,800 = $4.7 per machine hour
2. Designing costs = $100,000/10,000 = $10 per design hour
3. Setup costs = $72,720/505 = $144 per batch
Overhead assigned to product A
Machining = $4.7 x 38,000 = $178,600
Designing costs = $10 x 4000 = $40,000
Setup costs = $144 x 40 = $5760
Total overhead assigned = $224,360
Overhead assigned to product B
Machining = $4.7 x 48,000 = $225,600
Designing costs=$10 x 2200 =$22,000
Setup costs = $144 x 170 = $24,480
Total overhead assigned = $272,080
Overhead assigned to product C
Machining = $4.7 x 10,800 =$50,760
Designing costs = $10 x 3800 =$38,000
Setup costs = $144 x 295 = $42,480
Total overhead cost assigned = $131,240
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable...
Required Information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,eee Number of machine hours 73,6ee Number of design hours 71,600 Number of batches Estimated Cost Driver Be, evo 8, eae 500 Re 1. red: mpute the activity rate for each activity. 1551fy each activity as facility, product, batch, or unit level. complete this question by...
Required information 14-3, E4-4 and 54-5 Gable Company uses three activity cost pools. Each pool has a cost driver Information for Gable Company follows: Total Estimated Activity Cost Cost of Cost Pools Pool Cost Driver Driver BAE Number of Machining $345, 220 84,200 machine hours Designing 79,900 Number of design ign 8,500 costs hours Setup costs 70 982 Number of 10,903 batches 495 E4-4 (Algo) Assigning Costs Using Activity Rates (LO 4-4) Suppose that Gable Company manufactures three products, A....
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $250,680 Number of machine hours 61,600 Number of design hours 66,402 Number of batches Estimated Cost Driver 71,600 7, eee 465 Suppose that Gable Company manufactures three products, A, B, and C. Information about these products follows: Number of machine hours Number of design hours Number...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $280, 460 Number of machine hours 67,500 Number of design hours 70,070 Number of batches Estimated Cost Driver 75,800 7,500 490 Suppose that Gable Company manufactures three products, A, B, and C. Information about these products follows: Number of machine hours Number of design hours Number...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Part 2 of 2 136 points Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8.000 500 Suppose that Gable Company manufactures three products, A, B, and C. Information about these products follows: Number of machine hours...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $183,300 Number of machine hours 47,725 Number of design hours 71,150 Number of batches Estimated Cost Driver 61,100 5,750 500 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $171,100 Number of machine hours 45,100 Number of design hours 66,123 Number of batches Estimated Cost Driver 59,000 5,500 465 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your answers in...
! Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $416,700 Number of machine hours 93,100 Number of design hours 73,338 Number of batches Estimated Cost Driver 92,600 9,500 510 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8,000 500 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8,000 500 Required: 1. Compute the activity rate for each activity. (Round your answers to 2 decimal places.) Activity Rate per Machine Hour Activity Machining Design Costs Setup per Design...