Question

Midterm 1 The Lee Company uses a job-order cost system. The following data were recorded for June: Job Number 235 236 237 Jun

0 0
Add a comment Improve this question Transcribed image text
Answer #1

June 1- Work in progress Add: Direct Material Add: Direct Labor Add: Overhead Cost Job Number 235 236 237 238 $2,500 $1,500 $

Add a comment
Know the answer?
Add Answer to:
Midterm 1 The Lee Company uses a job-order cost system. The following data were recorded for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The Lee Company uses a job-order costing system. The following data were recorded...continues

    The Lee Company uses a job-order costing system. The following data were recorded for June:Added During June----JobNumberJune 1Work in ProcessInventory DirectMaterials DirectLabor235 $2,500 $600 $400236 $1,500 $800 $1,000237 $1,000 $1,200 $1,750238 $800 $1,500 $2,250Overhead is charged to production at 80% of direct materials cost. Jobs 235, 237, and 238 were completed during June and transferred to finished goods. Jobs 235 and238 have been delivered to customers.20. Lee Company's cost of goods sold for June wasA. $14,640.B. $15,520.C. $9,730.D. $10,170.Please SHOW...

  • The Lee Corporation uses a job-order costing system. The following data were recorded for June: June...

    The Lee Corporation uses a job-order costing system. The following data were recorded for June: June 1 Added During June Job Number Work in Process Inventory Direct Materials Direct Labor 235 $3,150 $860 $595 236 $2,210 $1,260 $1,435 237 $1,585 $1,720 $2,530 238 $1,125 $2,410 $3,290 Overhead is charged to production at 90% of direct materials cost. Jobs 235, 237, and 238 were completed during June and transferred to finished goods. Jobs 235 and 238 have been delivered to customers....

  • Data for the next 4 questions: The Donaldson Company uses a job-order cost system. The following...

    Data for the next 4 questions: The Donaldson Company uses a job-order cost system. The following data were recorded for June: June 1st DM and DL Costs Added During June Work in Process Job Number Inventory (per Job Direct Materials Direct Labor Cost Sheets) 175 $1,800 $1,000 $ 400 $1,000 $1,500 $ 800 I 177 $ 600 $2,000 $1,200 178 $ 700 $1,500 $1,000 Overhead is applied to jobs at the rate of 60 percent of direct labor cost. Jobs...

  • Question 13 points) Data for the next 2 questions: The Shaw Company uses a job-order cost...

    Question 13 points) Data for the next 2 questions: The Shaw Company uses a job-order cost system. Factory overhead is applied to jobs at the rate of 140% of direct labor cost. Jobs 475, 477, and 478 were completed during April and transferred to finished goods. Jobs 475 and 478 have been delivered to the customer. The following data were recorded for April: 100 Added During April Direct Direct Number Materials Labor $ 500 S 800 476 $ 700 $1,000...

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

  • Samuelson's Work in Process inventory balance on June 30 was: The Samuelson Company uses a job-order...

    Samuelson's Work in Process inventory balance on June 30 was: The Samuelson Company uses a job-order cost system. The following data were recorded for June June 1 Added During June Work in Process Direct Direct Job Number Inventory Materials Labor 475 $1,000 $ 400 $ 200 476 $ 900 $ 600 $ 800 477 $ 800 $ 900 $1,400 478 $ 600 $1,100 $1,900 Overhead is charged to production at 70% of the direct materials cost. Jobs 475, 477, and...

  • PROBLEM 2-3 Prepare entries in a job order cost system and cost of goods manufactured schedule....

    PROBLEM 2-3 Prepare entries in a job order cost system and cost of goods manufactured schedule. Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2017, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $4,200 Manufacturing Overhead Applied $32,640 Work in Process Inventory $5,540 Manufacturing Overhead Incurred $31,650 Subsidiary data for Work in Process Inventory on June...

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

  • Stine Company uses a job order cost system. On May 1, the company has a balance...

    Stine Company uses a job order cost system. On May 1, the company has a balance in Work in Process Inventory of $3,500 and two jobs in process: Job No. 429 $2,000, and Job No. 430 $1,500. During May, a summary of source documents reveals the following. Job Number Materials Requisition Slips Labor Time Tickets 429 $2,500 $1,900 430 3,500 3,000 431 4,400 $10,400 7,600 $12,500 General use 800 1,200 $11,200 $13,700 Stine Company applies manufacturing overhead to jobs at...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT