Solution:
June 1st |
DM , DL and Overheads Added During June |
||||
Job Number |
Work in Process Inventory (per Job Cost Sheets) |
Direct Materials |
Direct Labor |
Overheads (60% of Direct Labor) |
Total Manufacturing Costs |
175 |
$1,800 |
$1,000 |
$400 |
$240 |
$3,440 |
176 |
$1,000 |
$1,500 |
$800 |
$480 |
$3,780 |
177 |
$600 |
$2,000 |
$1,200 |
$720 |
$4,520 |
178 |
$700 |
$1,500 |
$1,000 |
$600 |
$3,800 |
Jobs completed and transferred to finished goods during June = 175, 176, 177
Jobs delivered to the customer = 175
Jobs in FG inventory = 176, 177
FG Inventory as of June 30th = $3,780 + $ $4,520 = $8,300
Sales for the month of June = (Manufacturing Cost + 150% of Cost) of Job 175 = $3,440 + 150% of 3,440 = $8,600
Opening Work-in-Process = $1,800 + $1,000 + $600 + $700 = $4,100
Closing Work-in-Process (Job 178) = $3,800
Total Manufacturing Costs = $3,440 + $3,780 + $4,520 + $3,800 = $15,540
Closing Inventory = $8,300
Gross Profit = Sales + Closing Inventory + Closing Work-in-process – Manufacturing Costs – Opening Work-in-process = $8,600 + $8,300 + $3,800 - $15,540 - $4,100 = $1,060
Data for the next 4 questions: The Donaldson Company uses a job-order cost system. The following...
Question 13 points) Data for the next 2 questions: The Shaw Company uses a job-order cost system. Factory overhead is applied to jobs at the rate of 140% of direct labor cost. Jobs 475, 477, and 478 were completed during April and transferred to finished goods. Jobs 475 and 478 have been delivered to the customer. The following data were recorded for April: 100 Added During April Direct Direct Number Materials Labor $ 500 S 800 476 $ 700 $1,000...
Midterm 1 The Lee Company uses a job-order cost system. The following data were recorded for June: Job Number 235 236 237 June 1 Work in Process Inventory $2,500 $1,500 $1,000 $ 800 Added During June Direct Direct Materials Labor $ 600 S 400 S 800 $1,000 $1,200 $1,750 $1,500 $2,250 238 Overhead is charged to production at 80% of direct materials cost. Jobs 235, 237, and 238 were completed during June and transferred to finished goods. Jobs 235 and...
The Lee Company uses a job-order costing system. The following data were recorded for June:Added During June----JobNumberJune 1Work in ProcessInventory DirectMaterials DirectLabor235 $2,500 $600 $400236 $1,500 $800 $1,000237 $1,000 $1,200 $1,750238 $800 $1,500 $2,250Overhead is charged to production at 80% of direct materials cost. Jobs 235, 237, and 238 were completed during June and transferred to finished goods. Jobs 235 and238 have been delivered to customers.20. Lee Company's cost of goods sold for June wasA. $14,640.B. $15,520.C. $9,730.D. $10,170.Please SHOW...
Use below information for Questions 5 to 7: Company X uses a job cost system and applies overhead to production on the basis of direct labor cost. On January 1, 2018, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: DM of TL27,000, DL of TL11,600, and MOH of TL15,003. As of January 1, Job 49 had been completed at a cost of TL85,007 and was part of...
Company X uses a job cost system and applies overhead to production on the basis of direct labor cost. On January 1, 2018, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: DM of TL27,000, DL of TL11,600, and MOH of TL15,008. As of January 1, Job 49 had been completed at a cost of TL85,004 and was part of finished goods inventory. There was a TL13,500 balance...
The Blue Star Manufacturing Company uses a job order costing system and normal costing. It started operations in January 2014. Total production cost for Job A14 was $35,000. Job A14 was completed, but not sold as of the end of 2014. During 2014, the total production cost (DM + DL + OH) charged to B14 was $24,000. Job B14 was still unfinished at the end of 2014. The ending balance for Materials Inventory for 2014 was $6,000. At the end...
The Lee Corporation uses a job-order costing system. The following data were recorded for June: June 1 Added During June Job Number Work in Process Inventory Direct Materials Direct Labor 235 $3,150 $860 $595 236 $2,210 $1,260 $1,435 237 $1,585 $1,720 $2,530 238 $1,125 $2,410 $3,290 Overhead is charged to production at 90% of direct materials cost. Jobs 235, 237, and 238 were completed during June and transferred to finished goods. Jobs 235 and 238 have been delivered to customers....
TEST 1 Problem The Black Company uses a job order cost system. The following data pertains to the direct material and direct labor costs charged to production during the month of January: Job number 663 664 665 666 Direct Material $3,200 7,800 9,000 3.500 $23.500 Direct Labor $4,000 9,600 12,000 5,400 $31.000 Job 663 was in process at the beginning of January at which time it had incurred $2.500 of direct material costs and $3,000 of direct labor costs. Manufacturing...
The Healthy Heart Company uses a normal job-order costing system in its only production department. Overhead is applied to jobs by a plant-wide overhead rate based on direct labor hours. The first year of operation began on December 1, 2018. During the month of December 2018, Healthy Heart purchased direct materials with a total cost of $4,000. Of the $4,000, Healthy Heart uſed $500 on Job 100. Job 100 was the only job worked during the month of December 2018....
Job-Order Costing U-Design-It Furniture Company uses a job-order cost system. The company applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor hours. The estimated MOH was $144,000 for the year and the estimated direct labor hours were 18,000 hours. In March, Job #175 was completed. Direct materials totaled $7,000. Total labor costs were $6,000 at $20 per hour. At the end of the year, it was determined that the company worked 17,000 direct labor hours...