Question

Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Co
question by entering your answers in the tabs below. Required 1 Required 2 Classify each activity as facility, product, batch
Suppose that Gable Company manufactures three products, A, B, and C. Information about these products follows: Number of mach
Suppose that Gable Company manufactures three products, A, B, and C. Information about these Number of machine hours Number o
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1] activity rate = total cost/cost driver

total cost estimated cost driver activity rate
Machining $171,100 59,000 $2.9 per machine hour[171,100/59,000]
designing cost $45,100 5,500 $8.2 per Design hour [$45,100/5,500]
set up cost $66,123 465 $142.2 per Batch
Machining Unit level The machine cost is related directly to production. it will be defined as unit level cost
design cost Product level Design is related to a particular product and not the individual units. so it is product level cost
setup cost Batch level Setup Cost involves cost associated with setting up machines for production of a specific batch of the product.

2] overhead cost allocated = cost per driver*cost driver used

total cost activity rate A B C
Machining $171,100 $2.9 per machine hour[171,100/59,000] $58,000[$2.9*20,000] $87,000[$2.9*30,000] $26,100[$2.9*9,000]
designing cost $45,100 $8.2 per Design hour [$45,100/5,500] $18,040[$8.2*2,200] $10,660[$8.2*1,300] $16,400[$8.2*2,000]
set up cost $66,123 $142.2 per Batch $5,688[$142.2*40] $24,174[$142.2*170] $36,261[$142.2*255]
Total $81,728 $121,834 $78,761

1. ACTIVITY PROPORTIONS

A

Estimated driver/ Total driver* total cost
Machining $58,000[20,000/59,000]*$171,100
Desiging $8,040(0.4*$45,100)[2,200/5,500]
Set up $5,688[(40/465)*$66,123]
Total $71,728

B

Estimated driver/ Total driver* total cost
Machining $87,000[30,000/59,000]*$171,100
Desiging $10,660[1300/5,500]*$45,100
Set up $24,174[(170/465)*$66,123]
Total $121,834

C

Estimated driver/ Total driver* total cost
Machining $26,100[9,000/59,000]*$171,100
Desiging $16,400[2,000/5,500]*$45,100
Set up $36,261[(255/465)*$66,123]
Total $78,761

Please upvote if you find this helpful.Incase of query please comment.

Add a comment
Know the answer?
Add Answer to:
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information...

    Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $183,300 Number of machine hours 47,725 Number of design hours 71,150 Number of batches Estimated Cost Driver 61,100 5,750 500 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...

  • Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable...

    Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total cost of Pool Cost Driver $454,960 Number of machine hours 100,000 Number of design hours 72,720 Number of batches Estimated Cost Driver 96,800 10,000 505 E4-4 (Algo) Assigning Costs Using Activity Rates (LO 4-4) Suppose that Gable Company manufactures three products, A, B, and C. Information about these products follows: Number of machine...

  • Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information...

    Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $250,680 Number of machine hours 61,600 Number of design hours 66,402 Number of batches Estimated Cost Driver 71,600 7, eee 465 Suppose that Gable Company manufactures three products, A, B, and C. Information about these products follows: Number of machine hours Number of design hours Number...

  • Required Information Gable Company uses three activity cost pools. Each pool has a cost driver. Information...

    Required Information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,eee Number of machine hours 73,6ee Number of design hours 71,600 Number of batches Estimated Cost Driver Be, evo 8, eae 500 Re 1. red: mpute the activity rate for each activity. 1551fy each activity as facility, product, batch, or unit level. complete this question by...

  • ! Required information Gable Company uses three activity cost pools. Each pool has a cost driver....

    ! Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $416,700 Number of machine hours 93,100 Number of design hours 73,338 Number of batches Estimated Cost Driver 92,600 9,500 510 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering...

  • Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information...

    Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8,000 500 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...

  • Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable...

    Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8,000 500 Required: 1. Compute the activity rate for each activity. (Round your answers to 2 decimal places.) Activity Rate per Machine Hour Activity Machining Design Costs Setup per Design...

  • Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable...

    Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8,000 500 Required: 1. Compute the activity rate for each activity. (Round your answers to 2 decimal places.) Activity Rate per Machine Hour Activity Machining Design Costs Setup per Design...

  • Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information...

    Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $ 250,680 Number of machine hours 61,600 Number of design hours 66,482 Number of batches Estimated Cost Driver 71,600 7.ee 465 Required: 1. Compute the activity rate for each activity 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering...

  • Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information...

    Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $171,100 Number of machine hours 45,100 Number of design hours 66,123 Number of batches Estimated Cost Driver 59,000 5,500 465 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT