1] activity rate = total cost/cost driver
total cost | estimated cost driver | activity rate | ||
Machining | $171,100 | 59,000 | $2.9 per machine hour[171,100/59,000] | |
designing cost | $45,100 | 5,500 | $8.2 per Design hour [$45,100/5,500] | |
set up cost | $66,123 | 465 | $142.2 per Batch |
Machining | Unit level | The machine cost is related directly to production. it will be defined as unit level cost |
design cost | Product level | Design is related to a particular product and not the individual units. so it is product level cost |
setup cost | Batch level | Setup Cost involves cost associated with setting up machines for production of a specific batch of the product. |
2] overhead cost allocated = cost per driver*cost driver used
total cost | activity rate | A | B | C | |
Machining | $171,100 | $2.9 per machine hour[171,100/59,000] | $58,000[$2.9*20,000] | $87,000[$2.9*30,000] | $26,100[$2.9*9,000] |
designing cost | $45,100 | $8.2 per Design hour [$45,100/5,500] | $18,040[$8.2*2,200] | $10,660[$8.2*1,300] | $16,400[$8.2*2,000] |
set up cost | $66,123 | $142.2 per Batch | $5,688[$142.2*40] | $24,174[$142.2*170] | $36,261[$142.2*255] |
Total | $81,728 | $121,834 | $78,761 |
1. ACTIVITY PROPORTIONS
A
Estimated driver/ Total driver* total cost | |||||
Machining | $58,000[20,000/59,000]*$171,100 | ||||
Desiging | $8,040(0.4*$45,100)[2,200/5,500] | ||||
Set up | $5,688[(40/465)*$66,123] | ||||
Total | $71,728 |
B
Estimated driver/ Total driver* total cost | |
Machining | $87,000[30,000/59,000]*$171,100 |
Desiging | $10,660[1300/5,500]*$45,100 |
Set up | $24,174[(170/465)*$66,123] |
Total | $121,834 |
C
Estimated driver/ Total driver* total cost | |
Machining | $26,100[9,000/59,000]*$171,100 |
Desiging | $16,400[2,000/5,500]*$45,100 |
Set up | $36,261[(255/465)*$66,123] |
Total | $78,761 |
Please upvote if you find this helpful.Incase of query please comment.
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $183,300 Number of machine hours 47,725 Number of design hours 71,150 Number of batches Estimated Cost Driver 61,100 5,750 500 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total cost of Pool Cost Driver $454,960 Number of machine hours 100,000 Number of design hours 72,720 Number of batches Estimated Cost Driver 96,800 10,000 505 E4-4 (Algo) Assigning Costs Using Activity Rates (LO 4-4) Suppose that Gable Company manufactures three products, A, B, and C. Information about these products follows: Number of machine...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $250,680 Number of machine hours 61,600 Number of design hours 66,402 Number of batches Estimated Cost Driver 71,600 7, eee 465 Suppose that Gable Company manufactures three products, A, B, and C. Information about these products follows: Number of machine hours Number of design hours Number...
Required Information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,eee Number of machine hours 73,6ee Number of design hours 71,600 Number of batches Estimated Cost Driver Be, evo 8, eae 500 Re 1. red: mpute the activity rate for each activity. 1551fy each activity as facility, product, batch, or unit level. complete this question by...
! Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $416,700 Number of machine hours 93,100 Number of design hours 73,338 Number of batches Estimated Cost Driver 92,600 9,500 510 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8,000 500 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8,000 500 Required: 1. Compute the activity rate for each activity. (Round your answers to 2 decimal places.) Activity Rate per Machine Hour Activity Machining Design Costs Setup per Design...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8,000 500 Required: 1. Compute the activity rate for each activity. (Round your answers to 2 decimal places.) Activity Rate per Machine Hour Activity Machining Design Costs Setup per Design...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $ 250,680 Number of machine hours 61,600 Number of design hours 66,482 Number of batches Estimated Cost Driver 71,600 7.ee 465 Required: 1. Compute the activity rate for each activity 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $171,100 Number of machine hours 45,100 Number of design hours 66,123 Number of batches Estimated Cost Driver 59,000 5,500 465 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...