Question

Multiple Choice Question 67 Sunland Company’s high and low level of activity last year was 51000...

Multiple Choice Question 67

Sunland Company’s high and low level of activity last year was 51000 units of product produced in May and 12000 units produced in November. Machine maintenance costs were $161800 in May and $52600 in November. Using the high-low method, determine an estimate of total maintenance cost for a month in which production is expected to be 36000 units.

$142800
$115050
$119800
$136050
1 0
Add a comment Improve this question Transcribed image text
Answer #1

$119800

Step-1:Calculation of variable cost per unit
Variable cost per unit = (a-b)/(x-y) Where,
= (161800-52600)/(51000-12000) a = Maintenance cost at highest level = $       1,61,800
= $       2.80 b = Maintenance cost at lowest level = $           52,600
x = High level of activity =               51,000
y = Low level of activity =               12,000
Step-2:Calculation of fixed cost
Level of activity a               51,000           12,000
Total costs b $       1,61,800 $       52,600
Variable cost per unit c $               2.80 $            2.80
Total Variable cost d=a*c $       1,42,800 $       33,600
Fixed Cost e=b-d $           19,000 $       19,000
Note:
Fixed cost is same at all level of activity.
Step-3:Calculation of total maintenance cost at 36000 units
Level of activity a 36000
Variable cost per unit b $               2.80
Total variable cost c=a*b $       1,00,800
Total fixed Cost d $           19,000
Total maintenance cost e=c+d $       1,19,800
Add a comment
Know the answer?
Add Answer to:
Multiple Choice Question 67 Sunland Company’s high and low level of activity last year was 51000...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Crane Company’s high and low level of activity last year was 70000 units of product produced...

    Crane Company’s high and low level of activity last year was 70000 units of product produced in May and 24000 units produced in November. Machine maintenance costs were $167000 in May and $65800 in November. Using the high-low method, determine an estimate of total maintenance cost for a month in which production is expected to be 54000 units. $146150 $131800 $128550 $154000

  • Gribble Company's high and low level of activity last year was 60,000 units of product produced in May and 20,00...

    Gribble Company's high and low level of activity last year was 60,000 units of product produced in May and 20,000 units produced in November. Machine maintenance costs were $156,000 in May and $60,000 in November. Using the high-low method, determine an estimate of total maintenance cost for a month in which production is expected to be 45,000 units. a. $135,000 b. $144,000 c. $117,000 d. $120,000 D10: Rin AP Mam MinAACSR Anal AICPA RR Industarter Pannen AICPA FN: Mement AICPA...

  • Question 5 --/1 View Policies Current Attempt in Progress Waterway Industries's high and low level of...

    Question 5 --/1 View Policies Current Attempt in Progress Waterway Industries's high and low level of activity last year was 65000 units of product produced in May and 10000 units produced in November. Machine maintenance costs were $212000 in May and $47000 in November. Using the high-low method, determine an estimate of total maintenance cost for a month in which production is expected to be 48000 units. O $156750 O $195000 O $182250 O $161000

  • Maintenance Cost Assume a company provided the following information: Patient- Days High activity level 3,500 (September)...

    Maintenance Cost Assume a company provided the following information: Patient- Days High activity level 3,500 (September) Low activity level (May) 2,500 $ 10,400 $ 9,200 Using the high-low method, what would be the estimated maintenance cost in a month with 2,650 patient-days? Multiple Choice $8,372 $9,560 $6,180 $9,380

  • Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of...

    Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 52,000 $ 207,440 May 42,000 $ 181,740 June 62,000 $ 233,140 July 72,000 $ 258,840 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) $ 63,000 Supervisory salaries (fixed) 56,000 Maintenance (mixed) 62,740...

  • Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of...

    Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 46,000 $ 179,200 May 36,000 $ 156,700 June 56,000 $ 201,700 July 66,000 $ 224,200 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 36,000 machine-hour level of activity is: Utilities (variable) $ 43,200 Supervisory salaries (fixed) 61,000 Maintenance (mixed) 52,500...

  • The following information is available for a company’s maintenance cost over the last seven months. Month...

    The following information is available for a company’s maintenance cost over the last seven months. Month Units Produced Maintenance Cost June 110 $ 5,320 July 170 7,300 August 130 5,980 September 160 6,970 October 220 8,950 November 250 9,940 December 70 4,000 Using the high-low method, estimate both the fixed and variable components of its maintenance cost.

  • -Page Break Ex. 174 Henderson Farms reports the following results for the month of November: Sales (10,000 units...

    -Page Break Ex. 174 Henderson Farms reports the following results for the month of November: Sales (10,000 units) $600,000 Variable costs 420,000 Contribution margin 180,000 Fixed costs 110,000 Net income $ 70.000 Management is considering the following independent courses of action to increase net income. 1. Increase selling price by 5% with no change in total variable costs. 2. Reduce variable costs to 66 % of sales. 3. Reduce fixed costs by $10,000. Instructions If maximizing net income is the...

  • ova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...

    ova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 49,000 $ 199,830 May 39,000 $ 173,130 June 59,000 $ 226,530 July 69,000 $ 253,230 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000 machine-hour level of activity is: Utilities (variable) $ 58,500 Supervisory salaries (fixed) 55,000 Maintenance (mixed) 59,630 Total overhead cost $ 173,130 Nova Company’s...

  • Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...

    Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 47,000 $ 192,050 May 37,000 $ 168,550 June 57,000 $ 215,550 July 67,000 $ 239,050 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: Utilities (variable) $ 48,100 Supervisory salaries (fixed) 66,000 Maintenance (mixed) 54,450 Total overhead cost $ 168,550 Nova Company’s...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT